Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD18-00776
StatusIssued
Name PERKINS CONSTRUCTION
Site Address 2800 S MAPLE GROVE RD
Project NameMaple Grove Elem Addition
Customer Number 
ePlanReviewYes
Description
(MAPLE GROVE ELEMENTARY) **(Project Management - Ron Hill)""Green Tag""** Special inspections are required per the attached form 310. This project consists of constructing a 12,003 sq. ft. addition to an existing 45,000 sq. ft. elementary school. The addition includes a gymnasium and support spaces, 5 new classrooms, minor site upgrades, and minor utility work per the approved plans. The new building will be fully fire sprinklered and alarmed. The existing 45,000 sq. ft. building is considered a separate building and will be fire sprinklered per the attached upgrade agreement by December of 2019. The walls separating the new and existing building are to be constructed per the attached code modification. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/21/20198/21/20198/21/2019PPART
DetailsMike Jordan
Ok for temp occ. Final occ pending public works approval, zoning approval, fire/life safety giving perm occ. and completing the envelope for 1hr. construction in riser room, providing final letter from special inspection agency and posting the correct occupant load sign in gym.
FIRE-Final Inspection8/21/20198/21/20198/21/2019PFAIL
DetailsTroy Cobbley
The "trouble" issues with the fire alarm panel need resolved prior to a to a final for the life safety. Ron Phone #: ###-####
FIRE-Final Inspection8/15/20198/15/20198/15/2019PPART
DetailsTroy Cobbley
A temp for life safety is being given with Boise Fire approval until the project related fire alarm permit is finaled the exit discharge light is repaired and the fire hydrant issue is addressed.

Phone #: ###-####
FIRE-Final Inspection8/14/20198/14/20198/14/2019PFAIL
DetailsTroy Cobbley
Need the project related fire alarm and fire sprinkler permits finaled, need the fire hydrant addressed, need the west exit discharge light addressed. Ron Phone #: ###-####
FIRE-Final Inspection8/9/20198/12/20198/12/2019AFAIL
DetailsJim Page
Project related FIR permits need to inspected and finaled before life fire safety. Informed point of contact on 09AUG2019 that the fire hydrant on the southeast side of project is pointed the wrong way, steamer connection needs to be pointing at the fire lane, response was "I think that was the school disticts scope". Fire hydrants are on page A1.01 and are part of the new scope of work. Hydrant on the northwest side is in different location than what is shown on the city approved drawings. No other items inspected at this time.

Ron Phone #: ###-####
BLD-Ceiling Grid Inspection6/13/20196/13/20196/13/2019PPASS
DetailsMike Jordan
Charlie Phone #: ###-####
BLD-Ceiling Grid Inspection6/3/20196/3/20196/3/2019PNR
DetailsMike Jordan
Charlie Phone #: ###-####
BLD-Framing/Rough-in5/6/20195/6/20195/6/2019PPART
DetailsBrandon Shaw
Vestibule lid, between new building and existing...
BLD-Wall Bracing4/17/20194/17/20194/17/2019PPASS
DetailsMike Jordan
Charlie- nailing Phone #: ###-####. Box out of intercom box in 1hr. wall ok.
BLD-Framing/Rough-in4/9/20194/9/20194/9/2019PPASS
DetailsMike Jordan
Charlie Phone #: ###-####. Interior steel stud framed walls and hardlids for classrooms and restrooms ok to cover.
BLD-Framing/Rough-in3/27/20193/28/20193/28/2019APASS
DetailsMike Jordan
Charlie Phone #: ###-####. Reamainder of anchor bolts on exterior shear walls.
BLD-Framing/Rough-in3/21/20193/22/20193/22/2019APASS
DetailsMike Jordan
Charlie Phone #: ###-####. Interior steel stud framed walls for resrooms, storage rooms off of gym between grids 2 and 3.
BLD-Wall Bracing3/14/20193/15/20193/15/2019APASS
DetailsMike Jordan
Nailing inspection-Charlie Phone #: ###-####
BLD-Wall Bracing3/12/20193/13/20193/13/2019APASS
DetailsMike Jordan
Nailing inspection- Charlie Phone #: ###-####
BLD-Framing/Rough-in2/8/20192/11/20192/11/2019APASS
DetailsMike Jordan
Charlie Phone #: ###-####. Interior bearing wall on gridline 3 ok toone side.
BLD-Wall cover1/14/20191/14/20191/14/2019PPASS
DetailsMike Jordan
Charlie Phone #: ###-####. Interior side of 1hr. wall ok.
BLD-Wall Bracing1/14/20191/14/20191/14/2019PPART
DetailsMike Jordan
Charlie Phone #: ###-####. Exterior walls, work in progress.
BLD-Wall cover1/9/20191/9/20191/9/2019PPART
DetailsBrandon Shaw
Fire wall, West side, seams mud and taped...
BLD-Wall Bracing1/8/20191/8/20191/8/2019PPASS
DetailsMike Jordan
shear // Charlie Phone #: ###-####inner layer of 5/8 densae glass for shear and 1hour assembly ok.
BLD-Framing/Rough-in1/2/20191/3/20191/3/2019APART
DetailsMike Jordan
Charlie Phone #: ###-####. Infill for existing window.
BLD-Foundation12/6/201812/6/201812/6/2018PPART
DetailsBrandon Shaw
Interior footings cleaned...
Contractor is going to keep covered until Tues, 11Dec2018, 5 days...
BLD-Concrete12/3/201812/4/201812/4/2018APART
DetailsMike Jordan
slab on grad // Charlie Phone #: ###-####. Needs to clean bottom of interior thickend footings and provide dobees.
BLD-Foundation11/5/201811/6/201811/6/2018PPART
DetailsMike Jordan
stem wall // Charlie Phone #: ###-####
BLD-Footing10/31/201811/1/201811/1/2018ADEFR
DetailsMike Jordan
Charley Phone #: ###-####
BLD-Footing10/30/201810/31/201810/31/2018APART
DetailsMike Jordan
Charlie Phone #: ###-####. Work in progress on footing next to existing building on grids 4.9 and B.6.
BLD-Concrete10/15/201810/16/201810/16/2018PPART
DetailsMike Jordan
Charlie Phone #: ###-####. Work in progress on installing reiforcement for thickend footing and interior slab on grade. Will have specail inspection.
BLD-Foundation9/18/20189/18/20189/18/2018PPART
DetailsMike Jordan
steam wall // Charlie Phone #: ###-####. Work in progress. Will hve special inspection, perimeter stemwalls.
BLD-Footing9/6/20189/7/20189/7/2018PPART
DetailsMike Jordan
Charlie Phone #: ###-####. Perimeter footings. Noted insufficient clearances from bottom rebar. Will have special inspection. Special inspector to verify correction. Placement will be on Monday Sept. 10th.
Issue PAID IN FULL permit  7/31/2018 DONE
Print Occupancy Form  7/31/2018 DONE
OVERRIDE  7/16/2018  
Permit Ready to Issue  7/16/2018  
Need:
Revised value (DO NOT CHARGE OVER STATE PLAN CHK FEES)

