BLD-Final | 9/16/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Mike Jordan
|
|
|
Call ahead // David Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Mike Jordan
|
|
|
Call ahead // David Phone #: ###-####. All issues have been reolved.
|
FIRE-Final Inspection | 7/22/2019 | 7/23/2019 | 7/24/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide single action hardware on the two store front doors as discussed. Fire alarm has been addressed.
Mark Phone #: ###-####
|
BLD-Final | 7/22/2019 | 7/23/2019 | 7/23/2019 | P | NR |
Mike Jordan
|
|
|
Mark Phone #: ###-####. Issues with door hardware. Waiting for plan review. Will need to reschedule.
|
FIRE-Final Inspection | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide fire alarm modifications for the required manual pull station at the new door, provide single action hardware on the two new store front doors as discussed.
Mark Phone #: ###-####
|
BLD-Final | 6/17/2019 | 6/18/2019 | 6/17/2019 | A | CANC |
Mike Jordan
|
|
|
Mark Phone #: ###-####
|
BLD-Final | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PART |
Mike Jordan
|
|
|
Julian Phone #: ###-####. Ok for temp occ. to use the new sevice/lube addition. Still some storefront work and plan mod for the deletion of the storage room.
|
FIRE-Final Inspection | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for new oil change building. Relocated fire hydrant is approved but requires a plan mod prior to a final life safety sign off on the scope of work.
julian Phone #: ###-####
|
BLD-Conference | 2/1/2019 | 2/4/2019 | 2/5/2019 | A | DONE |
Mike Jordan
|
|
|
Julian Phone #: ###-####
|
FIRE-Final Inspection | 1/24/2019 | 1/28/2019 | 1/28/2019 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was just for the shop area since other work is not complete. To allow use of the shop area the relocated fire hydrant needs tto be approved by plan review, the existing overhead door needs to be removed as per plan for our exit path and the walls the dealer wants to keep shown on a revised building plan, also on the path of egress the thumbturn deadbolt needs to be removed at the exterior exit door and the exit sign over this same door repaired. In the other areas shown to be modified the Storage Room was not built which will need to be addressed on modified approved plans.
Juilan Phone #: ###-####
|
BLD-Foundation | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PART |
Jim Sly
|
|
|
cmu grout at 1 (mti) // tony Phone #: ###-#### ok pending MTI special inspection, tests and approvals.
|
BLD-Concrete | 11/12/2018 | 11/13/2018 | 11/13/2018 | P | DEFR |
Mike Jordan
|
|
|
Requesting CMU re- bar ; grout inspection, grout is scheduled for 1;30. MTI will also being doing special inspections. , Thank you Tony. Phone #: ###-#### Inspection requested via web by Tony Inserra
|
BLD-Foundation | 10/18/2018 | 10/19/2018 | 10/19/2018 | P | PEND |
Dave Hannah
|
|
|
pouring at 2pm- Tony Phone #: ###-#### ok after spec. sign off
|
BLD-Footing | 10/15/2018 | 10/16/2018 | 10/16/2018 | P | PASS |
Mike Jordan
|
|
|
concrete 130 // Tony Phone #: ###-####
|