INSP-Final Inspection | 7/12/2019 | 7/15/2019 | 7/15/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Brett Lawatch
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2019 | 4/29/2019 | 4/29/2019 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test for the south half of the project passed with no visible loss at the guage. Also corrections have been made as previously noted so all piping can be covered.
Contact is Jeff Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2019 | 4/25/2019 | 4/25/2019 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for all piping to the south of the dividing doors between the Cafeteria and Gym. Hydro test failed due to missing sprinkler heads, also piping size for the amount of heads at the south end of the corridor does not match plans. Two additional 90's and additional piping needs to be added to the Gym area hydraulic calculation.
CONTACT NAME IS JEFF. INSPECTION IS FOR TEN SPRINKLER HEADS. Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | A | PART |
Troy Cobbley
|
|
|
The Phase 1 work is complete. Forward flush testing passed. Robert Phone #: ###-####
|
INSP-Final Inspection | 3/20/2019 | 3/21/2019 | 3/21/2019 | A | CANC |
Troy Cobbley
|
|
|
Fire alarm was not ready. To be rescheduled. Robert Phone #: ###-####
|
INSP-Final Inspection | 3/19/2019 | 3/20/2019 | 3/20/2019 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow. Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2019 | 3/20/2019 | 3/20/2019 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed for the phase 1 area. Need to add sprinkler coverage in Display/Trophy case as discussed. Need plan modes for additional 90's for the remote area under the mezzanine.
Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled, Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/15/2019 | 3/18/2019 | 3/18/2019 | P | CANC |
Troy Cobbley
|
|
|
Not ready for inspection yet after onsite visit with Robert during a conference with the General Contractor. Will need city approved drawings and we also discussed the need for a hydro test for the phase 1 area. Will be rescheduled for the morning. Robert Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | PART |
Troy Cobbley
|
|
|
Hydro test held pressure but I found out not all piping has been cut/installed and the general contractor stated there was a leak in the Gym. Hydro will need to be redone. Rough-in passed for the Kitchen/Office/Dish Washing area and piping can be covered. Jeff Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations in the south side of building where sprinkler piping can be covered. I also looked at the overhead sprinkler piping in the Kitchen/Cooler area. Another rough-in inspection will be needed for cover when the T-bar and pendants in this area have been installed. Right now it is just the supply piping at the roof deck.
Cesear Phone #: ###-####
|
INSP-Supply line flush | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
Cesear Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | PASS |
Troy Cobbley
|
|
|
Underground Hydro passed. Rough to cover passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2018 | 11/6/2018 | 11/6/2018 | P | PART |
Troy Cobbley
|
|
|
Rough in for the underground supply line passed and the piping can be covered./ The Hydro for underground dedicated fire main failed due to visible loss at the guage.. Contact is Cesar Rodriguez Phone #: ###-#### Inspection requested via web by Brett Lawatch
|