Permit Information
Permit NumberESC18-00027
StatusFinaled
Name JASON JONES
Site Address 2980 S MILLBROOK WAY
Project NameParkcenter Blvd, Warm
Customer Number 
ePlanReviewNo
Description
Completion of Parkcenter Blvd between Millbrook and Warm Springs bypass. Includes box culvert work to connect channel of Warm Springs Creek to the new re-alignment south of Parkcenter. Some work also along Creek @ Warm Springs bypass, see also ESC17-00774. ESC plan approved, LEW filed. Work is hoped to be completed before spring runoff. Site preparation inspection required.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection3/14/20193/14/20193/19/2019 PASS
DetailsAndy J. Long
Road construction, sidewalks, landscaping complete. No ESC corrections. ESC permit finaled.
DOC - Permit Finaled3/19/20193/19/20193/19/2019PPASS
DetailsAndy J. Long
General Inspection2/27/20192/27/20192/27/2019 PASS
DetailsMichael Zawacki
Inspected 2-26. Work complete and area planted. Will need to watch for erosion along top and edge of culvert on south side.
General Inspection2/12/20192/12/20192/13/2019 PASS
DetailsMichael Zawacki
General Inspection1/28/20191/28/20191/28/2019 PASS
DetailsMichael Zawacki
Area landscaped and hydroseeded. Area on north side hasn't been stabalized.
General Inspection1/11/20191/11/20191/11/2019 PASS
DetailsMichael Zawacki
Road and landscaping complete. No work on new homes in area.
General Inspection12/27/201812/27/201812/27/2018 PASS
DetailsMichael Zawacki
Inspected 12/26.
Work completed and being stabalized.
General Inspection12/12/201812/12/201812/13/2018 PASS
DetailsMichael Zawacki
BMPs still installed around culvert. Area still bare and waiting for growth. No rills or erosion.
General Inspection11/27/201811/27/201811/27/2018 PASS
DetailsAndy J. Long
Work complete. Monitoring creek and runoff areas into Warm Springs. No violations observed.
General Inspection11/9/201811/9/201811/9/2018 PASS
DetailsMichael Zawacki
Road and landscaping complete.
General Inspection10/25/201810/25/201810/26/2018 PASS
DetailsMichael Zawacki
Work completed. Wattle has been installed along perimeter of creek. Lots of wind blown trash in creek, HOA or other group needs to over creek and work on keeping it clean.
General Inspection10/9/201810/9/201810/9/2018PPASS
DetailsAndy J. Long
Site Final10/2/201810/2/201810/2/2018PNR
DetailsAndy J. Long
need to pick up trash. Install wattle and/or berm on lots adjacent to Warm Springs creek
General Inspection6/14/20186/14/20186/14/2018PCANC
DetailsMichael Zawacki
Using road for access to site. No trackout, water truck is on site no fugitive dust.
General Inspection3/29/20183/29/20184/6/2018PPEND
DetailsAndy J. Long
Site Preparation2/16/20182/16/20182/16/2018PPASS
DetailsMichael Zawacki
Will continue to use old staging area and road closure for staging and storage. Will need to protect old Warm Springs Creek when working nearby, it still is primary waterway until they divert into new channel. Permit and SWPPP in box on west side.
Issue & PRINT permit SFD  1/10/2018 DONE
Application received  1/9/2018  
Routing - Erosion and Sediment1/9/2018 1/9/2018 DONE
DetailsAndy J. Long
ESC plan approved. Valid PD/RP. Site preparation required.
PLANS/APPL TAKEN TO FRONT DESK  1/9/2018  
Permit Ready to Issue  1/9/2018 DONE
DetailsChristina Prado
All requirements met
Telephone call  1/9/2018 DONE
DetailsChristina Prado
Called Jeff to advise permit is ready adn gave fees due