Permit Information
Permit NumberBLD17-04447
StatusFinaled
Name JORDAN WILCOMB CONSTRUCTION
Site Address 9492 W EMERALD ST
Project NameSalvation Army
Customer NumberBLD18-00632
ePlanReviewYes
Description
*(SALVATION ARMY) .Permit for a new 36-foot-tall, 31,828 sq.ft., 2 story building of type V-B construction. This facility will include a chapel/auditorium, classrooms, day care and offices. This building is required to be fully fire sprinklered and includes a fire alarm system. Separate fire sprinkler and fire alarm permits will be required for the required fire protection systems; as regulated by the Fire Department. CDM/SJA
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/24/20199/25/20199/25/2019APASS
DetailsMike Jordan
Jim Phone #: ###-####-still need PW sign off. OK fpr perm occ.
FIRE-Final Inspection9/23/20199/24/20199/24/2019PPASS
DetailsTroy Cobbley
Life safety passed. Jim Phone #: ###-####
FIRE-Final Inspection9/23/20199/23/20199/23/2019PCANC
DetailsTroy Cobbley
Need the FIR inspection for the range hoods scheduled/passed. Jim Phone #: ###-####
BLD-Conference9/20/20199/20/20199/20/2019PDONE
DetailsMike Jordan
Michael pre final walk around, see you around 1 Phone #: ###-#### Inspection requested via web by Jim Carriveau
FIRE-Final Inspection9/18/20199/19/20199/19/2019AFAIL
DetailsTroy Cobbley
Previous correctlons have been addressed but additional permits are required for the residential type 1 hood extinguishing systems. Jim Phone #: ###-####
FIRE-Final Inspection9/11/20199/12/20199/12/2019PFAIL
DetailsJim Page
FIR permits for hood suppression and fire alarm need to be finaled before life fire safety can be signed as complete. Provice internally illuminated exit signage and emergency lighting on exterior gates. Fire caulk condensate drain hole in riser room, riser room is a 1 hour rated assembly. Escutcheon in level 1 common restroom does not cover the entire sprinkler hole, escutcheon must cover entire hole. Remove masking from sprinkler heads in level 2 janitors closet and mech room.

Jim Phone #: ###-####
BLD-Conference9/10/20199/11/20199/11/2019ACANC
DetailsTell Riley
Hello Michael, pre walk and consult preparing for final Phone #: ###-#### Inspection requested via web by Jim Carriveau//cancel per Jim-he will reschedule for tomorrow//
FIRE-Conference8/30/20198/30/20198/30/2019PDONE
DetailsTroy Cobbley
Jim and I discussed the smoke detectors for the daycare area of this project. See E3.1 drawing sheet for reference.
BLD-Ceiling Grid Inspection8/7/20198/7/20198/7/2019APASS
DetailsMike Jordan
Kitchen ceiling grid, Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Ceiling Grid Inspection7/25/20197/25/20197/25/2019ACANC
DetailsTell Riley
Ceiling grid west single story-- BLD18-00632, i am using BLD 17-04447 to login as 00632 has a plan modification, not affecting ceiling grid though Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Ceiling Grid Inspection7/17/20197/18/20197/18/2019APASS
DetailsMike Jordan
Jim- 1st floor hall way and lobby Phone #: ###-####
BLD-Ceiling Grid Inspection7/9/20197/9/20197/9/2019APASS
DetailsMike Jordan
2nd floor ceiling grid Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Ceiling Grid Inspection6/17/20196/17/20196/17/2019APASS
DetailsMike Jordan
Hello Michael
ceiling grid inspection 1st floor, north and south sides Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Wall cover4/15/20194/15/20194/15/2019APASS
DetailsMike Jordan
Hello Mike
draft stop inspection 2nd floor mechanical shaft Phone #: ###-#### Inspection requested via web by Jim Carriveau. Firestoping ok.
BLD-Framing/Rough-in4/12/20194/12/20194/12/2019APASS
DetailsMike Jordan
Hello Mike
inspection for cover 2nd floor hard lids Phone #: ###-#### Inspection requested via web by Jim Carriveau. 2nd. floor hardlids ok. Needs to fire block mech. shaft at 2nd. floor.
BLD-Wall cover4/3/20194/3/20194/3/2019PPASS
DetailsMike Jordan
Hello Mike
i have the pipe penetrations and expansion joint complete with fire treatment in our 2 hour separation wall, inspection for cover. Phone #: ###-#### Inspection requested via web by Jim Carriveau. MAsonry 2hr. fire wall penetrations and CJ completed.
BLD-Energy code compliance3/29/20193/29/20193/29/2019APASS
DetailsDave Hannah
Hello Mike
2nd floor south side exterior insulation Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Energy code compliance3/21/20193/22/20193/22/2019APASS
DetailsMike Jordan
Hello Mike
insulation exterior walls for cover, north wing 2nd floor Phone #: ###-#### Inspection requested via web by Jim Carriveau. 2nd floor, north wing exterior walls ok.
