General Inspection | 8/2/2019 | 8/2/2019 | 8/2/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 8/2/2019 | 8/2/2019 | 8/2/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 6/17/2019 | 6/17/2019 | 6/17/2019 | | PASS |
Michael Zawacki
|
|
|
All outside work completed, landscaping done, temporary BMPs removed. All work is now TIs inside.
|
General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/13/2019 | 3/13/2019 | 3/14/2019 | | PASS |
Michael Zawacki
|
|
|
Site contained, no dirt leaving site.
|
General Inspection | 1/17/2019 | 1/18/2019 | 1/22/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | PASS |
Michael Zawacki
|
|
|
Major ground disturbances completed, area around building still bare. Masond working on exterior, mortar mixer has secondary containment and washout on site. No dirt leaving site.
|
General Inspection | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on vertical. No trackout or dicharges from site or staging area across the street. Trash and materials are contained.
|
General Inspection | 8/20/2018 | 8/21/2018 | 8/22/2018 | A | PASS |
Andy J. Long
|
|
|
check on trackout control, construction entrance and dust control on the laydown yard east of 13th on and I-184 on-ramps. Project using it for staging and parking.
No trackout or discharges from site. WIP on vertical frame for office building.
ESC pernit sign posted. Okland will take care of any issues (trackout, discharges, dust) that arise from using the staging/laydown yard.
|
General Inspection | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on foundation. No trackout. Permit sign and SWPPP info posted inside entrance. MS4 inlet at 13th & Myrtle has sediment protection instaled.
Ecopan concrete washout pans being utilized to contain washout. No corrrections requested.
|
General Inspection | 6/1/2018 | 6/1/2018 | 6/1/2018 | A | PASS |
Michael Zawacki
|
|
|
Completed all permits as one large site inspection. Controlled entrance and exit, no trackout onto roads. Site is free from fugitive dust, all trash contained. Materials on site are neatly stored. Landscaping along front of hotel not yet completed. Panera Bread has no stucco washout, is being dumped on ground.
|
Site Preparation | 5/15/2018 | 5/16/2018 | 5/16/2018 | A | PASS |
Michael Zawacki
|
|
|
Met with Tom from Alta, did site walkthrough. He will talk to Syman to get a SWPPP & board on site, I left him some green permit signs. DIs are all protected, site will eventually be below sidewalk grade. Water wagon is on site, roads will need to be monitored for trackout, site has controlled access.
|
Site Preparation | 5/15/2018 | 5/16/2018 | 5/15/2018 | A | CANC |
Andy J. Long
|
|
|
|