INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection complete.
Please call Tanner 30 minutes prior at ###-#### Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 4/10/2019 | 4/11/2019 | 4/11/2019 | P | FAIL |
Jim Page
|
|
|
Replace fire sprinkler head that was painted. Add missing sidewall in level 3 apartment.
Contact Tanner Loomis - ###-#### 30 min prior to Fire Final insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | DONE |
Jim Page
|
|
|
24 hour air test for dry system complete.
Contact Tanner Loomis ###-#### 30 min Prior to 24 HR pressure Test start please, all Fees were PAID...04/08/19 AM...
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2019 | 4/9/2019 | 4/9/2019 | A | DONE |
Jim Page
|
|
|
Level 1 wet system hydro witnessed, no pressure loss observed.
Contact Tanner Loomis ###-#### 30 min Prior to Hydro Insp start please, all Fees were PAID...04/08/19 AM...
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2019 | 4/8/2019 | 4/8/2019 | P | PART |
Jim Page
|
|
|
24 hour air test started at 12PM with 42 PSI
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2019 | 4/8/2019 | 4/8/2019 | P | CANC |
Jim Page
|
|
|
Permit fees need to be paid before inspection can be performed, permit has fees due at time of this entry, this request is cancelled.
Contact Tanner Loomis ###-#### 30 min prior to 24 Hr Pressure Test please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/8/2019 | 4/8/2019 | 4/8/2019 | P | CANC |
Jim Page
|
|
|
Permit fees need to be paid before inspection can be performed, permit has fees due at time of this entry, this request is cancelled.
Contact Tanner Loomis ###-#### 30 Min Prior to Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | FAIL |
Jim Page
|
|
|
Level 1 wet system lost 11 PSI during test.
Contact Tanner Loomis ###-#### 30 min prior to RTC insp Start of the 1st Floor and Dry System please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2019 | 4/5/2019 | 4/5/2019 | A | PART |
Jim Page
|
|
|
Hydrostatic test for dry system witnessed, no pressure loss observed.
|
INSP-Sprinkler Rough-in | 4/1/2019 | 4/4/2019 | 4/4/2019 | P | FAIL |
Jim Page
|
|
|
Both dry system and small wet system lost pressure, 6 PSI on dry, 15 PSI on small wet system. Larger wet system had no pressure loss observed.
Contact Tanner Loomis - ###-#### 30 Min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/14/2019 | 1/14/2019 | 1/14/2019 | A | PASS |
Jim Page
|
|
|
Rough in inspection for dry system complete.
Contact Noemi Carrero ###-#### 30 min prior to RTC Insp on DRY SYSTEM start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Supply line flush | 1/11/2019 | 1/14/2019 | 1/14/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Contacts will be Tanner Loomis - PFP ###-#### ; Stacy Stuart - SUEZ ###-####..All Parties would like to request a 9:00AM start time if possible, if not please let them know.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Supply line flush | 1/9/2019 | 1/11/2019 | 1/11/2019 | A | CANC |
Troy Cobbley
|
|
|
Canceled and rescheduled for monday as per contact.
Contact Tanner Loomis at ###-#### 30 mins before UG Flush insp please Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/4/2019 | 1/7/2019 | 1/7/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for level 1 wet system sprinkler piping complete, level 1 wet system approved for cover.
Contact Noemi Carrero - ###-#### 30 Min prior to RTC Insp for 1st floor wet system please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 12/31/2018 | 1/2/2019 | 1/2/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkkler piping located on levels 2 and 3 complete, levels 2 and 3 approved for cover.
Contact Andrew Larson ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. No inspection was performed.
Tanner Phone #: ###-####
|