Information based on query as of Monday, April 29, 2024.
Permit Information
Permit NumberFIR13-00187
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 6001 W CASSIA ST
Project NameBorah High School FA Upgrade
Customer Number 
ePlanReviewYes
Description
This fire alarm permit is to upgrade the existing fire alarm system to meet current code requirements. This permit scope of work includes adding, relocating, and/or replacing notification and initiating devices. NAC panels are being provided, as well as voice evacuation in the gymnasium areas. Pull stations are being provided at every exit, monitor modules for conventional attic devices, heat detectors in unsprinklered attic spaces, smoke detection in unsprinklered areas, smoke detectors for door holder release, and HVAC shutdown/monitoring. There is no associated building permit.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIR-Aging Inspection5/8/20205/8/20205/11/2020 PASS
DetailsTroy Cobbley
Permit has been finaled.
INSP-Final Inspection5/8/20205/8/20205/8/2020PPASS
DetailsTroy Cobbley
Permit finaled. Doors repaired.
INSP-Final Inspection8/13/20198/14/20198/14/2019PFAIL
DetailsTroy Cobbley
Two of the three sets of doors did not latch due to positive air pressure from the classroom wings. The roll down fire door functioned with activation on the control box test function. So to final this permit the classroom wing doors need to be adjusted to overcome the air pressure and latch automatically.

Jeff Phone #: ###-####
CHANGE STATUS TO (ISS)  1/10/2019 DONE
accidentally changed to void. Restored to issued.
Miscellaneous action  9/17/2018 DONE
Emailed Shane to request an acceptance test.
INSP-Final Inspection5/29/20186/4/20186/4/2018AFAIL
DetailsTroy Cobbley
No school disctrict personnell showed up to provide acces. No inspection was performed.


Bora HS final Phone #: ###-#### Inspection requested via web by Shane Lesteberg
FIR-Aging Inspection2/13/20182/13/20182/16/2018 NR
DetailsTroy Cobbley
I've spoken to Bill Harmon and Ray with the boise school district and people at Simplex about getting this permit finaled
FIR-Aging Inspection7/20/20177/20/20177/24/2017 NR
DetailsTroy Cobbley
I spoke to Colton with SimplexGrinnell about status. He is going to follow up.
Case Summary  4/1/2014 DONE
Miscellaneous action  4/1/2014 DONE
Received a cd with as builts from Charlie Bayne. I delivered it to Hattie for onbase archiving.
INSP-Final Inspection3/25/20143/26/20143/26/2014AFAIL
DetailsTroy Cobbley
To final project I need the doors as marked on the plans to be repaired, if they are part of a fire rated assembley, or they can remain if the door hold opens are a convience feature. Also needed is the roll down fire door repaired/tested. Need as-builts for the entire project submitted to Lee as discussed.
INSP-Alarm Testing1/28/20141/31/20141/31/2014PPASS
DetailsTroy Cobbley
Verified heat detector zones in the old gym.
INSP-Alarm Testing1/28/20141/30/20141/31/2014PDONE
DetailsTroy Cobbley
Todays inspection verified existing heat detectors in the Old Gym. Testing interconnect will be verified tomorrow.
INSP-Alarm Testing1/28/20141/29/20141/29/2014PDONE
DetailsTroy Cobbley
Testing of attic heat detectors in the Industrial Arts building completed today.
INSP-Alarm Testing1/28/20141/28/20141/28/2014PDONE
DetailsTroy Cobbley
See the city approved plans for location of tested heat detectors in the attic space. Minor corrections have been noted.
INSP-Sprinkler Rough-in/Hydro1/28/20141/28/20141/28/2014PCANC
DetailsTroy Cobbley
As late as possible Phone #: 2089411846 >> Inspection requested via mobile web by After 3pm please Inspection cancelled via mobile web on Tuesday, January 28, 2014.
INSP-Alarm Testing1/22/20141/24/20141/24/2014PFAIL
DetailsCraig D. Hanson
area in attic not covered by heat detectors, 2 need added. addressing of devices, there are two 67's.
INSP-Alarm Testing1/9/20141/10/20141/10/2014APASS
DetailsTroy Cobbley
Tested heat detectors in the Main building, north end.
INSP-Final Inspection1/3/20141/6/20141/6/2014PPART
DetailsForrest France
Completed fire sprinkler monitoring verification at five risers including three dry systems for east classroom wings and two wet systems.
INSP-Alarm Testing12/30/201312/31/201312/31/2013ADONE
DetailsTroy Cobbley
Todays inspection was for the remaining notification device function. All devices tested ok except a horn only was installed where a strobe is shown in a corridor in the Auditorium and there was one non-functional ceiling mounted strobe in the east main lobby restroom of the Gym.
INSP-Alarm Testing10/29/201311/1/201311/1/2013ADONE
DetailsTroy Cobbley
See the city approved plans for locations of devices tested and locations where corrections are needed. Items are marked on the small plans. Most devices tested. Still need to test the attic areas and set off the notification devices in the old gym and auditorium buidlings.
INSP-Alarm Testing10/2/201310/4/201310/4/2013ADONE
DetailsTroy Cobbley
See the small copy of city approved plans for additional devices tested today and the corrections noted.
INSP-Alarm Testing8/23/20138/26/20138/26/2013PDONE
DetailsTroy Cobbley
See the small version of the city approved plans for areas inspected today. Todays inspection took place in the Administration Building. No signals were tested, only verification of spacing, candellas and testing of smoke detectors. Devices tested have been marked "ok" in red on the plans. See plans for items needing corrected which include door closures, additional notification in the Kitchen and additional notification in the Lunch Room seating area where the visual notification is blocked by banners hanging from the ceiling.
INSP-Alarm Testing8/19/20138/19/20138/23/2013PNR
DetailsForrest France
Preliminary walkthrough completed of classroom wings A and B and portions of the cafeteria and kitchen. Noted several items in need of adjustment or revision. Discussed acceptance testing schedule, panel details, project parameters, etc.
Permit Ready to Issue  6/3/2013 DONE
DetailsTisha Gallop
Issue and Print Permit  6/3/2013 DONE
DetailsTisha Gallop
Inspection Record Card- Fire6/3/2013 6/3/2013 DONE
DetailsTisha Gallop
Alarm Plan Check5/23/2013 5/23/2013 PASS
DetailsStephanie L. Cobbley
plans approved with review comments
PLANS TAKEN FRONT DESK ALARM  5/23/2013 DONE
updated in project dox
Miscellaneous action  5/22/2013 DONE
Received requested documents. re-uploaded in proj dox
Miscellaneous action  5/21/2013 DONE
I emailed Dante with SimplexGrinnell to let him know that there were a few drawings that did not upload (there was an error). I explained that I would need to deny the submittal so he could have access to re-upload the plans, but that it would not count as a second "fail".
1st review completed  5/13/2013 FAIL
Applicant notified within electronic plan review.
Alarm Plan Check5/13/2013 5/13/2013 FAIL
DetailsStephanie L. Cobbley
Plans denied - resubmittal required
Miscellaneous action  5/13/2013 DONE
updated in project dox
Plan assigned to (Stephanie)4/29/2013 4/29/2013 DONE
DetailsStephanie L. Cobbley
Application received  4/25/2013 DONE
Application submitted via PDS Online on Apr 25 2013 1:26PM