General Inspection | 3/14/2019 | 3/14/2019 | 3/19/2019 | | PASS |
Andy J. Long
|
|
|
Road construction, sidewalks, landscaping complete. No ESC corrections. ESC permit finaled.
|
DOC - Permit Finaled | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/27/2019 | 2/27/2019 | 2/27/2019 | | PASS |
Michael Zawacki
|
|
|
Inspected 2-26. Work complete and area planted. Will need to watch for erosion along top and edge of culvert on south side.
|
General Inspection | 2/12/2019 | 2/12/2019 | 2/13/2019 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 1/28/2019 | 1/28/2019 | 1/28/2019 | | PASS |
Michael Zawacki
|
|
|
Area landscaped and hydroseeded. Area on north side hasn't been stabalized.
|
General Inspection | 1/11/2019 | 1/11/2019 | 1/11/2019 | | PASS |
Michael Zawacki
|
|
|
Road and landscaping complete. No work on new homes in area.
|
General Inspection | 12/27/2018 | 12/27/2018 | 12/27/2018 | | PASS |
Michael Zawacki
|
|
|
Inspected 12/26. Work completed and being stabalized.
|
General Inspection | 12/12/2018 | 12/12/2018 | 12/13/2018 | | PASS |
Michael Zawacki
|
|
|
BMPs still installed around culvert. Area still bare and waiting for growth. No rills or erosion.
|
General Inspection | 11/27/2018 | 11/27/2018 | 11/27/2018 | | PASS |
Andy J. Long
|
|
|
Work complete. Monitoring creek and runoff areas into Warm Springs. No violations observed.
|
General Inspection | 11/9/2018 | 11/9/2018 | 11/9/2018 | | PASS |
Michael Zawacki
|
|
|
Road and landscaping complete.
|
General Inspection | 10/25/2018 | 10/25/2018 | 10/26/2018 | | PASS |
Michael Zawacki
|
|
|
Work completed. Wattle has been installed along perimeter of creek. Lots of wind blown trash in creek, HOA or other group needs to over creek and work on keeping it clean.
|
General Inspection | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | PASS |
Andy J. Long
|
|
|
|
Site Final | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | NR |
Andy J. Long
|
|
|
need to pick up trash. Install wattle and/or berm on lots adjacent to Warm Springs creek
|
General Inspection | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | CANC |
Michael Zawacki
|
|
|
Using road for access to site. No trackout, water truck is on site no fugitive dust.
|
General Inspection | 3/29/2018 | 3/29/2018 | 4/6/2018 | P | PEND |
Andy J. Long
|
|
|
|
Site Preparation | 2/16/2018 | 2/16/2018 | 2/16/2018 | P | PASS |
Michael Zawacki
|
|
|
Will continue to use old staging area and road closure for staging and storage. Will need to protect old Warm Springs Creek when working nearby, it still is primary waterway until they divert into new channel. Permit and SWPPP in box on west side.
|