General Inspection | 5/13/2019 | 5/13/2019 | 5/13/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 4/26/2019 | 4/26/2019 | 4/26/2019 | | PEND |
Andy J. Long
|
|
|
|
General Inspection | 4/11/2019 | 4/11/2019 | 4/12/2019 | | CANC |
Andy J. Long
|
|
|
home occupied. revegetation phase
|
General Inspection | 3/26/2019 | 3/27/2019 | 3/28/2019 | A | PASS |
Andy J. Long
|
|
|
follow up on landscapers...
Trackout cleaned up as requested. No new new issues. Approved.
|
General Inspection | 3/20/2019 | 3/20/2019 | 3/20/2019 | | PART |
Andy J. Long
|
|
|
WIP on pool and landscaping. Front yard and driveway complete. Home is now occupied.
Corrections:
- pool shotcrete washout is not allowed to be dumped, potential that this site dumped on another site. Investigation in progress.
- rake out and compact area of erosion in the subdivsion flood drainage channel.
|
General Inspection | 3/5/2019 | 3/5/2019 | 3/5/2019 | | PASS |
Michael Zawacki
|
|
|
Needs final stabalization.
|
General Inspection | 2/14/2019 | 2/14/2019 | 2/15/2019 | | PASS |
Michael Zawacki
|
|
|
Home complete and sold. Backyard and pool not yet finished.
|
General Inspection | 1/29/2019 | 1/29/2019 | 2/6/2019 | | PASS |
Michael Zawacki
|
|
|
Home completed, backyard still needs to be landscaped.
|
General Inspection | 12/20/2018 | 12/20/2018 | 12/20/2018 | | FAIL |
Michael Zawacki
|
|
|
Lots of loose trash and wind blow trash starting to leave lot. Sent message to RP.
|
General Inspection | 11/6/2018 | 11/6/2018 | 11/6/2018 | P | PASS |
Michael Zawacki
|
|
|
WIP, perimeter BMPs in place. Permit displayed on board out front. Site is clean.
|
General Inspection | 10/10/2018 | 10/16/2018 | 10/17/2018 | A | PASS |
Andy J. Long
|
|
|
follow up inspection on correction requests.
Corrections requested completed. Perimter wattles installed. Run on diversion berm installed to prevent extra runoff from disturbed site. RP-GC onsite.
No new corrections requested.
|
Conference | 10/10/2018 | 10/10/2018 | 10/10/2018 | A | DONE |
Andy J. Long
|
|
|
10 AM site inspection and conference with GC and homeowner.
Correction requests: - clean up washout. provide new washout for any further concrete or rinsing required. - install perimeter sediment control wattles on the west side of home and have J- hooks. Reviewed installation guidelines. - install earthen berm diversion to prevent run on to lot from upper lot that has been disturbed. - prevent trackout - maintain DI bags once water has drained through
Follow inspection on Tuesday 10/16
Follow up scheduled
|
General Inspection | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | FAIL |
Andy J. Long
|
|
|
Site is not compliance.
- No concerete washout on site, concrete washout on open area of lot - No perimeter sediment controls. - No ESC permit sign posted. - Consruction entrance needs maintenence, some minor trackout occuring, any vehicel entering site will cause trackout
|
General Inspection | 9/21/2018 | 9/21/2018 | 9/21/2018 | P | PASS |
Michael Zawacki
|
|
|
Two homes being done under same inspection. All foundation work complete, concrete washout on site and clean. Homes are being framed, sites are clean. Excavator on site, loading into dump truck, some dirt on sidewalk. Rock channels along perimeter need better protection.
|
General Inspection | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | PASS |
Michael Zawacki
|
|
|
Two homes being built next to eachother. Each lot has construction entrance, workers are parked on street. Water truck on site. Piece of gator guard not trenched in protectiong drainage on sout side. Large dirt stockpile close to drainage, only a small natural buffer. Sites are clean and free from trash. No fugitive dust.
|
General Inspection | 6/25/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Michael Zawacki
|
|
|
Two neighboring lots. Still large piles of backfill. Perimeter controls are old and will need repair. Some dirt goes right onto slope drainage channel. Pump truck onsite, was using washout.
|
Site Preparation | 6/25/2018 | 6/25/2018 | 6/25/2018 | P | PART |
Andy J. Long
|
|
|
No site preparation inspection requested. Lots excavated and foundations in progress.
Two adjacent sites by same contractor. Permit sign posted, lined concrete washout and construction entrance installed. Subdivsion stormdrains have sediment bags.
No trackout, discharge, or fugitive dust at sites. After backfill is conducted, will need to re-install perimter controls on the west lot. Follow up inspeciton scheduled.
Will remind GC and excavator of site preparation requirement.
|