General Inspection | 9/6/2019 | 9/6/2019 | 9/6/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Michael Zawacki
|
|
|
|
Site Final | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | NR |
Andy J. Long
|
|
|
Project complete and landscaped. Need to remove storm drain sediment bag installed north of site on Franklin Road.
Notified RP Chuck
|
General Inspection | 6/10/2019 | 6/10/2019 | 6/11/2019 | | PASS |
Michael Zawacki
|
|
|
Parking lot now paved, area still needs landscaping.
|
General Inspection | 4/23/2019 | 4/23/2019 | 4/23/2019 | | PASS |
Michael Zawacki
|
|
|
Exterior work completed. Trash is all in trailer. Parking area still needs to be paved.
|
General Inspection | 3/7/2019 | 3/7/2019 | 3/7/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/15/2019 | 1/15/2019 | 1/16/2019 | P | PASS |
Michael Zawacki
|
|
|
Ite surrounded with fencing and K-rail. Inlets on Franklin protected with witches hats. Garbage trailer on site and used. Circular access road is completely rocked. No issues observed at time of inspection.
|
General Inspection | 11/13/2018 | 12/4/2018 | 12/3/2018 | A | FAIL |
Andy J. Long
|
|
|
No construction entrance. Employees and material loading occuring in the mud off Rose HIll. DI bags installed, but need a stabilized construction access.
|
General Inspection | 11/13/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Andy J. Long
|
|
|
WIP on frame. No trackout, permit posted. Storm drain to west of entrance on Rose Hill and storm drain south of site on Franklin have sediment protection installed. Perimeter barricades and wattles keeping site contained.
|
General Inspection | 8/29/2018 | 9/4/2018 | 9/4/2018 | A | PASS |
Andy J. Long
|
|
|
Follow up on corrections to RP Chuck. He will have site swept and add additional BMPs as needed.
Sidewalk was swept as requested. No activity at time of inspection. No new violations observed.
Re-inspection fee removed due to RP requesting an inspection under the Public Works permit.
|
General Inspection | 8/27/2018 | 8/27/2018 | 8/27/2018 | A | FAIL |
Andy J. Long
|
|
|
- no site preparation inspection requested as noted on permit documents and project description - no ESC permit sign posted - no construction entrance installed - concrete washout poured on the ground within site, no contaiment
Only BMP is inlet protection on the MS4 inlets on Rose Hill and south of site on Franklin @ Roosevelt.
- need to pay for re-inspection fee , complete corrections, and schedule Site Preparation inspection.
|