Permit Information
Permit NumberESC18-01466
StatusFinaled
Name JARED WAGGONER
Site Address 592 N BENJAMIN LN
Project NameAmherst Madison westpark
Customer Number 
ePlanReviewNo
Description
Site development and construction of new commercial building. ESC BMPs insclude onsite site preparation inspection requirement, install heavy duty rock construction entrance, provide sediment protection on MS4 storm drain on Benjamin.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final5/12/20205/13/20205/13/2020PPASS
DetailsAndy J. Long
Work complete. BLD finaled, site landscaped, temp storm drain sediment bag removed. ESC permit finaled.
General Inspection5/12/20205/12/20205/12/2020 CANC
DetailsAndy J. Long
rescheduled for site final
General Inspection3/27/20203/27/20203/30/2020 CANC
DetailsAndy J. Long
Conference2/7/20202/10/20202/10/2020PPASS
DetailsAndy J. Long
Ecopan washout now staged onsite. Posted ESC permit sign at front of site. Most of crew is parked on street, some vehicles and equipment parked in mud within site. Minor trackout to Benjamin.

Discussed construction entrance installation, currently no rock entrance installed. Plan is to remove mud layer that has collected on top of preveiously placed pit run and install more pit run to build up site and prevent mud. Parking lot to installed March, in meanwhile will do sweeping and trackout control until more material can be placed.
General Inspection2/7/20202/7/20202/7/2020PDONE
DetailsAndy J. Long
parcel hold removed
BMP Violation2/7/20202/7/20202/7/2020PPEND
DetailsAndy J. Long
BMP Violation2/3/20202/7/20202/7/2020AFAIL
DetailsMichael Zawacki
Dumped washout.
Not cleaned, placing all trades hold on site. Talked to foreman on 2/3, wasn't concerned about dumped washout, asked what it was hurting. Contractor responsible for cleaning and scheduling follow up inspection.
General Inspection2/3/20202/3/20202/3/2020 FAIL
DetailsMichael Zawacki
Dumped washout. Talked to foreman in trailer and his response ws "what's it hurting". If not cleaned by follow up will fine site. Said they will clean it.
Rest of site is clean
General Inspection12/4/201912/18/201912/18/2019PPART
DetailsMichael Zawacki
Met with foreman on site.
Entrance has been covered, has some rock on site and will fix it.
WIP{p on steel framing, site is clean and no issues beside entrance.
General Inspection11/29/201912/3/201912/4/2019PPASS
DetailsAndy J. Long
No trackout or discharges. No rock construction entrance or trackout pad, employees parking in adjacent parking lot. No corrections at this time.
General Inspection11/29/201911/29/201911/29/2019 CANC
DetailsAndy J. Long
rescheduled
General Inspection10/11/201910/14/201910/14/2019PPASS
DetailsMichael Zawacki
Backfill being placed back in foundation. Water truck on site, washout on site. Benjamin is clean. No trash, some steel beams stored on site. Large backfill pile is stabalized.
General Inspection10/10/201910/10/201910/11/2019 CANC
DetailsAndy J. Long
General Inspection8/19/20198/19/20198/19/2019PPASS
DetailsMichael Zawacki
South side of lot being prepped for footings. Some steel trusses on lot, stockpile is weed covered and stable.
General Inspection6/3/20196/3/20196/3/2019PPASS
DetailsAndy J. Long
No activity at time of inspection. Site has been prepped with utilities, no vertical construction yet.

No violations observed
General Inspection5/30/20195/30/20195/30/2019PPASS
DetailsMichael Zawacki
No new activity. Stockpiles have growth, entrance still at site, area clean.
General Inspection2/26/20192/26/20192/26/2019PPASS
DetailsMichael Zawacki
Site prep looks complete, stockpile on site. No activity at time of inspection.
General Inspection1/9/20191/9/20191/9/2019PPASS
DetailsMichael Zawacki
Stockpile is surrounded by wattle. Rock entrance installed, DI on street protected. Site is graded and surveyed, no heavy equipment on site.
General Inspection12/10/201812/10/201812/10/2018PPEND
DetailsMichael Zawacki
Hauling out backfill, some trackout. Talked witj foreman and he will make sure its cleaned up.
General Inspection11/13/201811/27/201811/27/2018PPASS
DetailsMichael Zawacki
Site is rough graded, all slopes go into parcel, no perimeter BMPs at this time. Survey crews are on site marking location. Few stockpiles are on site. Rock construction entrance in good shape, drain inlet still has protection.
Site Preparation11/13/201811/13/201811/13/2018PPASS
DetailsAndy J. Long
Jared RP 3:00 PM site walk through

Construction entrance installed with lining and thick layer of rock. Some of it is not angular, reviewed construction specs with RP. Will refresh as needed.

Sediment protection installed on east side of Benjamin in front of site. Site appears to have positive slopes back into center of site, so no silt fence or wattle is required at this time. RP stated they will utilize an Ecopan washout when they are ready for foundation work.

This ESC permit can cover the GRD and forthcoming BLD permit for this project.