FIRE-Final Inspection | 8/12/2020 | 8/13/2020 | 8/12/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Troy *screened Phone #: ###-####
|
BLD-Final | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PART |
Tell Riley
|
|
|
Screened- Troy Phone #: ###-####/temp occupancy ok, see entry from zoning, see email to Troy for public works--other signatures are on card// will need final special inspection report prior to permanant occupancy//
|
BLD-Final | 7/8/2020 | 7/10/2020 | 7/10/2020 | P | PART |
Tell Riley
|
|
|
Troy *screened* Phone #: ###-####//Temp ok to start setup in offices and classrooms//other trades and fire life safety has passed//let Troy know that ACHD, CDHD, zoning and Public works temps will be needed//an updated temp occupancy will be needed prior to full occupancy of the school//
|
FIRE-Final Inspection | 7/8/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Troy Cobbley
|
|
|
Temp for life safety until the new parking lot on norht side has been built/verified. All of the new school life safety items appear ok.
Troy *screened* Phone #: ###-####
|
FIRE-Conference | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | DONE |
Troy Cobbley
|
|
|
The general contractor and I went over the life safety notes.
|
BLD-Ceiling Grid Inspection | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//cafeteria area only//
|
BLD-Framing/Rough-in | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PART |
Brandon Shaw
|
|
|
Kitchen bathroom, ceiling framing... OK to cover...
|
BLD-Conference | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | DONE |
Tell Riley
|
|
|
|
BLD-Ceiling Grid Inspection | 1/14/2020 | 1/14/2020 | 1/14/2020 | P | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area C classrooms ok to cover//
Note: fire wall will need to be inspected for penetrations and fire caulking in the end rooms and hallway//
|
BLD-Ceiling Grid Inspection | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | PASS |
Tell Riley
|
|
|
Troy Phone #: ###-####//remaining portions of area A and B//hallways in area A,B and C//
|
BLD-Ceiling Grid Inspection | 12/20/2019 | 12/20/2019 | 12/20/2019 | A | PART |
Tell Riley
|
|
|
Area A grids ok, where rough ins are approved//
|
BLD-Wall cover | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//wall framing for cafeteria ok minus short wall near oven area//
|
BLD-Other | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Tell Riley
|
|
|
TROY- inspection for hardlid Phone #: ###-####//area c hardlids--ok add fire caulk to small conduit//area d wall cover ok in back of gym area--still need to see cafeteria//1 hour wall in electrical room was looked at and discussed for penetrations///
|
BLD-Ceiling Grid Inspection | 11/27/2019 | 12/2/2019 | 12/2/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area B six classrooms ok//
|
BLD-Ceiling Grid Inspection | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//walk through yesterday for school//discussed fire wall area and penetrations//hardlids area A ok to cover//no grid at this time//
|
BLD-Wall Bracing | 11/7/2019 | 11/8/2019 | 11/8/2019 | P | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//add screws at bottom of shear panels as discussed--guys working on when I left//
|
BLD-Wall Bracing | 10/15/2019 | 10/16/2019 | 10/16/2019 | P | PART |
Tell Riley
|
|
|
shear // Troy Phone #: ###-####//area d and part of c bolts and hold downs installed// shear nailing ok on areas that are complete//
|
BLD-Framing/Rough-in | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PART |
Tell Riley
|
|
|
area A wall framing ok to cover//electrical and plumbing ok//covered under shear inspection for shear wall// Area C walk through-will need to add double studs under girder as discussed//
|
BLD-Wall Bracing | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area A wall bracing complete//all wall bracing is on interior side of wall//framing is being inspected with hold down and anchor inspections//
|
BLD-Other | 9/20/2019 | 9/20/2019 | 9/20/2019 | P | PASS |
Tell Riley
|
|
|
Troy- sheeting inspection call in at 11:28 am Phone #: ###-####//roof sheathing last area ok to cover with roofing//straps installed and nailed//
|
BLD-Framing/Rough-in | 9/18/2019 | 9/19/2019 | 9/19/2019 | A | PART |
Tell Riley
|
|
|
roof sheathing- troy Phone #: ###-####//last of the roof sheathing--ok to cover//call to check strap nailing near gym wall//
|
BLD-Wall Bracing | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PART |
Tell Riley
|
|
|
