FIRE-Final Inspection | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
Jeff Phone #: ###-####
|
FIRE-Final Inspection | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | PART |
Troy Cobbley
|
|
|
A temporarty for life safety is ok with Ron's permission until the project related fire alarm permit is addressed.
Please call Jeff Fahey Phone #: ###-#### Inspection requested via web by Ami Ostrow
|
BLD-Final | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Mike Jordan
|
|
|
Please call Jeff Fahey Phone #: ###-#### Inspection requested via web by Ami Ostrow. building issues have been resolved. Ok for temp occ. as soon as fire/life/safety sings temp. Will be ok for perm. occ. when fire/life/safety sings perm.
|
BLD-Final | 11/14/2018 | 11/15/2018 | 11/15/2018 | P | NR |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Needs to provide directional signage at non ADA restroom showing location of ADA restrooms. Will be ok to final after life/safety and fire alarm finals and ADa sign posted at restroom.
|
FIRE-Final Inspection | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need the project related fire alarm permit finaled, need thumbturn removed from main exit and sticker installed at main exit, need emergency lighting repaired.
Jeff Phone #: ###-####
|
FIRE-Final Inspection | 11/13/2018 | 11/14/2018 | 11/14/2018 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm permit addressed prior to a life safety inspection.
Jeff Phone #: ###-####
|
BLD-Final | 11/12/2018 | 11/13/2018 | 11/13/2018 | P | NR |
Mike Jordan
|
|
|
Please call Jeff Fahey. Phone #: ###-#### Inspection requested via web by Ami Tracy. Needs fire/life/safety final and fire alarm.
|
BLD-Ceiling Grid Inspection | 10/8/2018 | 10/9/2018 | 10/9/2018 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Ceiling grid at new reception area.
|
BLD-Framing/Rough-in | 9/14/2018 | 9/17/2018 | 9/17/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Interior steel stud framed walls for new reception area ok, pending electrical rough in inspection.
|
BLD-Ceiling Grid Inspection | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PART |
Mike Jordan
|
|
|
Seth Phone #: ###-####. Needs to fireblock at top of walls.
|
BLD-Framing/Rough-in | 5/14/2018 | 5/15/2018 | 5/15/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. North half ok, exculding shear wall.
|
BLD-Other | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Mike Jordan
|
|
|
fire caulking- Jeff Phone #: ###-####. South of stairway ok. Ok to cover.
|
BLD-Framing/Rough-in | 5/9/2018 | 5/9/2018 | 5/9/2018 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. South of stairwell ok to cover all sides.
|
BLD-Framing/Rough-in | 5/7/2018 | 5/8/2018 | 5/8/2018 | A | PART |
Mike Jordan
|
|
|
. Ok to one side south of stairwell. Needs to complete fireblocking.
|
BLD-Framing/Rough-in | 5/4/2018 | 5/7/2018 | 5/7/2018 | P | NH |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|