Final | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...job complete...ok to final
|
Final | 12/13/2019 | 12/13/2019 | 12/13/2019 | P | PART |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins...temp occupency ok...millwork/counters need installed, front floor outlet and LV cabinet, water line bonding-waiting on clamp, and main LV rack bonding left to do
|
Final | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | PART |
Tom Saunders
|
|
|
Partial Final for Service Department Phone #: ###-#### Inspection requested via web by Bryan Atkins..back shop and exterior condtioning units, required GFCI protection verified...ok to final...breaker ties need verified, permanent panel labels, and sprinkler bond to building steel by complete final
|
Electrical Rough-In | 11/11/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Tom Saunders
|
|
|
Ceiling Inspection under Mezz Phone #: ###-#### Inspection requested via web by Bryan Atkins...ok to cover grid
|
Electrical Rough-In | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | PASS |
Eric Story
|
|
|
Showroom Fireplace Phone #: ###-#### Inspection requested via web by Bryan Atkins Showroom fireplace and both reception desk ok to cover
|
Electrical Rough-In | 10/15/2019 | 10/16/2019 | 10/16/2019 | A | PASS |
Rock A. Hudson
|
|
|
Underground, pole bases Phone #: ###-#### Inspection requested via web by Bryan Atkins West lot center planter underground and 2 pole bases rough in ok cover
|
Permanent Service | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PASS |
Tom Saunders
|
|
|
Journeyman on-site, Wade Luthy, ###-####.
Re-inspection. Phone #: ###-#### Inspection requested via web by Bryan Atkins..p/s u/g n ok
|
Electrical Rough-In | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | PASS |
Eric Story
|
|
|
Room behind electrical ok to cover
|
Permanent Service | 9/23/2019 | 9/23/2019 | 9/23/2019 | P | CANC |
Eric Story
|
|
|
Journeyman on-site, Wade Luthy, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins AFC needs re-calculated and posted
|
Electrical Rough-In | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
James Ady
|
|
|
North bathroom Wade Luthy on-site for questions, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins N Restroom. Very back Left corner of building. OK to cover
|
Electrical Rough-In | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | PASS |
Tom Saunders
|
|
|
Rough-in inspection for the southeast corner of showroom and mezzanine. Wade Luthy, lead journeyman on-site, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins.... front floor deck showrm SE corner furniture pwr mezzanine breakroom/kitchen area and room walls and hardlid...ok to cover
|
Electrical Rough-In | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | PASS |
Tom Saunders
|
|
|
Inspection needed for Retail area. Journeyman on-site, Wade Luthy ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins... vestibule walls and ceiling wall of retail sales/accessories ok to cover
|
Electrical Rough-In | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PASS |
Eric Story
|
|
|
Need rough-in in parts before they start sheetrocking. Wade Luthy on site, ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins Notice given if sheetrockers install proir to any electrical inspection ALL sheetrock will be removed.... Walls in front and back area(sales and parts areas) and hard lids in breakroom ok to cover
|
Electrical Rough-In | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Rock A. Hudson
|
|
|
Partial rough-in inspection for the southeast corner of the showroom. Phone #: ###-#### Inspection requested via web by Bryan Atkins Area noted wall rough in ok cover
|
Electrical Rough-In | 7/11/2019 | 7/12/2019 | 7/12/2019 | A | PASS |
Daryl DeGrange
|
|
|
Rough-in for East Wall and Mezzanine Lead Journeyman on site, Wade Luthy ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins Rough-in ok cover East office area under Mezzanine, Walls & hard lids
|
Electrical Rough-In | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Atkins South wall and sales area wall between show room ok to cover
|
Electrical Rough-In | 5/29/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Eric Story
|
|
|
West side of the showroom. On-site contact: Wade Luthy ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins West side walls ok to cover
|
Electrical Rough-In | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Tom Saunders
|
|
|
Underground Phone #: ###-#### Inspection requested via web by Bryan Atkins... ok to cover branch circuits under slab 3/4 PVC
|
Electrical Rough-In | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PASS |
Eric Story
|
|
|
Uffer inspection. Wade Luthy on site ###-#### Phone #: ###-#### Inspection requested via web by Bryan Atkins Retail,showoom,service area, bonding to building steel and fire riser and Uffer ok to cover, Also looked at west area lighting conduits for cover of insulation
|
Electrical Rough-In | 1/23/2019 | 1/24/2019 | 1/24/2019 | A | PASS |
Rock A. Hudson
|
|
|
Underground Rough-In Phone #: ###-#### Inspection requested via web by Bryan Atkins Underground associated with electrical room rough in ok cover
|
Electrical Rough-In | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | PASS |
Tom Saunders
|
|
|
Contact on site is Wade Luthy. Inspection for electrical rough-in for underground. Phone #: ###-#### Inspection requested via web by Bryan Atkins... east end runs to electrical rm ...ok to cover
|