Site Final | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Michael Zawacki
|
|
|
Home is completed and landscaped. Will continue to monitor.
|
General Inspection | 10/2/2019 | 10/2/2019 | 10/2/2019 | | PASS |
Michael Zawacki
|
|
|
Lot has been landscaped. EcB INSTALLED ALONG SIDE PERIMETER AND ON HILLSIDE BELOW HOME.
|
General Inspection | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | FAIL |
Michael Zawacki
|
|
|
Landscapers running track steer through mud and onto street. Streets will need to be swept end of work day.
|
General Inspection | 9/5/2019 | 9/5/2019 | 9/5/2019 | | PASS |
Michael Zawacki
|
|
|
Home is completed, concrete work looks done. No landscaping has been installed.
|
General Inspection | 8/21/2019 | 8/21/2019 | 8/21/2019 | | PASS |
Andy J. Long
|
|
|
WIP. Home near completion, not yet landscaped. No corrections needed.
|
General Inspection | 8/6/2019 | 8/6/2019 | 8/13/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/22/2019 | 7/22/2019 | 7/22/2019 | | PASS |
Michael Zawacki
|
|
|
Exterior of home about complte. Crew on site getting driveway pad prepped, washout on site. Soil being spread on lot, not landscaped yet.
|
General Inspection | 7/5/2019 | 7/5/2019 | 7/5/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/20/2019 | 6/20/2019 | 6/20/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/5/2019 | 6/5/2019 | 6/5/2019 | | PASS |
Michael Zawacki
|
|
|
Front lot starting to be graded and prepped, backfill filling planter boxes on side. Rear of lot still has rilling and needs repairs from water coming off roof. No gutters yet, no trackout or blowing dust.
|
General Inspection | 5/21/2019 | 5/21/2019 | 5/21/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/6/2019 | 5/6/2019 | 5/8/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 4/19/2019 | 4/19/2019 | 4/19/2019 | | PART |
Michael Zawacki
|
|
|
Stucco has been cleaned up, paint still being dumped. Trash has been cleaned, still rilling.
|
General Inspection | 4/4/2019 | 4/4/2019 | 4/4/2019 | | FAIL |
Michael Zawacki
|
|
|
Lots of rilling and erosion coming off site and headed down hill. Stucco was dumped on hill and flowed down. Spoke to Chris Conner and stucco contractor while on site. Cleanup began while I was still there.
|
General Inspection | 3/20/2019 | 3/20/2019 | 3/21/2019 | | PEND |
Michael Zawacki
|
|
|
List of correction request sent to RP.
|
General Inspection | 3/5/2019 | 3/5/2019 | 3/6/2019 | | PASS |
Michael Zawacki
|
|
|
Corrections requested for area were made.
|
General Inspection | 2/14/2019 | 2/14/2019 | 2/15/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/28/2019 | 1/28/2019 | 1/30/2019 | | PASS |
Andy J. Long
|
|
|
WIP. No trackout or loose trash. Subdivsion BMPs installed.
|
General Inspection | 12/25/2018 | 12/25/2018 | 12/26/2018 | | PASS |
Michael Zawacki
|
|
|
BMPs still installed on hillside below home. Front is clean, no trackout onto sidewalk. Trash is contained. Workers parked on street not mud.
|
General Inspection | 12/10/2018 | 12/10/2018 | 12/11/2018 | | PASS |
Andy J. Long
|
|
|
No trackout or discharges. House is framed, downslope vegetation below home preserved. BMPs installed, RP on duty. No corrections requested.,
|
General Inspection | 5/4/2018 | 5/22/2018 | 5/23/2018 | P | PASS |
Michael Zawacki
|
|
|
Site excavated and forms are starting to be put in. Site will have its own outpak. Perimeter is protected.
|
Site Preparation | 5/4/2018 | 5/4/2018 | 5/4/2018 | A | PASS |
Andy J. Long
|
|
|
RP on site. Permit sign posted. Hillside wattles installed on perimeter. Further BMPs may be required after excavation.
|