Meeting | | | 1/29/2020 | | DONE |
|
|
|
final values turned in 1-29-20
|
Third Notice | | 12/1/2019 | 12/30/2019 | | DONE |
|
|
|
mailed 1-1-20
|
Second Notice | | 11/8/2019 | 11/26/2019 | | DONE |
|
|
|
mailed 12-2-19
|
First Notice | 10/15/2019 | 10/15/2019 | 10/29/2019 | | DONE |
Mike Jordan
|
|
|
mailed 11-1
|
PubWorks Occupancy Approval | 10/16/2019 | 10/16/2019 | 10/16/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Mike Jordan
|
|
|
TONY Phone #: ###-####
|
DOC - Permit Finaled | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Mike Jordan
|
|
|
Received special inspection final letter. Ok for final.
|
Letter of compliance/Occupancy | | | 10/15/2019 | | DONE |
|
|
|
|
BLD-Final | 10/11/2019 | 10/14/2019 | 10/14/2019 | A | NR |
Mike Jordan
|
|
|
tONY Phone #: ###-####. Needs public works final.
|
BLD-Final | 9/26/2019 | 9/27/2019 | 9/27/2019 | A | PASS |
Tell Riley
|
|
|
Tony Phone #: ###-####//final complete per plans//pending all special inspections are complete and final//
|
FIRE-Final Inspection | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Tony Phone #: ###-####
|
FIRE-Final Inspection | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide final inspections for the project related fire alarm permits and fire sprinkler permits. Need fire dept access signage as discussed. Tony Phone #: ###-####
|
Zoning Approval | 9/3/2019 | 9/3/2019 | 9/3/2019 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Interior steel stud framed walls for riser and electrical rooms.
|
BLD-Framing/Rough-in | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | NR |
Tell Riley
|
|
|
Anthony Phone #: ###-####//electrical room and fire riser room framing//not ready need fire inspection and electrical inspection prior to framing ///
|
BLD-Concrete | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PEND |
Dave Hannah
|
|
|
concrete panels- Gene Phone #: ###-#### ok after spec inspection sign offs
|
BLD-Foundation | 3/12/2019 | 3/12/2019 | 3/12/2019 | P | PASS |
Mike Jordan
|
|
|
inpection for slab on grade-Jean Phone #: ###-####
|
BLD-Concrete | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Mike Jordan
|
|
|
rebar- Gene Phone #: ###-####. Remaining exterior east footing. Work in progress, ok to place concrete pending special inspection.
|
BLD-Foundation | 2/21/2019 | 2/22/2019 | 2/22/2019 | A | DEFR |
Mike Jordan
|
|
|
rebar-Gene Phone #: ###-####
|
BLD-Foundation | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | PART |
Mike Jordan
|
|
|
Rebar // Jean Phone #: ###-####
|
BLD-Conference | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | DONE |
Mike Jordan
|
|
|
Gene Phone #: ###-####
|
BLD-Concrete | 2/8/2019 | 2/11/2019 | 2/11/2019 | A | PART |
Mike Jordan
|
|
|
rebar- gene Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/14/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/13/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 11/13/2018 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
ACHD
|
Plan assigned to (CJW) | 9/13/2018 | 9/13/2018 | 11/10/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) 10/15/18 (waiting for fire) (new - 25 days) (ePlan - 72 sheets) Franklin Commerce Bldg. #1
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/2/2018 | | 11/9/2018 | | PASS |
Carl Westfall
|
|
|
Chris Merrill (Stapley)
|
Routing - FIRE | 11/2/2018 | 11/2/2018 | 11/5/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case and redlined plan sheet C2.3
|
Routing PW Drainage | 11/2/2018 | | 11/5/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 11/1/2018 | | 11/2/2018 | | PASS |
Carl Westfall
|
|
|
Remember to upload the final plan review report
|
Plan resubmittals received | | | 11/1/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/31/2018 | 11/3/2018 | 10/31/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/31/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/31/2018 | | DONE |
|
|
|
|
Routing - FIRE | 9/13/2018 | 9/13/2018 | 10/30/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - PLAN CHECK | 9/13/2018 | | 10/27/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing Off Site - STRUCTURAL | 9/13/2018 | | 9/27/2018 | | FAIL |
Carl Westfall
|
|
|
Chris Merrill (Stapley)
|
Routing PW Environmental | 9/13/2018 | | 9/20/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 9/17/2018 | | 9/17/2018 | | FAIL |
|
|
|
need perc test
|
Routing - Design Review | 9/13/2018 | | 9/17/2018 | | PASS |
Andrea Tuning
|
|
|
DRH18-00249, DRH18-00102 Andrea Tuning
|
Routing - MECHANICAL | 9/13/2018 | | 9/17/2018 | | PASS |
Troy James
|
|
|
Mechanical ventilation shall be addressed at future tenant improvements.
|
Routing PW Sewer Design | 9/13/2018 | | 9/14/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 9/13/2018 | | 9/14/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 9/13/2018 | | 9/13/2018 | | PASS |
Tom Marshall
|
|
|
No review required
|
Routing - PLUMBING | 9/13/2018 | | 9/13/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 9/13/2018 | | 9/13/2018 | | PASS |
Susan Riggs
|
|
|
No review required
|
Routing - Addressing | 9/13/2018 | | 9/13/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/13/2018 | | 9/13/2018 | | PASS |
Morgan Webb
|
|
|
SHELL ONLY, ASSESSMENT PREVIOUSLY PAID.
|
Routing - Erosion and Sediment | 9/13/2018 | | 9/13/2018 | | PASS |
Michael Zawacki
|
|
|
Site prep inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/13/2018 | | DONE |
|
|
|
|
Intake Approval | | | 9/11/2018 | | PASS |
|
|
|
|
Intake Approval | | | 9/5/2018 | | FAIL |
Brian McGowan
|
|
|
Please provide the following information or corrections for the Prescreen Approval:
1. Drawings DWG_EC-101 and DWG_EC-501 need to be the same sheet size as the others or a minimum 18"x24". They appear to not be complete, neither sheet is stamped and signed.
2. Please show Fire Hydrant locations on the Site Plan.
3. Sheet M-1 will not open. Please re-upload. Something prevents it from opening and shuts down our program.
4. Cannot locate Sheet O.2 for Building Envelope and COMcheck.
5. Several Sheets have notes where the City Stamp will need to be located and will print over your notes. Please relocate notes as needed. See Sheets C 5.1 S 1.1, S 1.2, S 2.1, S 2.1, S 9.1
|
Application received | | | 8/30/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 30 2018 3:45PM
|