Third Notice | | 5/12/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Second Notice | | 4/13/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
First Notice | | 4/2/2020 | 4/3/2020 | | DONE |
|
|
|
mailed 4-6-2020
|
Permanent Occupancy | | | 3/23/2020 | | DONE |
|
|
|
|
BLD-Final | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | PASS |
Mike Jordan
|
|
|
nate Phone #: ###-####. Occupant load sign posted and seating installed. Ok for perm occ.
|
CHANGE STATUS TO (TMP) | | | 3/19/2020 | | DONE |
|
|
|
Permit not supposed to be finaled needs a pass not part on bld final
|
FIRE-Final Inspection | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
Temporary Occupancy | 2/27/2020 | 5/27/2020 | 2/27/2020 | | DONE |
Brittany Hill
|
|
|
|
BLD-Final | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | PART |
Mike Jordan
|
|
|
Temp Occupancy Phone #: ###-#### Inspection requested via web by Nate Carriveau. Ok for temp occ. Needs to post max of 40 occupant load sign in room 138 and have fixed seating installed.
|
FIRE-Final Inspection | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PART |
Troy Cobbley
|
|
|
A temporary for life safety is being given for 90 days. A final life safety can be given when the project related fire alarm permit is finaled.
Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
FIRE-Final Inspection | 2/24/2020 | 2/24/2020 | 2/24/2020 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the project related fire alarm permit is finaled.
Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
FIRE-Final Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled. Need the two exit signs modified as discussed. Need suite number posted. All other items appear ok. Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
BLD-Ceiling Grid Inspection | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
BLD-Ceiling Grid Inspection | 1/29/2020 | 1/30/2020 | 1/30/2020 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Carriveau need mains supported max 8 inches both ends of mains/ ok to flood sm rooms and primtors ajsent to mains.
|
BLD-Ceiling Grid Inspection | 1/23/2020 | 1/24/2020 | 1/24/2020 | A | PASS |
Mike Jordan
|
|
|
West half of building Phone #: ###-#### Inspection requested via web by Nate Carriveau
|
BLD-Framing/Rough-in | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | FAIL |
Mike Jordan
|
|
|
Soffit inspection to cover Phone #: ###-#### Inspection requested via web by Nate Carriveau. Soffits to be supported from rtop chord or pan decking, or provide engineering showing bottom chords of joist can support additional loads.
|
BLD-Framing/Rough-in | 12/12/2019 | 12/13/2019 | 12/13/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Nate Carriveau. Remainder of interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Mike Jordan
|
|
|
Partial inspection for West side of building. Phone #: ###-#### Inspection requested via web by Nate Carriveau. Interior steel stud framed walls, west half only. No grid, hardlids or soffits at this time.
|
Print Occupancy Form | | | 12/3/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/2/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/2/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/2/2019 | | DONE |
|
|
|
Emailed Mitch to ask if ACHD fees are due and if an inspection is needed.
|
Plan assigned to (CJW) | 10/7/2019 | 10/29/2019 | 11/27/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 10/22/19 (L-3 - 15 days) (eplan - 22 sheets) Unitek College (route to staff)
|
Routing - PLANNING | 1/27/2019 | | 11/27/2019 | | PASS |
Jeff Lowe
|
|
|
route to Jeff
|
Plan resubmittals received | | | 11/27/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/27/2019 | | 11/27/2019 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/27/2019 | | DONE |
|
|
|
MET jnorton@jwci.com
Need GC
Need Revised Value
|
Plan resubmittals requested | | | 11/19/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 11/15/2019 | | 11/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 11/13/2019 | | 11/15/2019 | | PASS |
Carl Westfall
|
|
|
|
Routing PW Sewer Rating | 11/15/2019 | | 11/15/2019 | | PASS |
Morgan Webb
|
|
|
Proposed mop sink removed
|
Routing - PLANNING | 11/15/2019 | | 11/15/2019 | | FAIL |
David Moser
|
|
|
Appeal period not over yet for CUP19-00081
|
Plan resubmittals received | | | 11/13/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 10/31/2019 | 11/3/2019 | 11/1/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 10/7/2019 | 10/7/2019 | 10/31/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 10/31/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/31/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/7/2019 | | 10/31/2019 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - MECHANICAL | 10/7/2019 | | 10/14/2019 | | FAIL |
Troy James
|
|
|
Need Idaho stamped plans for mechanical, plumbing and electrical.
|
Routing - PLANNING | 10/7/2019 | | 10/9/2019 | | FAIL |
David Moser
|
|
|
CUP15-00030 requires the future expansion to the CWI Facility obtain planning approval prior to issuance of buildings and or Certificates of Occupancy. This BLDG permit will expand nursing classrooms into the rest of the office bldg. As such, a CUP modification is required.
|
Routing PW Environmental | 10/8/2019 | | 10/9/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 10/7/2019 | | 10/8/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2019 | | 10/8/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 10/7/2019 | | 10/8/2019 | | PASS |
Dan Ediger
|
|
|
Per Plans and ISPC
|
Plan Reviewer's activity | | | 10/2/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 10/2/2019 | | PASS |
|
|
|
|
Application received | | | 9/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 30 2019 4:47PM
|