Site Final | 5/26/2020 | 6/1/2020 | 6/1/2020 | A | PASS |
Michael Zawacki
|
|
|
|
Site Final | 5/22/2020 | 5/26/2020 | 5/26/2020 | P | NR |
Michael Zawacki
|
|
|
Talked to foreman on site. Will get crew to pull DI bags on fed way, remove silt fence, and do trash walk. Still steel building to be erected, no more dirt or concrete work. Rescheduled final for next week.
|
General Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Michael Zawacki
|
|
|
Site is clean and contained. Entrance is off federal way, no tracking. No trash has blown out.
|
General Inspection | 4/6/2020 | 4/6/2020 | 4/7/2020 | | PASS |
Michael Zawacki
|
|
|
Building up and acting as perimeter. No issues.
|
General Inspection | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on west side of project. Only entrance on Fed Way. No tras blown into fields, work area is all contained.
|
General Inspection | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Michael Zawacki
|
|
|
Work has begun on new shell. Entrance of Fed way onto paved lot then rock, no trackout. All materials stored within site. Trash is being cleaned when it blows away.
|
General Inspection | 1/6/2020 | 1/6/2020 | 1/6/2020 | | PASS |
Michael Zawacki
|
|
|
Entrance is off fed way. Apron is paved to rock. Site recently swept. Working on pads, no ointention to pour until weather is better, next buildings aren't scheduled to arrive for 2 months. No blown trash behind site.
|
General Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 | P | PASS |
Michael Zawacki
|
|
|
Around site is now paved, no one should need to drive in dirt. Material for next phase of buildings delivered, pads have been poured. May start pads for next phase depending on weather. Trash has been cleaned from neighboring lot.
|
General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Michael Zawacki
|
|
|
Some of area paved and units sold. Entrance to Fed Way has been closed, concrete crew opened it. Planning on getting rest of area paved on the 15th so they don't have mud issues. Concrete washout on sites, some small trash like drinks and labels around site.
|
General Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PASS |
Andy J. Long
|
|
|
|
BMP Violation | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Michael Zawacki
|
|
|
New entrance was installed, currently closed for concrete work. Sidewalks and apron being installed, washout on site. Trash has been picked up, still some in field, will do walkthrough and clean up. Plan is to pave main drive and finish pads before winter.
|
BMP Violation | 9/23/2019 | 9/24/2019 | 9/25/2019 | A | CANC |
Andy J. Long
|
|
|
|
BMP Violation | 9/17/2019 | 9/19/2019 | 9/23/2019 | P | PEND |
Andy J. Long
|
|
|
follow up
|
Tracking Control | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | FAIL |
Andy J. Long
|
|
|
Construction entrance not maintained, trackount on Summersweet leading Federal Way. Concrete cutting slurry not properly contained within work area. High pH water flowing toward storm drain.
Lot of windblown trash east of site.
Corrections required: - maintain/re-install construction entrance - install sandbag/gutter barriers to contain and suck up concrete cutting slurry. - pick up windblown trash east of site
|
General Inspection | 7/31/2019 | 7/30/2019 | 7/31/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP on foundations and steel frames. Water truck and washouts on site. No ESC issues.
|
General Inspection | 7/2/2019 | 7/2/2019 | 7/2/2019 | P | PASS |
Michael Zawacki
|
|
|
Steel frame construction has begun. No blowing dust or other ESC issues.
|
General Inspection | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Michael Zawacki
|
|
|
Lots of regrowth creating a natural buffer. Retaining walls and building pads poured. Water wagon on site, no dust. Dumpster on site, no loose trash.
|
General Inspection | 5/30/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with foreman on site. Exit needs new rocks and to be cleaned up. Not much work with weather, some concrete poured. Ecopan on site, perimeter BMPs ok. No major ESC issues.
|
General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Michael Zawacki
|
|
|
Shotcrete wall completed, perimeter wall for first building completed. Getting ready to start with floors, will bring back eco pans. Roads are clean, not much activity.
|
General Inspection | 3/29/2019 | 3/29/2019 | 4/1/2019 | P | PASS |
Andy J. Long
|
|
|
WIP. No trackout from either entrance. No corrections at this time.
|
General Inspection | 1/24/2019 | 1/24/2019 | 1/25/2019 | P | PASS |
Michael Zawacki
|
|
|
Some grading activity, no new excavation. Shotcrete wall lokks complete, no workers on it. Street looks like it has just been swept, no trackout.
|
General Inspection | 1/8/2019 | 1/15/2019 | 1/15/2019 | A | PASS |
Michael Zawacki
|
|
|
Not much activity, were changes in building plans and are still in review. Probably two weeks before Dasco starts disturbances for utilitie work. Shotcrete wall is being installed, two eco pans on site. Sweepers are being used as needed.
|
General Inspection | 1/7/2019 | 1/8/2019 | 1/8/2019 | P | PASS |
Andy J. Long
|
|
|
No trackout to Federal Way or Summersweet. Construction entrances and storm drains sediment protection are installed.
|
General Inspection | 11/20/2018 | 11/20/2018 | 11/20/2018 | P | PASS |
Michael Zawacki
|
|
|
Grading in progress. All BMPs have been installed. Entrance on Federal Wat, exit onto still water, no trackout. Some large stockpiles on site.
|
Site Preparation | 11/5/2018 | 11/6/2018 | 11/9/2018 | A | PASS |
Michael Zawacki
|
|
|
pre con already conducted. This is main site ESC permit. No duplicate permits required.
|
Stop Work Order | 10/24/2018 | 10/24/2018 | 10/24/2018 | A | DONE |
Andy J. Long
|
|
|
WBTBC working without with issued GRD and ESC permits. No site preparation inspection conducted. Double fee on ESC permit. Stop Work Order includes re-inspection fee and walk through inspection before proceeding.
|