hold down // Troy Phone #: ###-####//hold downs and anchor bolts for shear walls in area A and B--bolts ok and hold downs corrected// insulation visual inspection area B//ledger attachment per detail on gym//
|
BLD-Other | 9/11/2019 | 9/11/2019 | 9/11/2019 | A | PART |
Tell Riley
|
|
|
area B and portion of area A hold downs//add double stud to hold down in corner// fix two hold downs(saddles upside down)// will double check next inspection//
|
BLD-Other | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PART |
Tell Riley
|
|
|
roof // Troy Phone #: ###-####//area c roof nailing//need to adjust nail depth//corrected onsite ok to continue...///
|
BLD-Wall cover | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PART |
Tell Riley
|
|
|
troy Phone #: ###-####//area B partial wall cover for insulation and shear walls//
|
BLD-Other | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PART |
Tell Riley
|
|
|
Troy-roof sheating Phone #: ###-####//roof decking ok per plans//
|
BLD-Other | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | PART |
Tell Riley
|
|
|
roof seathing // Troy Phone #: ###-####//nailing ok on deck//
|
BLD-Foundation | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Tell Riley
|
|
|
Troy Phone #: ###-####//pier stems// ok to pour pending specials....//
|
BLD-Foundation | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//pier footings for awnings//ok to pour pending specials//
|
BLD-Foundation | 8/9/2019 | 8/12/2019 | 8/12/2019 | P | PASS |
Tell Riley
|
|
|
TROY- REBAR INSPECTION Phone #: ###-####//area d slab// final slab pour//pending all specials//
|
BLD-Other | 8/6/2019 | 8/7/2019 | 8/7/2019 | P | PART |
Tell Riley
|
|
|
roof sheeting // Jeff Phone #: ###-####//area b roof sheathing//
|
BLD-Footing | 8/6/2019 | 8/7/2019 | 8/7/2019 | P | PART |
Tell Riley
|
|
|
rebar and vapor barrier concrete // Jeff Phone #: ###-####//slab vapor barrier ok pending specials//
|
BLD-Foundation | 7/30/2019 | 7/30/2019 | 7/30/2019 | P | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//final foundation inspection on building//ok pending specials....///
|
BLD-Concrete | 7/25/2019 | 7/26/2019 | 7/26/2019 | P | PART |
Tell Riley
|
|
|
tROY Phone #: ###-####//slab vapor barrier//middle section of building//ok//pending specials//
|
BLD-Footing | 7/22/2019 | 7/23/2019 | 7/23/2019 | P | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area D footings//ok pending specials......////
|
BLD-Foundation | 7/18/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Tell Riley
|
|
|
TROY- foundation insalation inspection Phone #: ###-####//insulation ok//
|
BLD-Foundation | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Pending special inspection...
|
BLD-Other | 7/8/2019 | 7/9/2019 | 7/9/2019 | P | PART |
Tell Riley
|
|
|
TROY- inspection for vapor barrier floor Phone #: ###-####//ok pending specials...////also looked at exterior footings//
|
BLD-Concrete | 7/1/2019 | 7/2/2019 | 7/2/2019 | P | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area A slab//vapor barrier installed//remesh installed//rebar ok//pendinng special inspections//
|
BLD-Footing | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//foundation insulation//area B///
|
BLD-Other | 6/27/2019 | 6/27/2019 | 6/27/2019 | A | PART |
Tell Riley
|
|
|
CMU inspection ok pending specials// gym area//1st grout//
|
BLD-Foundation | 6/26/2019 | 6/27/2019 | 6/27/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//ok for foundation pending specials//area D//
|
BLD-Foundation | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area A foundation insulation//ok per plans//
|
BLD-Footing | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####//area b footings and rebar.//ok pending specials//
|
BLD-Foundation | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | PART |
Tell Riley
|
|
|
stem wall // Troy Phone #: ###-####//walls ok on west side//pending special inspection ok to pour//
|
BLD-Footing | 6/7/2019 | 6/10/2019 | 6/10/2019 | A | PART |
Tell Riley
|
|
|
Troy Phone #: ###-####, west footings ok per plans, ok pending special inspections
|
BLD-Footing | 6/3/2019 | 6/4/2019 | 6/4/2019 | P | PART |
Tony Young
|
|
|
Call ahead for directions // Troy Phone #: ###-####,, looked at NE interior footers,, approved pending special,, looked at north and east wall slab insulation, ok work in progress. NW foundation wall work in progress pending special inspection. look at current engineering plan for current rebar plans
|
BLD-Footing | 5/15/2019 | 5/17/2019 | 5/17/2019 | A | PART |
Jim Sly
|
|
|
call for directions // Troy Phone #: ###-#### Area D.....OK pending STRATA special inspection, tests and approvals.
|