Information based on query as of Thursday, May 2, 2024.
Permit Information
Permit NumberBLD18-03200
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 12555 W FRANKLIN RD
Project NameFranklin Commerce Ctr - Bldg 1
Customer Number 
ePlanReviewYes
Description
(FRANKLIN COMMERCE CENTER – BUILDING #1 (A) - SHELL) (DRH18-00102) (DRH18-00249) The fire sprinkler system is used for building area increase and for fire area. To construct a new one story, 34,754 square foot shell building (34,973 square feet projected roof area). This is a shell only permit. This permit is not intended to establish a Certificate of Occupancy for any tenant. Future occupancies could include B, M, S-1, and F-1. Future tenants are required to apply for their own permit to establish occupancy. Work is to include concrete continuous footings, concrete tilt-up exterior wall panels, interior concrete spot footings, steel columns with steel base plates and anchors, concrete slab on grade, steel open-web roof girders, steel open-web roof joists, steel roof decking, rigid insulation installed on top or the roof deck with a single ply membrane roof covering, primary and secondary roof drains, skylights with fall proof cages, roll-up exterior doors, exterior man doors, exterior storefront windows and doors, exterior steel stairways with steel landings, two trash enclosures constructed of concrete tilt-up panel with steel gates, a 50 foot wide concrete apron at the loading dock area, a 1-hr fire riser room with a door directly to the outside, and steel shade awnings at storefront windows and doors. Minimal heating and lighting will be provided. Special Inspection is required for soils, concrete, steel (including welding), and for post-installed anchors in hardened concrete. Deferred submittals include the design for open web steel girders and open web steel roof joists. Concrete retaining walls will also be constructed on site. Future roof top HVAC units weighing 750 pounds each were anticipated and roof curbs were provided. The gas unit heaters weigh 172 pounds each. Separate racking permit are required for racks over 8 feet tall. All work shall be done without impacting the integrity of the existing canal and in accordance with canal company recommendations. The structural integrity of the canal is required to be maintained. A safe dispersal area is required on the South side of this building at least 50 feet from the building. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. Service sinks, toilet rooms, and perhaps drinking fountains for each tenant space will be required under future tenant improvement permits. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Meeting  1/29/2020 DONE
final values turned in 1-29-20
Third Notice 12/1/201912/30/2019 DONE
mailed 1-1-20
Second Notice 11/8/201911/26/2019 DONE
mailed 12-2-19
First Notice10/15/201910/15/201910/29/2019 DONE
DetailsMike Jordan
mailed 11-1
PubWorks Occupancy Approval10/16/201910/16/201910/16/2019 DONE
DetailsTiffany Lowery
BLD-Final10/15/201910/15/201910/15/2019PPASS
DetailsMike Jordan
TONY Phone #: ###-####
DOC - Permit Finaled10/15/201910/15/201910/15/2019PPASS
DetailsMike Jordan
Received special inspection final letter. Ok for final.
Letter of compliance/Occupancy  10/15/2019 DONE
BLD-Final10/11/201910/14/201910/14/2019ANR
DetailsMike Jordan
tONY Phone #: ###-####. Needs public works final.
BLD-Final9/26/20199/27/20199/27/2019APASS
DetailsTell Riley
Tony Phone #: ###-####//final complete per plans//pending all special inspections are complete and final//
FIRE-Final Inspection9/25/20199/26/20199/26/2019APASS
DetailsTroy Cobbley
Life safety passed. Tony Phone #: ###-####
FIRE-Final Inspection9/19/20199/19/20199/19/2019PFAIL
DetailsTroy Cobbley
Provide final inspections for the project related fire alarm permits and fire sprinkler permits. Need fire dept access signage as discussed. Tony Phone #: ###-####
Zoning Approval9/3/20199/3/20199/3/2019 PASS
DetailsJosh Wilson
BLD-Framing/Rough-in7/29/20197/29/20197/29/2019PPASS
DetailsMike Jordan
Tony Phone #: ###-####. Interior steel stud framed walls for riser and electrical rooms.
BLD-Framing/Rough-in7/24/20197/25/20197/25/2019ANR
DetailsTell Riley
Anthony Phone #: ###-####//electrical room and fire riser room framing//not ready need fire inspection and electrical inspection prior to framing ///
BLD-Concrete3/28/20193/29/20193/29/2019APEND
DetailsDave Hannah
concrete panels- Gene Phone #: ###-#### ok after spec inspection sign offs
BLD-Foundation3/12/20193/12/20193/12/2019PPASS
DetailsMike Jordan
inpection for slab on grade-Jean Phone #: ###-####
BLD-Concrete2/28/20193/1/20193/1/2019APART
DetailsMike Jordan
rebar- Gene Phone #: ###-####. Remaining exterior east footing. Work in progress, ok to place concrete pending special inspection.
