Final | 7/10/2020 | 7/10/2020 | 7/10/2020 | A | PART |
Mark Moncarr
|
|
|
exterior building Phone #: ###-#### Inspection requested via web by Debby Pierce Partial final. Waiting for possible commisioning report. General said there was only 1 for mechanical, is checking for the electrical side.
|
Final | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | PART |
Mark Moncarr
|
|
|
area c final Phone #: ###-#### Inspection requested via web by Debby Pierce Partial for cafeteria, and a couple of classrooms. Discussed moving line sets and gas line up so they are out of working clearance zone for panel in mezzanine.
|
Final | 6/17/2020 | 6/17/2020 | 6/17/2020 | A | PART |
Rock A. Hudson
|
|
|
FINAL MEZZANINE AND ELECTRICAL ROOM Phone #: ###-#### Inspection requested via web by Debby Pierce No heat tape installed yet, did not test EPD breakers. 110.26- Work space height shall be provided for area A Mezz. Panel M1.Line sets at 6' 28" in front of panel, 6'6" required, TCO for areas noted ok
|
Final | 6/10/2020 | 6/11/2020 | 6/10/2020 | A | CANC |
Mark Moncarr
|
|
|
final main electrical room and mezzanines Phone #: ###-#### >> Inspection requested via web by Debby Pierce Inspection cancelled from web by: Debby Pierce
|
Final | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | PART |
Mark Moncarr
|
|
|
final area B Phone #: ###-#### Inspection requested via web by Debby Pierce Area B classrooms
|
Final | 6/9/2020 | 6/9/2020 | 6/9/2020 | P | PART |
Mark Moncarr
|
|
|
PARTIAL FINAL AREA A Phone #: ###-#### Inspection requested via web by Debby Pierce Area A
|
Electrical Rough-In | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Mark Moncarr
|
|
|
kitchen ceiling Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover kitchen ceiling
|
Electrical Rough-In | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | PASS |
Mark Moncarr
|
|
|
front entry rough in Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover ceiling inside main entrance on E side.
|
Electrical Rough-In | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Mark Moncarr
|
|
|
ceiling inspection area c Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover area listed
|
Electrical Rough-In | 3/31/2020 | 3/31/2020 | 3/31/2020 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling inspection please. ###-#### Area A corridor and classroom grid rough in ok cover.
|
Permanent Service | 3/5/2020 | 3/9/2020 | 3/9/2020 | A | PASS |
Mark Moncarr
|
|
|
service Phone #: ###-#### Inspection requested via web by Debby Pierce Equiptment tested, service was energized over the weekend. AFC present
|
Electrical Rough-In | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Mark Moncarr
|
|
|
ceiling inspection south wing. consult on disconnect locations roof Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover ceilings S side classrooms. Disconnects for units on rooftop clearance ok.
|
Electrical Rough-In | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | PASS |
Mark Moncarr
|
|
|
GYM CEILING Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover gym ceiling
|
Electrical Rough-In | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PASS |
Mark Moncarr
|
|
|
kitchen Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover kitch walls.
|
Electrical Rough-In | 1/14/2020 | 1/15/2020 | 1/15/2020 | A | PASS |
Mark Moncarr
|
|
|
wall and hard lid rough in west wing. excludes kitchen and gym. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover areas listed
|
Electrical Rough-In | 12/24/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Mark Moncarr
|
|
|
area a north wing rough in. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover Area A north side.
|
Electrical Rough-In | 12/2/2019 | 12/3/2019 | 12/3/2019 | A | PASS |
Mark Moncarr
|
|
|
south wing wall rough in exterior soffit rough in. south wing hard lid rough in Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover areas listed. Fire hats installed on exterior soffits.
|
Rough-In Permanent Service | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Mark Moncarr
|
|
|
UNDERGROUND AT IDAHO POWER TRANSFORMER Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover conduits from trans to building on E side of school.
|
Electrical Rough-In | 10/8/2019 | 10/8/2019 | 10/8/2019 | P | PASS |
Mark Moncarr
|
|
|
electrical room underground rough in. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover grd work elec room on E bldg W side.
|
Electrical Rough-In | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PASS |
Mark Moncarr
|
|
|
branch underground area A Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover conduits from elec room to misc locations for classrooms.
|
Electrical Rough-In | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Mark Moncarr
|
|
|
In Slab, underground, Area B. - Steve Hook is contact at ###-####. Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover conduit in area listed.
|
Electrical Rough-In | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Mark Moncarr
|
|
|
underground gym and UFER Phone #: ###-#### Inspection requested via web by Debby Pierce Ok cover grd work for gym, and 3/0 ufer.
|