Permit Information
Permit NumberBLD19-02464
StatusIssued
Name DAVE EVANS CONSTRUCTION
Site Address 101 S ALLUMBAUGH WAY
Project NameChildren's Therapy Place
Customer Number 
ePlanReviewYes
Description
(CHILDREN’S THERAPY PLACE – NEW TWO STORY BUILDING) (DRH19-00094) (12-31-19 PLAN MODIFICATION TO INSTALL AN ELECTRIC OVEN WITH A COOKTOP AND A STANDARD DOMESTIC HOOD WITHIN THE 1ST STORY BREAKROOM. COOKING OPERATIONS THAT CREATE GREASE LADEN VAPORS ARE NOT ALLOWED. A WORK SURFACE ACCESSIBLE TO THE DISABLED LOCATED NEXT TO THE RANGE WITH KNEE AND TOE CLEARANCE FOR A FRONT APPROACH WILL BE PROVIDED. KNEE AND TOE CLEARANCE FOR A FRONT APPROACH TO THE BREAKROOM SINK WILL ALSO BE PROVIDED. CLARIFICATION CHANGES WERE ALSO MADE TO THE DRAWINGS TO INCLUDE TEMPERED GLASS NEAR THE SWIMMING POOL, DECK DRAIN AT THE SWIMMING POOL, ETC.) The fire sprinkler system is used for fire flow and to substitute for 1-hr corridors. To construct a two story building having a total floor area of about 18,281 square feet (9,866 square feet 1st story and 8,415 square feet 2nd story). In addition, the 2nd story will have a 902 square foot occupied roof with a seasonal membrane shade structure above it. Work is to include concrete footings; concrete stem walls; a concrete elevator pit; a concrete pool pit; concrete slabs on grade with slabs thickened below interior bearing walls; wood stud bearing walls and shear walls; steel columns; steel beam; wood floor trusses with wood sheathing and gypcrete topping; wood roof trusses with wood structural panel decking, standing seam metal roofing, and/or single-ply membrane roof covering over R-35 continuous rigid insulation on top of the roof deck; adjustable pedestal concrete tile pavers above the roof covering at the occupied roof; exterior wood stud walls with wood structural panels and furred out sections with metal panel siding, or cement stucco, or manufactured stone finishes; exterior storefront windows; exterior storefront doors; steel awnings; interior walls; four multi-user toilet rooms accessible to the disabled; four single-user toilet rooms accessible to the disabled; two interior stairways; interior doors; interior windows; horizontal sliding partitions; a therapy pool; millwork; and finishes. Special Inspection is required for soils and for steel (including bolting and welding). Engineered trusses are a deferred submittal item. A masonry trash enclosure with steel gates will also be constructed on site. A 4 foot high non-climbable fence will be constructed around a playground. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. A separate permit is required for the therapy pool. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/13/20208/13/20208/13/2020PPART
DetailsMike Jordan
Ed *screened Phone #: ###-####. OK for temp occ. once mech. passes final.
Zoning Approval8/13/20208/13/20208/13/2020 PASS
DetailsKatelyn Menuge
FIRE-Final Inspection8/4/20208/6/20208/6/2020APART
DetailsTroy Cobbley
A temp for life safety until the project related fire alarm permit has been finaled.

Ed- */Screened*/ Phone #: ###-#### 7am inspection
FIRE-Final Inspection7/29/20207/30/20207/30/2020PFAIL
DetailsTroy Cobbley
Need the project related fire alarm permit finaled, need signs for fire dept access at the two entrances, need signage on electrical room door, need to test the door mags on main entrance.

Screened- ED Phone #: ###-####
BLD-Ceiling Grid Inspection6/18/20206/19/20206/19/2020APASS
DetailsMike Jordan
screened // Ed Phone #: ###-####. 1st. floor ok.
BLD-Ceiling Grid Inspection6/15/20206/15/20206/15/2020PPASS
DetailsMike Jordan
Ed Phone #: ###-####. 2nd. floor grid and east stairwell only.
BLD-Ceiling Grid Inspection5/15/20205/15/20205/15/2020PPASS
DetailsMike Jordan
Ed Phone #: ###-####. HArdlid in pool room ok.
BLD-Energy code compliance5/15/20205/15/20205/15/2020PPASS
DetailsMike Jordan
Ed Phone #: ###-####. 2nd floor above ceiling ok.
BLD-Energy code compliance5/12/20205/12/20205/12/2020PCANC
DetailsMike Jordan
Ed *screened* Phone #: ###-####
BLD-Energy code compliance5/6/20205/7/20205/7/2020PPASS
DetailsMike Jordan
Ed *screened* Phone #: ###-####. Pool room, north half of first floor.
BLD-Energy code compliance5/1/20205/4/20205/4/2020PCANC
DetailsMike Jordan
screened // Ed Phone #: ###-####
BLD-Energy code compliance5/4/20205/4/20205/4/2020PPASS
DetailsMike Jordan
screened // Ed Phone #: ###-####. 1st. floor south half.
BLD-Energy code compliance4/28/20204/29/20204/29/2020APASS
DetailsMike Jordan
Ed *cleared* Phone #: ###-####. 2nd. floor North half.