BLD-Foundation2/21/20192/22/20192/22/2019ADEFR
DetailsMike Jordan
rebar-Gene Phone #: ###-####
BLD-Foundation2/19/20192/19/20192/19/2019PPART
DetailsMike Jordan
Rebar // Jean Phone #: ###-####
BLD-Conference2/11/20192/12/20192/12/2019ADONE
DetailsMike Jordan
Gene Phone #: ###-####
BLD-Concrete2/8/20192/11/20192/11/2019APART
DetailsMike Jordan
rebar- gene Phone #: ###-####
Issue PAID IN FULL permit  1/14/2019 DONE
Inspection Record Card- Bld  1/14/2019 DONE
OVERRIDE  11/13/2018  
Permit Ready to Issue  11/13/2018 DONE
MET
NEED
GC FORM
REVISED VALUE
ACHD
Plan assigned to (CJW)9/13/20189/13/201811/10/2018 PASS
DetailsCarl Westfall
(2nd done) 10/15/18 (waiting for fire) (new - 25 days) (ePlan - 72 sheets) Franklin Commerce Bldg. #1
PLANS/APPL TAKEN TO FRONT DESK  11/10/2018 DONE
Routing Off Site - STRUCTURAL11/2/2018 11/9/2018 PASS
DetailsCarl Westfall
Chris Merrill (Stapley)
Routing - FIRE11/2/201811/2/201811/5/2018 PASS
DetailsErika Akin
Attached comments to case and redlined plan sheet C2.3
Routing PW Drainage11/2/2018 11/5/2018 PASS
DetailsBrian Murphy
Routing - PLAN CHECK11/1/2018 11/2/2018 PASS
DetailsCarl Westfall
Remember to upload the final plan review report
Plan resubmittals received  11/1/2018 DONE
Route to Impact Fee Review10/31/201811/3/201810/31/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  10/31/2018 DONE
Plan resubmittals requested  10/31/2018 DONE
Routing - FIRE9/13/20189/13/201810/30/2018 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing - PLAN CHECK9/13/2018 10/27/2018 FAIL
DetailsCarl Westfall
Revised drawings required
Routing Off Site - STRUCTURAL9/13/2018 9/27/2018 FAIL
DetailsCarl Westfall
Chris Merrill (Stapley)
Routing PW Environmental9/13/2018 9/20/2018 PASS
DetailsRick Christenson
Routing PW Drainage9/17/2018 9/17/2018 FAIL
need perc test
Routing - Design Review9/13/2018 9/17/2018 PASS
DetailsAndrea Tuning
DRH18-00249, DRH18-00102 Andrea Tuning
Routing - MECHANICAL9/13/2018 9/17/2018 PASS
DetailsTroy James
Mechanical ventilation shall be addressed at future tenant improvements.
Routing PW Sewer Design9/13/2018 9/14/2018 PASS
DetailsDeAnn Brown
Routing PW Solid Waste9/13/2018 9/14/2018 PASS
DetailsEvan Carpenter
Routing PW Street Lights9/13/2018 9/13/2018 PASS
DetailsTom Marshall
No review required
Routing - PLUMBING9/13/2018 9/13/2018 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - PLANNING9/13/2018 9/13/2018 PASS
DetailsSusan Riggs
No review required
Routing - Addressing9/13/2018 9/13/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/13/2018 9/13/2018 PASS
DetailsMorgan Webb
SHELL ONLY, ASSESSMENT PREVIOUSLY PAID.
Routing - Erosion and Sediment9/13/2018 9/13/2018 PASS
DetailsMichael Zawacki
Site prep inspection required.
Plans ACCEPTED BY PLAN TECH  9/13/2018  
Recd Pcfee & Taken To Pln CK  9/13/2018 DONE
Intake Approval  9/11/2018 PASS
Intake Approval  9/5/2018 FAIL
DetailsBrian McGowan
Please provide the following information or corrections for the Prescreen Approval:
1. Drawings DWG_EC-101 and DWG_EC-501 need to be the same sheet size as the others or a minimum 18"x24". They appear to not be complete, neither sheet is stamped and signed.
2. Please show Fire Hydrant locations on the Site Plan.
3. Sheet M-1 will not open. Please re-upload. Something prevents it from opening and shuts down our program.
4. Cannot locate Sheet O.2 for Building Envelope and COMcheck.
5. Several Sheets have notes where the City Stamp will need to be located and will print over your notes. Please relocate notes as needed. See Sheets C 5.1 S 1.1, S 1.2, S 2.1, S 2.1, S 9.1
Application received  8/30/2018 DONE
Application submitted via PDS Online on Aug 30 2018 3:45PM