BLD-Framing/Rough-in3/19/20193/20/20193/20/2019APASS
DetailsMike Jordan
Hello Mike
Hard Lids first floor for cover. i also have the information to clean up the correction notice on our foam spray insulation Phone #: ###-#### Inspection requested via web by Jim Carriveau. 1st. floor hardlids ok to cover. After reiview of corrected IAMPO report, noted that spray foam insulation used does not require an added ignition barrier.
BLD-Energy code compliance3/7/20193/8/20193/8/2019APASS
DetailsMike Jordan
first floor exterior wall insulation Phone #: ###-#### Inspection requested via web by Jim Carriveau. 1st. floor.
BLD-Framing/Rough-in3/8/20193/8/20193/8/2019PFAIL
DetailsMike Jordan
first floor exterior wall insulation Phone #: ###-#### Inspection requested via web by Jim Carriveau. Spray faom insulation requires an ignition barrier.
BLD-Framing/Rough-in3/6/20193/6/20193/6/2019APASS
DetailsMike Jordan
framing on a sofitt for cover Phone #: ###-#### Inspection requested via web by Jim Carriveau. Will provide the ESR report for the foam insulation. Also inspected intrerior steel stud framed walls, 1st. floor ok.
BLD-Framing/Rough-in2/6/20192/7/20192/7/2019APASS
DetailsMike Jordan
Hello Mike, we want to look at 1 hour assembly of elevator machine room,, shaft wall Inspection requested via web by Jim Carriveau. Interior layer of 1 inch saft board for 1 hr. ceiling asembly in elevator machine room.
BLD-Framing/Rough-in1/14/20191/14/20191/14/2019PPASS
DetailsMike Jordan
Hello Mike
we would like to inspect for cover to begin exterior drywall on the 2 story structure. i am here till 3:00 . We can do tomorrow am if that works better for you? Phone #: ###-#### Inspection requested via web by Jim Carriveau. Exterior steel stud wall framing for the 1st and 2nd. floors at the south east and waest exterior walls.
BLD-Framing/Rough-in1/9/20191/9/20191/9/2019APART
DetailsBrandon Shaw
Partial framing inspection in order to drywall parapet at roof ...
BLD-Concrete11/12/201811/13/201811/13/2018APASS
DetailsMike Jordan
Hello Michael
requesting inspection for 2nd floor concrete on pan deck placement, mesh and rebar Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Concrete9/25/20189/25/20189/25/2018PDEFR
DetailsMike Jordan
Hello Mike, we have a structural block grout placement at 2 pm today Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Concrete9/18/20189/18/20189/18/2018PPART
DetailsMike Jordan
Hello Mike, we have a masonry grout placement at 2:00 this afternoon, Strata will be onsite for rebar and grout testing Phone #: ###-#### Inspection requested via web by Jim Carriveau. Work in progress. Special inspector on site.
BLD-Foundation8/20/20188/21/20188/21/2018PPART
DetailsMike Jordan
we will be placing our final foundation concrete at 1:00 Tuesday. Strata will be onsite for rebar and concrete testing Phone #: ###-#### Inspection requested via web by Jim Carriveau. Placement in progress.
BLD-Foundation8/13/20188/14/20188/14/2018APASS
DetailsMike Jordan
we will be placing 18 yards in foundation stem wall 12:00. Strata will be onsite for rebar inspection and concrete testing Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Foundation8/9/20188/10/20188/10/2018ADEFR
DetailsMike Jordan
we will be placing 77 yards in stem walls and footings. 11:00 placement. Strata will be onsite for rebar inspection at 10 with concrete testing at 11 Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Footing8/1/20188/2/20188/2/2018PDEFR
DetailsMike Jordan
Hi Mike, hoping for a 1 30 rebar inspection, east and south exterior footing.
Strata will be onsite at 1;30 and 10:00 Friday for concrete testing Phone #: ###-#### Inspection requested via web by Jim Carriveau. Pending special inspection.
BLD-Footing7/30/20187/31/20187/31/2018APASS
DetailsMike Jordan
Mike, requesting rebar inspection Tuesday 10 am, we will have rebar in gym floor, elevator, stair tower walls, and exterior footings, 235 yards to be placed Wednesday morning 3 am. Strata will be inspecting rebar and concrete testing Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Footing7/18/20187/19/20187/19/2018APASS
DetailsMike Jordan
Hello Mike,
looking for rebar inspection at the large spread footing for the elevator, stair tower. Strata will be onsite at 10 to look at rebar. Concrete placement friday 4 am Phone #: ###-#### Inspection requested via web by Jim Carriveau
BLD-Conference6/14/20186/15/20186/15/2018ADONE
DetailsMike Jordan
Hey Michael, hoping i can schedule a 10 am pre con on site with you and Strata for tomorrow Phone #: ###-#### Inspection requested via web by Jim Carriveau. Went over special inspection requirements. lso discussed the issue of project having 2 building permits. All MEP inspections will occur under this building permit and will reference area of work that has been inspected. All building inspections will occur under the required bldg. permit as well as life/safety finals.
BLD-Concrete9/18/20189/19/2018 A 
DetailsMike Jordan
Hey Mike, we are placing a slab on grade tomorrow at 4am, strata will b onsite for rebar and concrete testing. You could look at our slab prep today if you come out for the grout placement Phone #: ###-#### >> Inspection requested via web by Jim Carriveau