BLD-Energy code compliance4/23/20204/24/20204/24/2020APASS
DetailsMike Jordan
screened // Ed Phone #: ###-####. 2nd floor, south half. fire blocking, 1st and 2nd. floors.
BLD-Framing/Rough-in4/14/20204/14/20204/14/2020PPASS
DetailsMike Jordan
Ed **Cleared** Phone #: ###-####. 1st and 2nd. floor.
BLD-Framing/Rough-in4/9/20204/10/20204/10/2020APART
DetailsMike Jordan
screened // Ed Phone #: ###-####. Needs to complete airseal. ok to one side.2nd. floor.
BLD-Framing/Rough-in4/1/20204/2/20204/2/2020APASS
DetailsMike Jordan
Ed Phone #: ###-####. Ok to insulate roof deck and 2nd floor were discussed. All missing holdowns have been installed.
FIRE-Conference3/13/20203/13/20203/13/2020PDONE
DetailsTroy Cobbley
Ed and I discussed the combustible concealed pockets.

Ed Phone #: ###-####
BLD-Other3/10/20203/11/20203/11/2020APASS
DetailsMike Jordan
2 hour wall for elevator shaft inspection - Ed Phone #: ###-####. Per the architect, the 2hr. assembly on plans is in correct and has provided the correct assembly.
BLD-Wall Bracing3/10/20203/11/20203/11/2020APASS
DetailsMike Jordan
Ed Phone #: ###-####. All nailing on interior and exterior walls ok. All floor to floor straps ok except at pool area and at east interior stairs.
BLD-Framing/Rough-in3/6/20203/6/20203/6/2020PPART
DetailsMike Jordan
Ed Phone #: ###-####. @hr. shaft for elevator. Need to verify type of sheet rock being used. GA file notes 1/2" type C, contractor has used 5/8 type X.
BLD-Wall Bracing3/4/20203/5/20203/5/2020APART
DetailsMike Jordan
SHEAR // Ed Phone #: ###-####. Exterior and interior shear wall nailing. Needs to install all floor to floor straps, and fasten missed areas. Also received RFI ok an additional 7/16 OSB on high roof and noting 7/16 over pool area is ok due to 12" oc roof truss spacing.
BLD-Framing/Rough-in2/28/20203/2/20203/2/2020APASS
DetailsMike Jordan
roof nailing // Ed Phone #: ###-####. Main roof structure.
BLD-Wall Bracing2/20/20202/21/20202/21/2020APART
DetailsMike Jordan
Ed Phone #: ###-####. East exterior wall, 1st floor. Portion were meter pack is to be set only ok.
BLD-Foundation1/3/20201/3/20201/3/2020PPASS
DetailsMike Jordan
Ben Phone #: ###-####. remainder of interior thickend footings ok.
Print Occupancy Form  1/2/2020 DONE
CHANGE STATUS TO (ISS)  1/2/2020 DONE
OVERRIDE  12/31/2019  
Plan assigned to (CJW)12/16/201912/16/201912/31/2019 PASS
DetailsCarl Westfall
plan mod - Children's Therapy Place (routed to staff)
Plan Reviewer's activity  12/31/2019 PASS
Plan mod review approved
Permit Ready to Issue  12/31/2019 DONE
**PLAN MOD - DO NOT RE-ISSUE**
BLD-Foundation12/24/201912/26/201912/26/2019PPART
DetailsDave Hannah
Ben Phone #: ###-#### int ftgs ok to pour
Routing - FIRE12/19/201912/19/201912/26/2019 PASS
DetailsErika Akin
Hood above new range in first floor breakroom. Per policy dated 11-26-2019, fire suppression system for standard domestic hood not required.
BLD-Foundation12/23/201912/24/201912/24/2019AFAIL
DetailsMike Jordan
Ben Phone #: ###-####
BLD-Foundation12/20/201912/23/201912/23/2019ANR
DetailsMike Jordan
inspection not in plan mod location // Ben Phone #: ###-####
Routing Off Site - STRUCTURAL12/19/2019 12/23/2019 PASS
DetailsCarl Westfall
Jan Welch (Stapley) Detail at truss bearing changed
Routing PW Sewer Rating12/19/2019 12/20/2019 PASS
DetailsMorgan Webb
Hose bib moved at swimming pool
Plan Modification Accepted  12/18/2019 DONE
Task in ePlanReview received
Routing - PLAN CHECK12/18/2019 12/18/2019 PASS
DetailsCarl Westfall
1st plan mod approved
BLD-Foundation12/15/201912/16/201912/16/2019APASS
DetailsMike Jordan
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Elevator pit walls and walls around swimming pool ok.
Plan Modification Accepted  12/16/2019 DONE
plan mod of - A2.0, A4.0, A6.1, A7.O, S0.00, S1.01, S1.02, S3.11, M2.1, M3.0, P2.1,P2.3, P3.0E2,1P, E3.0
BLD-Foundation12/9/201912/9/201912/9/2019PPASS
DetailsBrandon Shaw
Perimeter foundation...
