General Inspection | 10/29/2018 | 10/29/2018 | 10/29/2018 | | PASS |
Andy J. Long
|
|
|
All parcels in Hollowrose Sub are now built upon. No subdivision work remaining. SFHs in progress on Maxwell are permitted seperately. No corrections.
|
DOC - Permit Finaled | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/12/2018 | 10/12/2018 | 10/12/2018 | | PASS |
Michael Zawacki
|
|
|
Last home exterior complete. Lot still needs to be landscaped. No ESC issues.
|
General Inspection | 9/27/2018 | 9/27/2018 | 9/27/2018 | | PASS |
Michael Zawacki
|
|
|
One home remains under construction. Street shows sign of sweeping.
|
General Inspection | 9/12/2018 | 9/12/2018 | 9/14/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/28/2018 | 8/28/2018 | 8/28/2018 | | PASS |
Michael Zawacki
|
|
|
One home remains under construction, the rest are landscaped and only interior remains. Some building material stored on sidewalk.
|
General Inspection | 8/13/2018 | 8/13/2018 | 8/13/2018 | | PART |
Michael Zawacki
|
|
|
Landscaper has gotten some dirt on sidewalk and road. Last two foundations poured, washout has been rinsed straight onto ground. Trackout from recent foundation pours.
|
General Inspection | 7/27/2018 | 7/27/2018 | 7/27/2018 | | PASS |
Andy J. Long
|
|
|
1 lot under excavation in Hollowrose. Other units near completion. No violations observed.
|
General Inspection | 7/12/2018 | 7/12/2018 | 7/12/2018 | | PASS |
Michael Zawacki
|
|
|
Project more than half complete. Washout has been dumped on vacant lot on south of project.
|
BMP Violation | 6/18/2018 | 6/27/2018 | 6/29/2018 | A | PEND |
Andy J. Long
|
|
|
check for washout clean up
|
General Inspection | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | FAIL |
Andy J. Long
|
|
|
Correction request:
- clean up washout that is full. - clean up the non-lined washout and provide new portable washout for next project.
Verbal correction request to RP/GC Andy.
|
General Inspection | 6/14/2018 | 6/14/2018 | 6/15/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/18/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Andy J. Long
|
|
|
check if new washout will be needed. for next round of foundations.
Need new washout, did not overflow but is now full. Need to have excavator sweep up recently excavated foundation. No trackout outside of sub. Trash contained.
|
General Inspection | 4/30/2018 | 5/16/2018 | 5/18/2018 | P | PASS |
Andy J. Long
|
|
|
No trackout or discharges.No earthwork occuring currently, finisih up two homes. No corrections requested.
Will need a new washout for next set of homes. Current washout about 65% full
|
General Inspection | 4/27/2018 | 4/27/2018 | 4/30/2018 | | PASS |
Andy J. Long
|
|
|
Storm drains have DI bags, concrete washout pit provided. Street and sidewalks are clean. Trash contained. Approved.
|
BMP Violation | 4/5/2018 | 4/12/2018 | 4/13/2018 | A | PASS |
Michael Zawacki
|
|
|
Area has been swept, sidewalks and road cleaned. Washout area has been cleaned.
|
General Inspection | 4/3/2018 | 4/3/2018 | 4/5/2018 | | FAIL |
Michael Zawacki
|
|
|
Entire site is covered with trackout. One concrete washout correctly built, large pile of washout right next to it just dumped on dirt. Site hasn't passed inspection in 2018. Took pictures and will send them to RP. Scheduled follow up for 4/12, if site not improved will hold inspections on other trades until site improved.
|
General Inspection | 3/16/2018 | 3/19/2018 | 3/19/2018 | P | FAIL |
Michael Zawacki
|
|
|
Lots of trackout throughout site. Painters are washing out into the dirt.
|
General Inspection | 3/14/2018 | 3/14/2018 | 3/16/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 | | PART |
Michael Zawacki
|
|
|
One home has overflowing trash box. Front end loader in use on corner lot causing trackout.
|
General Inspection | 2/9/2018 | 2/9/2018 | 2/9/2018 | | PART |
Michael Zawacki
|
|
|
Some trackout in neighborhood, not leaving site. Besides trackout site is clean, trash cleaned up.
|
General Inspection | 1/24/2018 | 1/24/2018 | 1/24/2018 | | PART |
Michael Zawacki
|
|
|
WIP on SFH. All workers parking on paved road. Some piles of scrap lumber that will need to be cleaned. Some trackout, coming from lot posted private and being used for firewood & rough cut lumber storage. No dirt leaving area and DI on ethridge clean and protected.
|
General Inspection | 10/23/2017 | 10/23/2017 | 10/23/2017 | P | PASS |
Andy J. Long
|
|
|
Work complete, parcels have been sold but are not yet active or stabilized. Large stockpile onsite. No discharges, trackout or other violations observed.
|