Permanent Service | 7/23/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Mark Moncarr
|
|
|
Service inspection to turn on main power to building. Call Lonny when on-site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Service to be energized so a few spider boxes can be placed throughout for contruction power. All equiptment has been tested and approval stickers placed on equipt by testing agency. p/s u/g n ok
|
Electrical Rough-In | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PASS |
Mark Moncarr
|
|
|
UFER inspection for the on-site generator. Have pictures and will send. If you have questions please call. ###-####. Thanks, Lonny Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover 3/0 copper for ufer on generator.
|
Electrical Rough-In | 3/4/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Mark Moncarr
|
|
|
Wall rough-in inspection 3rd floor area ''A'' west block of exam rooms, all of north rooms, and south lobby. Also need conference concerning clearance of split unit 1st floor emergency electrical room 1E292. Call Lonny when on site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed. 3rd floor elec room has 3 mini splits. Center mini split cannot be above elec UPS 110.26(E)(1)(A) Equipt needs minimum 6' clearence above from any foreign systems
|
Electrical Rough-In | 2/26/2020 | 2/27/2020 | 2/27/2020 | P | PASS |
Mark Moncarr
|
|
|
Wall rough-in inspection 3rd floor area ''A'' MOB, excluding x-ray rooms and utility yard under ground duct bank conduits. Call Lonny when on site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover walls 3rd floor Center and East exam rooms, and duct bank on SE corner of property.
|
Electrical Rough-In | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Mark Moncarr
|
|
|
1st floor MOB grid lines 5W-7.5W ; B-D.5 wall rough-in. Call Lonny when on-site. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed
|
Electrical Rough-In | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Mark Moncarr
|
|
|
2nd floor MOB area ''A'' west side wall rough-in and 1st floor MOB area ''A" west side exam rooms wall rough-in. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed
|
Electrical Rough-In | 1/16/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Mark Moncarr
|
|
|
Wall rough-in inspection 2nd floor east side of area ''A'' MOB. Call Lonny when on site, ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover 2nd floor N side offices, and exams rooms.
|
Electrical Rough-In | 12/12/2019 | 12/16/2019 | 12/16/2019 | A | PASS |
Mark Moncarr
|
|
|
Rough-in wall inspections for 1E288 Fire Pump Riser Room and 5th floor MOB Penthouse. Call Lonny when on-site.Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed
|
Electrical Rough-In | 12/4/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Mark Moncarr
|
|
|
Requesting inspection for 4th floor Penthouse wall rough-in and 5th floor Rooftop wall rough-in. Call Lonny when on site, Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover MLB rooftop and Hospital penthouse.
|
Electrical Rough-In | 11/19/2019 | 11/21/2019 | 11/21/2019 | P | PASS |
Mark Moncarr
|
|
|
Wall inspection 2nd floor area- D rooms: 2E045A, 2E140-2E142, 2E154-2E156, 2E162, 2E163, 2E170, 2E171, 2E232, 2E233, ; 2E250-2E256. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed.
|
Electrical Rough-In | 11/8/2019 | 11/12/2019 | 11/12/2019 | P | PASS |
Mark Moncarr
|
|
|
Wall inspection 2nd floor area ''D'' PACU rooms 2E151, 2E157-2E161, 2E164-2E169, ; 2E172. Call Lonny when on site ###-####, thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed except bathroom at top of stairs.
|
Electrical Rough-In | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Mark Moncarr
|
|
|
SOG conduit inspection area A 1st Floor and area C roof wall rough-in. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover grd work for Area A, 2 cad welds. Cover for duct bank on SE corner, and conduits for generator also SE corner.
|
Electrical Rough-In | 10/2/2019 | 10/3/2019 | 10/3/2019 | P | PASS |
Mark Moncarr
|
|
|
Need wall inspection for the following rooms 2nd floor area C/D: 2E216A, 2E227, 2E228, 2E229, 2E230, 23231, 2E236, 2E237, ; 2E238. Call Lonny when on site ###-####. Thanks Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover areas listed except vendor room. Sheetrock and insulation is being installed in areas that still need electrical. Talked to Lonny and asked him to get with sheet rockers and let them know how far down they can go so as not to cover any electrical installations. If these areas are covered after being told, all sheetrock in areas will be removed before inspection.
|
Electrical Rough-In | 9/27/2019 | 9/30/2019 | 9/30/2019 | P | PASS |
Mark Moncarr
|
|
|
Roof top wall inspection 4th floor area D. Conference on transformer clearance in electrical rooms. Call Lonny when on site. ###-####. Thanks Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover rest of parapet top floor SE corner. Discussed elec room on 2nd floor for transformer clearences.
|
Electrical Rough-In | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Mark Moncarr
|
|
|
Rough-in inspection of roof top walls level 3 ; 4. Call Lonny when on site, ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover parapet S center and SE corner.
|
Electrical Rough-In | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Mark Moncarr
|
|
|
Need inspection of lightning protection system being installed at ground level. Call Lonny when on site. Thanks, Lonny Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover 4/0 lightning protection. 27 locations around building that are cad welded to building steel. a long with 27 grd rods that will also be of cad weld connection. Plans call for grd rods roughly every 60ft.
|
Electrical Rough-In | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | PASS |
Mark Moncarr
|
|
|
Wall inspection 3rd floor east roof area and transformer ground for electrical room 1E212. Call Lonny when on site. ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover walls for 2 parapets, 1 on E side and 1 on S side to left of stairwell. 2 trans grounds bonded to building steel.
|
Electrical Rough-In | 8/14/2019 | 8/15/2019 | 8/15/2019 | A | PASS |
Mark Moncarr
|
|
|
Inspection requested for duct bank on east side of project and 1E260 Electrical Room transformer grounding. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Building steel bonding at elect rm listed. Ok cover trench E side.
|
Electrical Rough-In | 8/2/2019 | 8/5/2019 | 8/5/2019 | P | PASS |
Mark Moncarr
|
|
|
Inspection of east side duct bank and main electrical room grounding to column. Call Lonny when on site ###-####. Thanks. Phone #: ###-#### Inspection requested via web by Lonny Baum Ok cover duct bank E side building, and bonding of building steel via cad weld.
|
Telephone call | | | 7/23/2019 | | DONE |
|
|
|
Per Tom the rough in and perm. serv. inspection should have been done on ELE19-02481. took inspection out of the activites of this permit and put in other. Tom stated he would call Lea Electric to find out where this permit needs to go.
|
Issue PAID IN FULL permit | | | 6/17/2019 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/17/2019 | | DONE |
|
|
|
This permit was created on the web by Cathy Duchek
|