BLD-Footing12/1/201912/2/201912/2/2019PPASS
DetailsMike Jordan
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru. Elevator pit, step footings and footings at pool ok.
BLD-Footing11/26/201911/27/201911/27/2019PPASS
DetailsMike Jordan
Phone #: 2086971241 >> Inspection requested via mobile web by Heron . Perimeter footings only, excluding step down areas by pool, pool footings and elevator pit.
BLD-Footing11/25/201911/26/201911/26/2019PNR
DetailsMike Jordan
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
BLD-Footing11/24/201911/25/201911/25/2019PCANC
DetailsMike Jordan
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru. Cancelled by contractor via phone call.
BLD-Footing11/22/201911/22/201911/22/2019PCANC
DetailsMike Jordan
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Friday, November 22, 2019.
Issue PAID IN FULL permit  10/24/2019 DONE
Print Occupancy Form  10/24/2019 DONE
OVERRIDE  10/18/2019  
Permit Ready to Issue  10/18/2019 DONE
MET
NEED
RP
GC FORM
REVISED VALUE
Plan assigned to (CJW)7/16/20198/26/201910/17/2019 PASS
DetailsCarl Westfall
(1st done) 08/19/19 (New Building - 25 days) (eplan - 74 sheets) Children's Therapy Place (routed to staff)
PLANS/APPL TAKEN TO FRONT DESK  10/17/2019 DONE
Routing - PLAN CHECK10/15/2019 10/16/2019 PASS
DetailsCarl Westfall
Routed resubmittal
Routing PW Street Lights10/16/2019 10/16/2019 PASS
DetailsTom Marshall
Plan resubmittals received  10/15/2019 DONE
Routing Off Site - STRUCTURAL10/7/2019 10/14/2019 PASS
DetailsCarl Westfall
Jan Welch (Stapley)
Plan resubmittals requested  10/14/2019 DONE
Routing PW Street Lights10/7/2019 10/8/2019 FAIL
DetailsTom Marshall
Routing - PLAN CHECK10/4/2019 10/7/2019 PASS
DetailsCarl Westfall
Pending structural
Plan resubmittals received  10/4/2019 DONE
Plan resubmittals requested  9/24/2019 DONE
Routing - FIRE9/16/20199/16/20199/23/2019 PASS
DetailsErika Akin
Attached comments to case
Routing Off Site - STRUCTURAL9/16/2019 9/20/2019 FAIL
DetailsCarl Westfall
Jan Welch (Stapley)
Routing PW Street Lights9/16/2019 9/19/2019 FAIL
DetailsTom Marshall
Routing - Design Review9/16/2019 9/18/2019 PASS
DetailsKatelyn Menuge
Routing - MECHANICAL9/16/2019 9/18/2019 PASS
DetailsTroy James
Commissioning for mechanical is not required, sensible load for cooling is under 600,000 btu's.
Routing - PLAN CHECK9/13/2019 9/16/2019 PASS
DetailsCarl Westfall
Pending structural
Routing PW Sewer Rating9/16/2019 9/16/2019 PASS
DetailsMorgan Webb
New shower added
Plan resubmittals received  9/13/2019 DONE
Route to Impact Fee Review9/3/20199/6/20199/4/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Routing - PLAN CHECK7/16/2019 9/3/2019 FAIL
DetailsCarl Westfall
1st review completed  9/3/2019 DONE
Plan resubmittals requested  9/3/2019 DONE
Routing - FIRE7/16/20197/18/20198/26/2019 FAIL
DetailsErika Akin
Attached comments to case and emailed architect
Routing Off Site - STRUCTURAL7/18/2019 7/30/2019 FAIL
DetailsCarl Westfall
Jan Welch (Stapley)
Routing - MECHANICAL7/16/2019 7/24/2019 FAIL
DetailsTroy James
Need commissioning form uploaded.
Routing PW Drainage7/18/2019 7/23/2019 PASS
DetailsBrian Murphy
Routing PW Environmental7/18/2019 7/22/2019 PASS
DetailsRick Christenson
Routing PW Street Lights7/18/2019 7/19/2019 FAIL
DetailsTom Marshall
Routing - Addressing7/16/2019 7/19/2019 PASS
DetailsDoug Chausow
Routing - Design Review7/16/2019 7/19/2019 FAIL
DetailsKatelyn Menuge
See changemarks. Also need updated easement agreement with parcel to south to allow use of the private drive along the south of the site and their written approval to construct sidewalk on their property with an affidavit of legal interest form.
Routing - PLUMBING7/16/2019 7/18/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - PLANNING7/16/2019 7/18/2019 PASS
DetailsDavid Moser
Routing - PUBLIC WORKS7/16/2019 7/18/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment7/16/2019 7/18/2019 PASS
DetailsMichael Zawacki
RP needed. Site prep inspection required.
Routing PW Solid Waste7/18/2019 7/18/2019 PASS
DetailsEvan Carpenter
Intake Approval  7/16/2019  
DetailsJoe Bruce
Application received  7/2/2019 DONE
Application submitted via PDS Online on Jul 2 2019 3:14PM