INSP-Final Inspection | 1/22/2019 | 1/24/2019 | 1/24/2019 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
Tony Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/26/2018 | 12/28/2018 | 12/28/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead firte sprinkler piping on level 1 restroom/gym area complete. RTC for grid areas on level 1 complete, areas inspected approved for cover.
Contact is Mike Martin. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for level 1 witnessed, nio pressure loss observed.
Mike Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | PASS |
Troy Cobbley
|
|
|
The piping above the hardlids in Area "C" Restrooms at the east side of the building is ok for cover.
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/6/2018 | 12/7/2018 | 12/7/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkler piping located above hardlids in restrooms complete, approved for cover.
to cover, 1st floor // Tony Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/4/2018 | 12/5/2018 | 12/5/2018 | A | PART |
Jim Page
|
|
|
Rough in inspection for shell piping complete, a cover inspection will be required after pendant heads/arm overs are installed.
Tony Cetani is the contact and he would like a rough to cover inspection on piping. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above the hardlids in the east restrooms complete to include corridor, areas inspected approved for cover.
Tony Cetani is the Shilo foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans for the areas requested for inspection
Tony Cetani is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for hydro since all heads have not been cut in.
Tony Cetani is the contact. Thanks:) Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/30/2018 | 10/31/2018 | 10/31/2018 | P | DONE |
Jim Page
|
|
|
Consultation complete.
Consultation Phone #: ###-#### Inspection requested via web by Stan Beus
|