Permit Information
Permit NumberBLD19-03209
StatusIssued
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 1720 N WESTGATE DR
Project NameDp.of Health & Welfare Remodel
Customer Number 
ePlanReviewYes
Description
(DEPARTMENT OF HEALTH & WELFARE) //7-06-2020 PLAN MODIFICATION TO CREATE OPEN WORKSPACE INSTEAD OF INDIVIDUAL OFFICES, RECEPTION/OFFICE AREA REVISED TO ELIMINATE HALLWAY, REVISED PLANS TO RETAIN ONE EXISTING OFFICE AND ELEMINATE ANOTHER, REVISED PLANS TO ADD STAFF MEETING ROOM AND ADDITIONAL MEETING ROOM AT LOBBY // This building is fire sprinkled for building area increase and for code trade-offs. Certificate of completion to be issued upon completion. Permit to remodel the interior of an existing 73,639 square foot building for the current tenant. Work is to include replace exterior door with storefront glazing, one new exterior door, replace exterior door with new window, interior nonbearing walls, interior doors, interior windows, new fixtures / accessories and finishes in existing bathrooms, new millwork, select new finishes, mechanical work, electrical work, and plumbing work. The work is required to comply with the approved drawings, and with all applicable codes and ordinances. Interior finishes shall be in compliance with Ch. 8 of the 2015 IBC. Any alterations or modifications to the buildings fire sprinkler or fire alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise fire department. MDH
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/10/20208/11/20208/11/2020AFAIL
DetailsTroy Cobbley
Inspection was for phase 3 and 4. Need the fire alarm addressed in these areas, Need exit signs and emergency lightys repaired.

Schedule with fire alarm at 7am. Thank you Phone #: ###-#### Inspection requested via web by tom mccalister
FIRE-Final Inspection8/3/20208/3/20208/3/2020PFAIL
DetailsTroy Cobbley
Inspection was for the remodeled restrooms. The new fire alarm notification system needs to be extended into this remodeled area.

screened // TOm Phone #: ###-####
BLD-Framing/Rough-in7/31/20208/3/20208/3/2020APART
DetailsTell Riley
Give Tom a call when in route. Phone #: ###-#### Inspection requested via web by tom mccalister//phase 4 temp ok pending fire life safety temp//phase 5 framing of training room and vestibule ok per plans//
BLD-Ceiling Grid Inspection7/20/20207/21/20207/21/2020APART
DetailsTell Riley
screened // Tom Phone #: ###-####//phase 4 restrooms and phase 5 hall and conference room, grid ok pending mechanical//
BLD-Ceiling Grid Inspection7/20/20207/20/20207/20/2020PNR
DetailsMike Jordan
Tom - */Screened*/ Phone #: ###-####. Needs fire sprinkler rough in inspection.
BLD-Framing/Rough-in6/16/20206/17/20206/17/2020APART
DetailsTell Riley
Tom *screened* Phone #: ###-####//Phase 4, two offices, ok per plans//
BLD-Framing/Rough-in6/10/20206/10/20206/10/2020PPART
DetailsTell Riley
Screened- Tom Phone #: ###-####//phase 5- conference room--walls not full height per plan--Tom will provide details of using shorter braced walls per the architect// maintain 4'6" corridor width per the plans//phase 4 employee restrooms--center wall demo to increase size--no new framing--pending plumbing approval//
BLD-Ceiling Grid Inspection5/18/20205/18/20205/18/2020PPART
DetailsTell Riley
Screened // Tom Phone #: ###-####//phase 3 and a portion of phase 4//fix clips in areas noted prior to floodinng grid//
BLD-Framing/Rough-in4/30/20204/30/20204/30/2020PPART
DetailsTell Riley
Please give me a call when you are on your way. Phone #: ###-#### Inspection requested via web by tom mccalister//phase 3 restrooms and open work room, wall framing ok, add bracing at double/plumbing wall//
BLD-Framing/Rough-in4/9/20204/9/20204/9/2020PPART
DetailsTell Riley
screened // Tom Phone #: ###-####//phase 3, 1 wall, ele passed//ok to cover//
BLD-Framing/Rough-in3/10/20203/11/20203/11/2020APART
DetailsTell Riley
Tom Phone #: ###-####//area 3A walls ok to cover//
BLD-Final2/18/20202/19/20202/19/2020PPART
DetailsTell Riley
Tom Phone #: ###-####//phase 2 temp occupancly approved//wall at start of phase 3 ok to cover//
FIRE-Final Inspection2/18/20202/19/20202/19/2020APART
DetailsTroy Cobbley
Life safety for phase 1 and phase 2 is complete.

Tom Phone #: ###-####
BLD-Final2/14/20202/18/20202/18/2020ACANC
DetailsTell Riley
Tom Phone #: ###-####//cancel per Tom//
FIRE-Final Inspection2/14/20202/18/20202/18/2020ACANC
DetailsTroy Cobbley
Need the project related fire alarm permit finaled prior to a life safety sign off.

Tom Phone #: ###-####
BLD-Ceiling Grid Inspection1/22/20201/23/20201/23/2020PPART
DetailsTell Riley
TOM Phone #: ###-####//phase 2 grid//ok pending mechanical this afternoon//wing wall ok//
BLD-Framing/Rough-in12/26/201912/27/201912/27/2019PPART
DetailsTell Riley
Tom Phone #: ###-####//phase 2 wall framing--areas without plumbing--ok to cover//
BLD-Final12/3/201912/3/201912/3/2019PPART
DetailsTell Riley
Tom Phone #: ###-####//phase 1 temp occupancy approved//
FIRE-Final Inspection12/2/201912/3/201912/3/2019APART
DetailsTroy Cobbley
Life safety passed for Phase 1/Building B. Will need the project related fire alarm permit finaled prior to a Phase 1 sign off.

Tom Phone #: ###-####
BLD-Ceiling Grid Inspection11/13/201911/13/201911/13/2019PPART
DetailsTell Riley
Building B // Tom Phone #: ###-####//grid looks ok//pending mechanical inspection//
BLD-Framing/Rough-in10/11/201910/11/201910/11/2019PPART
DetailsTell Riley
Tom Phone #: ###-####//moved wall 10 inches//new electrical inspection was completed//bracing ok//
BLD-Framing/Rough-in10/4/201910/7/201910/7/2019APART
DetailsTell Riley
Tom Phone #: ###-####//area B wall framing and demo//walls ok to cover area B only//plumbing and electrical approved///