Site Final | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Andy J. Long
|
|
|
Subdivsion construction complete, SFHs in progress.
All homes being built by Hammet Homes Homes, each have their own ESC permits.
BMPs inclufer DI bags, concrete washout, trackout control, fugitive dust control.
No further ESC inspections on this permit, homes are on Forsythia and Lassen.
|
General Inspection | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/14/2019 | 6/17/2019 | 6/18/2019 | P | PART |
Michael Zawacki
|
|
|
Permits not displayed on every activ lot. Dust blowing from road to washout, would like to see some rock to stabalize. Some dirt on sidewalks. Would like to see wattle on berm along Hill Rd.
|
General Inspection | 6/11/2019 | 6/11/2019 | 6/14/2019 | P | PASS |
Andy J. Long
|
|
|
|
Conference | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | PEND |
Andy J. Long
|
|
|
1 PM with Craig and Jay w/ Hammett Homes, which will be taking over subdivsion ESC responsibilities.
Corrections discussed:
- replace existing fiber mat sediment protection on storm drains in subdivision and on Forsythia - install lined concrete washout pit off Lassen with stabilized access, sign, - Hammett Homes is doing all homes (approx. 3 acres) so will need to file for LEW or CGP 2017 coverage. - clean up dumped concrete washout. - post subdivsion sign with information for subcontractors and public. Can post ESC permit signs here.
Reviewed employee parking, material unloading area, preserving vegetation on the lots, and keeping people off lots unless access is necessary. Requested that trash be contained
Dirt stockpiles to be regraded as part of the common area/park.
|
Complaint Inspection | 4/29/2019 | 4/30/2019 | 5/2/2019 | A | FAIL |
Andy J. Long
|
|
|
compaint that there is concrete (foundations) being poured for building
- uncontained concrete washout - no ESC permit sign posted at time of inspection
Verbal warning to RP/GC. Hammett Homes will be doing all homes in subdivsion. Onsite conference scheduled.
Hammett Homes has been warned that nay futher uncontained washout at this site will result in parcel holds and re-inspection fee.
|
General Inspection | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | DONE |
Michael Zawacki
|
|
|
Project is tiling the canal, ACHD project. They are dewatering into a bag within the canal. Turbidity of upstream water is 29.9 NTU, discharge point is 244 NTU. Refered to ACHD inspector.
|
General Inspection | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Andy J. Long
|
|
|
Sidewalk and road installed. No loose dirt leaving site , no trackout. Landscaping of sidewalk medians is in progress. Lots have volunteer vegetation sprouting. No corrections.
|
Random Inspection | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | FAIL |
Andy J. Long
|
|
|
Significant amount of dust clouds floating offsite. Landscape crew speeding around kicking up dust while re-distributing the stockpile. No water truck or other control onsite.
Verbal correction over phone to RP Eric. Will put landscape foreman on warning to.
|
General Inspection | 9/20/2018 | 9/20/2018 | 9/24/2018 | P | PASS |
Michael Zawacki
|
|
|
Work on Forsynthia is finished and street is paved. Road and sidewalk inside site complete, ne drain inlets are protected with blocksome. No dirt work at time of inspection, utilitie work looks completed and site is clean.
|
Complaint Inspection | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PART |
Andy J. Long
|
|
|
Dust complaint received.
No water truck on site at time of inspection. Only two machines working at time of inspection, dust levels were not bad. Talked to operator who stated they had moved a stockpile which created too much dust.
Verbal correction request to RP Eric: - install wattle to protect can at Stop sign at 33rd & Forsythia - have water truck onsite for rest of road and grading work
|
General Inspection | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PEND |
Andy J. Long
|
|
|
WIP on Forsythia utility connection to subdivision. Water truck on site for dust control. Dust occuring during loading operation, no dust when not unloading.
Follow up scheduled for post construction clean up of trackout and installation of cement washout for curbing.
|
Complaint Inspection | 6/28/2018 | 6/28/2018 | 6/28/2018 | P | PART |
Michael Zawacki
|
|
|
Construction entrance on Forsythia needs to be repaired. Site is free from dust during gusty winds. Hauling away fill material, some dust while dumping bucket into trucks. Road is torn up from sewer, hasn't been patched, some dust while trucks drive away down Forsythia, lots of dirt on road. Looks like trucks are pulling in and turning around on lot just before 34th, no rocks or other stabalization in area, rock pad should be constructed if area going to continue to be used as a turn around. Large stockpile on site has been sprayed with tackifier. Inlets on Lassen have been protected, very small construction exit built. Winds at time of inspection were blowing towards Hill & N 33rd.
|
General Inspection | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Michael Zawacki
|
|
|
Met with Capital Paving on site. Requested DI protection at 34th and Lassen and fabric under the entrances. A-core is on site on ACHD right of way doing sewers. No dust and some light track out.
|
Site Preparation | 6/15/2018 | 6/18/2018 | 6/18/2018 | A | PASS |
Andy J. Long
|
|
|
Approved for construction.
|
BMP Violation | 6/15/2018 | 6/15/2018 | 6/15/2018 | A | FAIL |
Andy J. Long
|
|
|
Work commenced without permits. temporary stop work order till ESC plan review. Double ESC permit fee assessed to project.
ESC plan to be submitted to division for review and approval.
|