FIR-Aging Inspection | 5/8/2020 | 5/8/2020 | 5/11/2020 | | PASS |
Troy Cobbley
|
|
|
Permit has been finaled.
|
INSP-Final Inspection | 5/8/2020 | 5/8/2020 | 5/8/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Doors repaired.
|
INSP-Final Inspection | 8/13/2019 | 8/14/2019 | 8/14/2019 | P | FAIL |
Troy Cobbley
|
|
|
Two of the three sets of doors did not latch due to positive air pressure from the classroom wings. The roll down fire door functioned with activation on the control box test function. So to final this permit the classroom wing doors need to be adjusted to overcome the air pressure and latch automatically.
Jeff Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 1/10/2019 | | DONE |
|
|
|
accidentally changed to void. Restored to issued.
|
Miscellaneous action | | | 9/17/2018 | | DONE |
|
|
|
Emailed Shane to request an acceptance test.
|
INSP-Final Inspection | 5/29/2018 | 6/4/2018 | 6/4/2018 | A | FAIL |
Troy Cobbley
|
|
|
No school disctrict personnell showed up to provide acces. No inspection was performed.
Bora HS final Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
FIR-Aging Inspection | 2/13/2018 | 2/13/2018 | 2/16/2018 | | NR |
Troy Cobbley
|
|
|
I've spoken to Bill Harmon and Ray with the boise school district and people at Simplex about getting this permit finaled
|
FIR-Aging Inspection | 7/20/2017 | 7/20/2017 | 7/24/2017 | | NR |
Troy Cobbley
|
|
|
I spoke to Colton with SimplexGrinnell about status. He is going to follow up.
|
Case Summary | | | 4/1/2014 | | DONE |
|
|
|
|
Miscellaneous action | | | 4/1/2014 | | DONE |
|
|
|
Received a cd with as builts from Charlie Bayne. I delivered it to Hattie for onbase archiving.
|
INSP-Final Inspection | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | FAIL |
Troy Cobbley
|
|
|
To final project I need the doors as marked on the plans to be repaired, if they are part of a fire rated assembley, or they can remain if the door hold opens are a convience feature. Also needed is the roll down fire door repaired/tested. Need as-builts for the entire project submitted to Lee as discussed.
|
INSP-Alarm Testing | 1/28/2014 | 1/31/2014 | 1/31/2014 | P | PASS |
Troy Cobbley
|
|
|
Verified heat detector zones in the old gym.
|
INSP-Alarm Testing | 1/28/2014 | 1/30/2014 | 1/31/2014 | P | DONE |
Troy Cobbley
|
|
|
Todays inspection verified existing heat detectors in the Old Gym. Testing interconnect will be verified tomorrow.
|
INSP-Alarm Testing | 1/28/2014 | 1/29/2014 | 1/29/2014 | P | DONE |
Troy Cobbley
|
|
|
Testing of attic heat detectors in the Industrial Arts building completed today.
|
INSP-Alarm Testing | 1/28/2014 | 1/28/2014 | 1/28/2014 | P | DONE |
Troy Cobbley
|
|
|
See the city approved plans for location of tested heat detectors in the attic space. Minor corrections have been noted.
|
INSP-Sprinkler Rough-in/Hydro | 1/28/2014 | 1/28/2014 | 1/28/2014 | P | CANC |
Troy Cobbley
|
|
|
As late as possible Phone #: 2089411846 >> Inspection requested via mobile web by After 3pm please Inspection cancelled via mobile web on Tuesday, January 28, 2014.
|
INSP-Alarm Testing | 1/22/2014 | 1/24/2014 | 1/24/2014 | P | FAIL |
Craig D. Hanson
|
|
|
area in attic not covered by heat detectors, 2 need added. addressing of devices, there are two 67's.
|
INSP-Alarm Testing | 1/9/2014 | 1/10/2014 | 1/10/2014 | A | PASS |
Troy Cobbley
|
|
|
Tested heat detectors in the Main building, north end.
|
INSP-Final Inspection | 1/3/2014 | 1/6/2014 | 1/6/2014 | P | PART |
Forrest France
|
|
|
Completed fire sprinkler monitoring verification at five risers including three dry systems for east classroom wings and two wet systems.
|
INSP-Alarm Testing | 12/30/2013 | 12/31/2013 | 12/31/2013 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for the remaining notification device function. All devices tested ok except a horn only was installed where a strobe is shown in a corridor in the Auditorium and there was one non-functional ceiling mounted strobe in the east main lobby restroom of the Gym.
|
INSP-Alarm Testing | 10/29/2013 | 11/1/2013 | 11/1/2013 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for locations of devices tested and locations where corrections are needed. Items are marked on the small plans. Most devices tested. Still need to test the attic areas and set off the notification devices in the old gym and auditorium buidlings.
|
INSP-Alarm Testing | 10/2/2013 | 10/4/2013 | 10/4/2013 | A | DONE |
Troy Cobbley
|
|
|
See the small copy of city approved plans for additional devices tested today and the corrections noted.
|
INSP-Alarm Testing | 8/23/2013 | 8/26/2013 | 8/26/2013 | P | DONE |
Troy Cobbley
|
|
|
See the small version of the city approved plans for areas inspected today. Todays inspection took place in the Administration Building. No signals were tested, only verification of spacing, candellas and testing of smoke detectors. Devices tested have been marked "ok" in red on the plans. See plans for items needing corrected which include door closures, additional notification in the Kitchen and additional notification in the Lunch Room seating area where the visual notification is blocked by banners hanging from the ceiling.
|
INSP-Alarm Testing | 8/19/2013 | 8/19/2013 | 8/23/2013 | P | NR |
Forrest France
|
|
|
Preliminary walkthrough completed of classroom wings A and B and portions of the cafeteria and kitchen. Noted several items in need of adjustment or revision. Discussed acceptance testing schedule, panel details, project parameters, etc.
|
Permit Ready to Issue | | | 6/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue and Print Permit | | | 6/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 6/3/2013 | | 6/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Alarm Plan Check | 5/23/2013 | | 5/23/2013 | | PASS |
Stephanie L. Cobbley
|
|
|
plans approved with review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 5/23/2013 | | DONE |
|
|
|
updated in project dox
|
Miscellaneous action | | | 5/22/2013 | | DONE |
|
|
|
Received requested documents. re-uploaded in proj dox
|
Miscellaneous action | | | 5/21/2013 | | DONE |
|
|
|
I emailed Dante with SimplexGrinnell to let him know that there were a few drawings that did not upload (there was an error). I explained that I would need to deny the submittal so he could have access to re-upload the plans, but that it would not count as a second "fail".
|
1st review completed | | | 5/13/2013 | | FAIL |
|
|
|
Applicant notified within electronic plan review.
|
Alarm Plan Check | 5/13/2013 | | 5/13/2013 | | FAIL |
Stephanie L. Cobbley
|
|
|
Plans denied - resubmittal required
|
Miscellaneous action | | | 5/13/2013 | | DONE |
|
|
|
updated in project dox
|
Plan assigned to (Stephanie) | 4/29/2013 | | 4/29/2013 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Application received | | | 4/25/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 25 2013 1:26PM
|