Information based on query as of Friday, May 10, 2024.
Permit Information
Permit NumberFIR18-00834
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3101 N SYCAMORE DR
Project NameFire Station #9
Customer Number 
ePlanReviewYes
Description
[Boise Fire Station #9]
The fire sprinkler scope of work consists of installing approximately 90' of 6" c900 to a stainless steel IBR, which will feed a 4" Ames Backflow and a single wet system. The building is VB, however all material above the ceiling-grid is non-combustible. The wet system is a split tree / grid system. The FDC is placed facing the main street where the architect desired its location. It is attached to the 2½ main of the grid portion of the system.

[BLD18-02497]
Demolition of the existing Fire Station #9, and construct a new 7,903 sq. ft. Fire Station with work to include general demolition, and site work and the construction of the fire station per the approved plans. Building to meet the 2012 International Green Construction Code (IGCC). This building is fully fire sprinklered for R-2 occupancy. CDM

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/17/201910/17/201910/17/2019PPASS
DetailsTroy Cobbley
Permit finaled

Todd Ketterling is the contact. This inspection should have already taken place, this is just the paper trail. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection10/15/201910/16/201910/16/2019PCANC
DetailsTroy Cobbley
To be rescheduled due to time constraints due to work load.Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro8/5/20198/6/20198/6/2019PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.

Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in8/6/20198/6/20198/6/2019PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.
INSP-Supply line flush8/2/20198/2/20198/2/2019PDONE
DetailsJim Page
Underground main line flush complete.

Todd Ketterling is the contact. Stacey with Suez is aware of this inspection, he and Todd are working out a specific time to meet there. Please contact them for that time. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro7/17/20197/19/20197/19/2019ADONE
DetailsJim Page
Hydrostatic test for underground supply witnessed, no pressure loss observed.

Troy Lowe is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/3/20197/3/20197/3/2019PPASS
DetailsJim Page
Rough to cover inspection for remaining underground supply complete, approved for cover.

Bryan Collins is the contact. He has already been in contact with Jim Page who has agreed to have this done today, he just needed the paper trail. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/20/20196/20/20196/20/2019PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above hardlids complete, hardlids approved for cover.

Jon Beazer is the contact. This rough-in is for the hard lids. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/24/20195/28/20195/28/2019APART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping complete, a cover inspection will be required for pendant heads/arm overs before cover can be approved.

Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in1/8/20191/8/20191/8/2019PPART
DetailsJim Page
Rough to cover ins[pection for IBR complete, IBR approved for cover, remaining underground supply to be installed at a later date.