Permit Information
Permit NumberESC19-00542
StatusIssued
Name JILL JENKINS
Site Address 749 E PARK BLVD
Project NamePark Place Apartments
Customer Number 
ePlanReviewNo
Description
Grading and utilities for new two building apartment complex. SWPPP for CGP submitted, no NOI filed at time of review. 7 day inspection frequency noted. BMPs include heavy duty construction entrance off Park Blvd, silt fence perimter control, storm drain sediment protection at Park and Ferguson, leakproof concrete washout and liquid waste containment, covered trash control with frequent trash pickups. Control fugitive dust. This will be the main ESC permit for the project. SITE PREPARATION INSPECTION is REQUIRED.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Tracking Control7/27/20207/30/20207/30/2020APASS
DetailsMichael Zawacki
Suez work in road done, has been patched and cleaned.
General Inspection7/24/20207/24/20207/27/2020 PART
DetailsMichael Zawacki
Doing some trench work. Mterials stored on park, lots of dirt on park. Site will need to be swept.
Talked to RP, water line, should be finished soon and be paved and swept.
Follow up scheduled.
General Inspection7/8/20207/8/20207/8/2020 PASS
DetailsMichael Zawacki
WIP on multiple phases.
Some area where concrete was spilled from pump truck, will need to be cleaned when dry. Multiple ecopans still on site. No loose trash or building debris. No dust or tracking.
Project is getting close to having all space covered.
General Inspection6/23/20206/23/20206/23/2020 CANC
DetailsMichael Zawacki
General Inspection6/5/20206/5/20206/5/2020 PASS
DetailsMichael Zawacki
Work on vertical and pads. Site is clean. Work on stockpiles in rear of site. Pool will start soon.
General Inspection5/21/20205/21/20205/26/2020 PASS
DetailsMichael Zawacki
Site clean and contained.
General Inspection5/6/20205/6/20205/6/2020 PASS
DetailsMichael Zawacki
Inspected 5-4
Concrete pour on upper levels of garage. Using crane and bucket to bring up mud, washout now on south side of entrance. Some more building foundations need to be poured. Lots of framng.
Site is pretty clean, some mess around portable mixer.
BMP Violation4/17/20204/21/20204/20/2020APASS
DetailsMichael Zawacki
Pump truck had a blocked hose and was cleaned where the truck was parked. Area cleane dup, no other issues with wash out.
General Inspection4/17/20204/17/20204/17/2020 FAIL
DetailsAndy J. Long
Dumped washout outside of containment area at site observed 4/16 by MPZ. See ESC19-00524
General Inspection4/2/20204/2/20204/2/2020 PASS
DetailsMichael Zawacki
Inspected 4/1.
Site is contained, no issues.
General Inspection3/18/20203/18/20203/18/2020 CANC
DetailsAndy J. Long
see ESC19-00525
General Inspection2/28/20202/28/20202/28/2020 PART
DetailsMichael Zawacki
Site is contained, no trackout.
Some spilled washout next to eco pans. Some washout/concrete on site, looks like where they transfered to pump truck. Should be cleaned.
Tracking Control2/10/20202/12/20202/12/2020APASS
DetailsMichael Zawacki
Talked with RP, she requested crushed basalt and they brought in round rock. She is there weekly and will monitor.
General Inspection2/7/20202/7/20202/10/2020 FAIL
DetailsMichael Zawacki
Trackout down Feguson and out to Park. Some blowing dust from where trackout has dried on road. Went to trailer and talked to PM, said they have a sweeper and will get it taken care off.
Follow up scheduled for 2-12, will need better entrance if contunues to be an issue.
General Inspection1/23/20201/23/20201/23/2020PPASS
DetailsMichael Zawacki
No trackout from either entrance. WIP on vertical. Seepage bed is surrounded by ecology blocks.
General Inspection1/7/20201/8/20201/8/2020PPASS
DetailsMichael Zawacki
No more open contanimated areas on site. WIp on slab and vertical colums.
Entrances started to become compacted.
Rock pads should be made for washouts, really wet and muddy aeound large roll off pan.
No issues at site.
BMP Violation12/20/201912/24/201912/24/2019APASS
DetailsMichael Zawacki
New rock added to both entrances.
General Inspection12/19/201912/20/201912/20/2019AFAIL
DetailsMichael Zawacki
Both entrances are bad. Need crushed rock brought in, entrance extended. Parking area is all mud.
Talked to foreman, RP has already told them entrance is bad and haven't done anything.
Said they will get it fixed and get sweeper on street.
General Inspection11/13/201911/14/201911/14/2019APASS
DetailsMichael Zawacki
Talked to Jim Williams about contanimated areas. Area along Park Center came back positive for hydrocarbons, waiting on formal report and directions to proceed. Area is fenced of and contanimated soil is on reinforced poly.
Rear void came back clean for water, waiting for final soil results to excavated for foundation. G&S on site waiting for ok to go.
2 washouts on site, pouring footings in middle of area where everything is ok.
No additional ESC issues.
Complaint Inspection11/6/201911/6/201911/6/2019PPEND
DetailsAndy J. Long
Report of excavated UST and contaminated soil/sludge on site. Unclear if incident has been properly reported.

Okland stating that MTI has sampled the material in coordination with Master Environmental and is awaiting results to determine proper remediation and reporting.

BLD inspector inspected site and has requested documentation.

Notified Idaho Dept. Environmental Quality Solid/Hazardous Waste division.
General Inspection10/17/201910/17/201910/17/2019PPASS
DetailsMichael Zawacki
No current dewatering. Crews digging swales deeper, engineers were not happy with drainage of material. Looking for approvals to change sewer routing and be able to bore instead of trenching through street. Water truck will be back to site Monday, no dust issues.
Diesel tank on site, is double walled, will get spec sheet on site.
General Inspection10/2/201910/3/201910/3/2019APASS
DetailsMichael Zawacki
First tap is completed and hole being backfilled.
Seepage bed took all water without issue, water line left plenty of room for more flow. Frack take hasn't been used.
General Inspection10/1/201910/2/201910/2/2019APASS
DetailsMichael Zawacki
Job being postponed. Part to tap into pipe needed to be overnighted.
Scheduled follow up tommorow.
Site Preparation9/17/20199/18/20199/18/2019APASS
DetailsMichael Zawacki
Met with RP and reps for site. OK to procede.