INSP-Final Inspection | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
George Jess is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 1/13/2020 | 1/14/2020 | 1/14/2020 | A | CANC |
Troy Cobbley
|
|
|
Wrong permit scheduled.
George Jess is the contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2019 | 12/20/2019 | 12/20/2019 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro was witnessed with no pressure loss.
George Jess is the contact. This is for an UG Hydro. Thanks for all you do. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | CANC |
Troy Cobbley
|
|
|
George Jess is the contact for this UG Hydro/ Flush inspection. We have arranged with Stacey @ Suez to do it around 1 or 1:30 pm. We hope this will work with your schedule too. Thank you so much for all your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Troy Cobbley
|
|
|
The supply line flush witnessed.
George Jess is the contact for this UG Hydro/ flush inspection. We have arranged with Stacey @ Suez to do it around 1 or 1:30pm. We hope this will work with your schedule too. Thank you so much for all your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground supply piping is ok for cover. Bryan Collins is requesting a Underground Rough in Inspection.
Thank you Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | CANC |
Troy Cobbley
|
|
|
Will need to be rescheduled. Can not make it due to work load and personell shortage. Bryan Collins is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/10/2019 | 9/10/2019 | 9/10/2019 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover from the point of connection to the last 45 fitting. The IBR, when installed, will need cover inspection.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/6/2019 | 9/9/2019 | 9/9/2019 | P | FAIL |
Troy Cobbley
|
|
|
Apparently due to the weather the holes that had been left open for inspection have filled with mud/dirt. The supply piping is not visible. Piping needs to be uncovered and an inspection re-scheduled. Jon Beazer is the contact for the underground RTC. He is hoping for an PM appointment. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for the underground supply piping that is ok for cover.
Jon Beazer is the contact. Please call ahead of time so someone can meet the inspector out there. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|