MET
GC Form
RP-met
Plan assigned to (CDM)3/19/20183/19/20187/14/2018 PASS
DetailsCarl D Madsen
Maple Grove Elementary
PLANS/APPL TAKEN TO FRONT DESK  7/14/2018 DONE
Routing - FIRE6/23/20186/23/20187/10/2018 PASS
DetailsErika Akin
Attached comments to case
Plan Reviewer's activity  7/10/2018 
DetailsErika Akin
Verbal approval of code alternate and upgrade agreement from Ron Johnson
Routing - PLAN CHECK6/23/2018 7/6/2018 PASS
DetailsCarl D Madsen
Passed pending code modification approval
Routing Off Site - STRUCTURAL5/3/2018 6/23/2018 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK5/3/2018 6/23/2018 PASS
DetailsCarl D Madsen
Routing - FIRE5/3/20185/3/20185/17/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - FIRE4/16/20184/16/20184/26/2018 FAIL
DetailsErika Akin
Attached comments to case
Routing Off Site - STRUCTURAL4/16/2018 4/26/2018 FAIL
DetailsCarl D Madsen
Routing - ELECTRICAL4/16/2018 4/26/2018 PASS
DetailsJavier Guzman
Routing - PLAN CHECK4/16/2018 4/26/2018 PASS
DetailsCarl D Madsen
Routing PW Drainage4/17/2018 4/17/2018 PASS
DetailsBrian Murphy
Route to Impact Fee Review3/31/20184/3/20184/2/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  3/31/2018 FAIL
Routing Off Site - STRUCTURAL3/19/2018 3/31/2018 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK3/19/2018 3/31/2018 FAIL
DetailsCarl D Madsen
Routing - MECHANICAL3/19/2018 3/26/2018 PASS
DetailsTroy James
Routing - FIRE3/19/20183/19/20183/23/2018 FAIL
DetailsScott Arellano
Attached comments to case and emailed architect.
Routing PW Drainage3/19/2018 3/20/2018 FAIL
DetailsBrian Murphy
NEED SEEPAGE BED PERC TEST
Routing - ELECTRICAL3/19/2018 3/20/2018 FAIL
DetailsJavier Guzman
1) Under sized service feeders
Routing - PLUMBING3/19/2018 3/19/2018 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - PLANNING3/19/2018 3/19/2018 PASS
DetailsCeline Acord
per CUP18-00009
Routing - Addressing3/19/2018 3/19/2018 PASS
DetailsDoug Chausow
Routing - Erosion and Sediment3/19/2018 3/19/2018 PASS
DetailsMichael Zawacki
Valid RP needed. Site inspection required.
Intake Approval  3/19/2018 PASS
Application received  3/7/2018 DONE
Application submitted via PDS Online on Mar 7 2018 7:47AM
Agreement of Future work8/16/201812/31/2020   
DetailsJoe Bruce
(MAPLE GROVE ELEMENTARY) 8/16/18 Upgrade Agreement attached to this case. Work to be completed by 12/31/19.
12/4/19 Fire alam work has been completed. A new Upgrade Agreement attached to this case to allow more time to upgrade the fire sprinkler system and insulate the intersitial space.
Routing - PUBLIC WORKS4/16/2018    
DetailsRachael Beierle