Permit Information
Permit NumberBLD18-04294
StatusFinaled
Name KIER CONSTRUCTION CORPORATION
Site Address 10577 W FAIRVIEW AVE
Project NameMaverik
Customer Number 
ePlanReviewYes
Description
(MAVERIK) Permit to construct a new 4,224 sq. ft. retail convenience store building, a 2,843 sq. ft. fuel canopy and related site improvements. Approval is contingent upon adhering to the approved plans on file, DRH18-00416, plan review report and attached engineering. Scope of work includes: construction of foundation, concrete slab on grade, construction of fuel canopy, construction of steel stud framed exterior building envelope walls, roof construction, construction of interior non-bearing walls to create a retail area, an office, men’s and women’s accessible restrooms, kitchen area, storage areas, a pump room, (3) coolers and a freezer, new windows and doors, new electrical, new mechanical, new plumbing, site work, and interior finishes to be in compliance with Ch. 8 of the 2015 IBC. The building is not fire sprinklered. Note: Special Inspections Required see form 310. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/7/20202/7/20202/7/2020PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves. Ok for perm occ.
BLD-Final2/6/20202/10/20202/7/2020ACANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Roger Graves Inspection cancelled from web by: Roger Graves
FIRE-Final Inspection2/5/20202/6/20202/6/2020PPASS
DetailsTroy Cobbley
Life safety passed.

Phone #: ###-#### Inspection requested via web by Roger Graves
FIRE-Final Inspection1/27/20201/29/20201/29/2020PFAIL
DetailsTroy Cobbley
See the Fire life safety review comments for items marked in red that need addressed. It includes testing of the three emergency off switches, duct smoke detectors, adding exit discharge lighting at the Store Room exit, removing the dead bolt at the Beer Cooler, removing the thumb turn dead bolts at both main exit doors, providing an operational permit for the tank storage/exchange, 6" island's....ect.

Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Ceiling Grid Inspection1/21/20201/22/20201/22/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Ceiling Grid Inspection1/20/20201/21/20201/21/2020APART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Energy code compliance12/6/201912/6/201912/6/2019PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves. Remaining walls ok to cover.
BLD-Framing/Rough-in12/5/201912/5/201912/5/2019PPASS
DetailsMike Jordan
Soffits and hardlids ok.
BLD-Energy code compliance12/5/201912/5/201912/5/2019PPART
DetailsMike Jordan
exterior walls except at cooler ares.
BLD-Energy code compliance12/4/201912/5/201912/5/2019ACANC
DetailsMike Jordan
Requesting a mid morning inspection if possible. thank you Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Framing/Rough-in12/2/201912/3/201912/3/2019APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves. walls only. Ok to insulate.
BLD-Wall Bracing12/2/201912/3/201912/3/2019APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Wall Bracing11/25/201911/25/201911/25/2019PFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Roger Graves. Not all blocking or screws installed.
BLD-Wall Bracing11/14/201911/14/201911/14/2019AFAIL
DetailsMike Jordan
Install all blocking as shown on plans and additional strapping on interior side of building with the required additional screws.
BLD-Wall Bracing11/14/201911/14/201911/14/2019ACANC
DetailsMike Jordan
BLD-Wall cover11/12/201911/13/201911/14/2019PCANC
DetailsMike Jordan
Requesting a partial wall cover for house keeping walls. Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Wall Bracing11/12/201911/13/201911/14/2019PCANC
DetailsMike Jordan
Requesting a later PM inspection Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Foundation10/16/201910/17/201910/17/2019PDEFR
DetailsMike Jordan
Concrete is scheduled for 1:00 pm Phone #: ###-#### Inspection requested via web by Roger Graves. ok pending special inspection.
BLD-Footing10/11/201910/14/201910/14/2019PPASS
DetailsMike Jordan
Concrete is scheduled for 2:00 pm Phone #: ###-#### Inspection requested via web by Roger Graves
BLD-Foundation5/20/20195/21/20195/22/2019PDEFR
DetailsMike Jordan
Trash enclosure foundation inspection. Concrete is scheduled for 3 pm. Phone #: ###-#### Inspection requested via web by Roger Graves. Will have special inspection.
BLD-Footing5/17/20195/20/20195/20/2019APASS
DetailsMike Jordan
Trash enclosure footing inspection. Concrete is scheduled for 11:00 am. Phone #: ###-#### Inspection requested via web by Roger Graves. Will hace special inspections as well for project as noted.
BLD-Foundation5/16/20195/17/20195/17/2019ACANC
DetailsMike Jordan
Trash enclosure footing inspection. Have an 11:00 am concrete pour scheduled. Phone #: ###-#### >> Inspection requested via web by Roger Graves Inspection cancelled from web by: Roger Graves
BLD-Footing5/15/20195/17/20195/16/2019ACANC
DetailsMike Jordan
Trash enclosure footing inspection Phone #: ###-#### >> Inspection requested via web by Roger Graves Inspection cancelled from web by: Roger Graves