Permit Information
Permit NumberFIR18-00435
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1300 S BIRD ST
Project NameIdaho Humane Society
Customer Number 
ePlanReviewYes
Description
[Idaho Humane Society]
The fire sprinkler scope of work consists of protecting an animal hospital, supporting offices, retail and pet classroom. The two story building is designed as a tree with telescoping branch lines and predominately 4” mains. There is above and below protection. The above protection is utilizing concealed spaced sprinklers. There are a few attic sprinklers. The system has EQ bracing and floor level control valves.

• The underground piping is under permit FIR18-00408

[BLD17-02871]
The fire sprinkler system is used for unlimited area of the building. To construct a 40,175 square foot building (34,443 square feet 1st story and a 5,732 square feet 2nd story) to be used as an animal shelter, as an animal hospital, for supporting office, for retail sales, and as a pet training classroom. Work is to include concrete footings, concrete foundations, concrete slabs on grade, masonry exterior walls, exterior framed walls, steel columns, steel beams, glu-lam beams, bearing walls, roof trusses, EIFS, metal exterior wall panels, cement exterior wall panels, pre-cast concrete exterior wall panels, roof insulation installed on top of the roof deck, roof coverings, exterior windows, exterior awnings, exterior doors, a 2nd story floor constructed of concrete on a metal deck, an elevator to serve the 2nd story with an elevator pit and shaft, two stairways to serve the 2nd story, interior doors, interior windows, millwork, and finishes. Special Inspection is required for concrete, masonry, welding, bolting, and EIFS. A trash enclosure with masonry walls will also be constructed on site. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. This permit is intended to establish a Certificate of Occupancy for this tenant and for the entire building. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/11/20197/12/20197/12/2019PPASS
DetailsTroy Cobbley
Permit finaled

Josh Eaton is the contact for this final inspection. We appreciate your help with this. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection7/10/20197/12/20197/11/2019PCANC
DetailsTroy Cobbley
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Conference6/11/20196/12/20196/12/2019PDONE
DetailsJim Page
Per conversation with Ron Johnson, the material that Petra wants to move in needs to be non-combustible material, due to fire sprinklers not being monitored/active then material cannot be combustible. Moving in combustibles that are not associated with cunstruction is fuel loading and per Ron Johnson with Boise Fire this is not acceptable until active fire protection is in place.

Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro5/22/20195/23/20195/23/2019APASS
DetailsTroy Cobbley
First floor hydro test was witnessed with no visible loss.
INSP-Sprinkler Rough-in/Hydro5/21/20195/21/20195/21/2019PFAIL
DetailsTroy Cobbley
The first floor overhead hydro test failed due to visible loss on the guage.
INSP-Sprinkler Rough-in/Hydro5/20/20195/21/20195/21/2019APASS
DetailsTroy Cobbley
The 2nd floor overhead hydro test was witnessed with no loss of pressure.
INSP-Sprinkler Rough-in/Hydro5/16/20195/17/20195/17/2019PPASS
DetailsJim Page
Rough to cover inspection for remaining overhead fire sprinkler piping complete, all areas approved for cover. Hydrostatic test to be completed at a later date.



James Wells is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/2/20195/3/20195/3/2019APASS
DetailsTroy Cobbley
The rough-in is for 2 heads in the main west entrance hard lid passed. Piping can be covered. The contact says this can take place anytime today (5/2) or tomorrow (5/3). Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/29/20194/29/20194/29/2019PPASS
DetailsTroy Cobbley
See the city approved plans for locations where sprinkler piping can be covered. Noted several areas with deficiencies that will need to be addressed such as blocked heads and missing heads.

Jon Beazer is the contact. This is to be a partial rough-in. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in3/6/20193/7/20193/7/2019APASS
DetailsTroy Cobbley
First floor concealed spaces have been filled with insulation. They can now be covered.
INSP-Sprinkler Rough-in2/13/20192/14/20192/14/2019APASS
DetailsTroy Cobbley
The south lobby is ok for cover. The hardlid ceiling just inside of the main west facing lobby is ok for cover. Missing earthquake bracing on te mains has been provided except in garage area which needs to be verified for weight as discussed. Sprinkler coverage has been provided under the stairs. It appears that the wall layout on the upper level does not match the sprinkler plans and will need to be modified

Josh Eaton is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in1/16/20191/17/20191/17/2019APART
DetailsTroy Cobbley
Todays inspection was for the remaining building except for the canopies and the garage/risers. As per the previous inspection branchline restraints are missing and additional 90's have been added that need to be included in on the hydraulic calculations. Piping above the hardlids in the Hospital portion of the building is ok for cover. Wall in the other portions of the building are ok to be covered as long as it does not cover any concealed pockets. There is stil the issue of the Concealed Space sprinkler heads on the second floor that need resolved.


Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in1/15/20191/16/20191/16/2019APART
DetailsTroy Cobbley
Todays inspection was for the north half, first floor, of the building. I noted that not all of the additional 90's have been shown on the drawings or probably provided in the hydraulic calculations. I noted branchline restraints, earthquake bracing, and retaining straps are missing in most locations. It appears sprinkler protection will need to be added under the stairs east of the elevator. Also wood walls have been built in the non-combustible portion of the building and will need to be addressed as discussed. Plan mods will be needed for the added fittings to verify calculations. Combustible concealed spaces have not been addressed. No piping can be covered.


Josh Eaton is the contact for this RTC inspection. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Conference10/17/201810/17/201810/17/2018PDONE
DetailsTroy Cobbley
Tom and I discussed items that needed corrected.
INSP-Sprinkler Rough-in10/12/201810/15/201810/15/2018PFAIL
DetailsTroy Cobbley
Todays inspection was more of a conference. I went over issues such as combustible concealed spaces, sprinkler obstructions, missinge branchline restraints, missing earth quake bracing, missing upright protection. Basically we all agreed the plans need to be resubmitted showing all of the additional heads, additional piping, rerouted piping, additional fittings. It also appears the CC2 heads may not be able to be used on the second floor. Draft stops has not been installed for the CC2 heads. No approval for cover was given.
INSP-Sprinkler Rough-in10/2/201810/3/201810/3/2018PFAIL
DetailsTroy Cobbley
There were no city approved plans or documents on site. We did discuss what appears to be alot of blocked heads and combustible concealed spaces that will need addressed.


Richard Clark is the contact for this RTC inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus