Information based on query as of Tuesday, May 7, 2024.
Permit Information
Permit NumberFIR17-00626
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 2855 W LOCKHEED LN
Project NameBOI ARFF REMODEL/EXPANSION
Customer Number 
ePlanReviewYes
Description
BOI ARFF Remodel/Expansion scope of work is to provide owner required notification, sprinkler monitoring and connection to the existing Main Airport FACP. This work is associated with building permit BLD17-00386.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/5/201912/5/201912/5/2019PPASS
DetailsTroy Cobbley
Permit finaled.
INSP-Final Inspection10/17/201910/18/201910/18/2019APART
DetailsTroy Cobbley
Fire alarm work complete for phase 4. See the city approved plans for the clouded area in red for the specific devices witnessed.

Brian Phone #: ###-####
INSP-Final Inspection10/14/201910/15/201910/15/2019APART
DetailsTroy Cobbley
Phase 4 fire alarm complete. See the city approved plans for the area clouded in red that was inspected for phase 4.
Brian Phone #: ###-####
INSP-Final Inspection10/9/201910/10/201910/10/2019AFAIL
DetailsTroy Cobbley
Placement and function tested. for phase 4 but tech could not provide verification for the candella settings for the strobes in the scope of work. Brian Phone #: ###-####
INSP-Final Inspection10/8/201910/9/201910/9/2019AFAIL
DetailsTroy Cobbley
On site fire man asked us to reschedule since they are using the phase 4 area. Brian Phone #: ###-####
INSP-Alarm Testing2/15/20192/15/20192/15/2019PPART
DetailsJim Page
Fire alarm testing for phase 3 complete, LF sound bases in rooms were a steady tone when alarms are active, LF bases need to be temporal 3 with the rest of the system, temporal sound fo LF bases will need to be verified at final inspection.

After 1PM if possible. Phone #: ###-#### Inspection requested via web by Gary Gambino
INSP-Final Inspection2/4/20192/4/20192/4/2019PPART
DetailsTroy Cobbley
Todays inspection was to verify that the fiber optic interconnection is functional which it was.

ARFF added to all devices descriptions going to the main panel. Phone #: ###-#### Inspection requested via web by Gary Gambino
INSP-Alarm Testing1/30/20192/1/20192/1/2019AFAIL
DetailsTroy Cobbley
The signals did go to the airport control as device and room number but the airport did not have an actual description of the location on site for the alarm. Gary is going to add description and reschedule.

Re-inspect after placing ARFF building on airport network - verification testing that new building reports to the Airport operations center. Phone #: ###-#### Inspection requested via web by Shane Lesteberg
INSP-Final Inspection10/25/201810/26/201810/26/2018APART
DetailsTroy Cobbley
Phase 2 work is complete, cellular dialer is being used temporary for 90 days

Phone #: ###-#### Inspection requested via web by Gary Gambino
INSP-Final Inspection10/24/201810/25/201810/25/2018PCANC
DetailsTroy Cobbley
Please call ahead Phone #: ###-#### >> Inspection requested via web by Gary Gambino Inspection cancelled from web by: Gary Gambino
INSP-Final Inspection10/24/201810/24/201810/24/2018PCANC
DetailsTroy Cobbley
Please call ahead Phone #: ###-#### >> Inspection requested via web by Gary Gambino Inspection cancelled from web by: Gary Gambino
INSP-Final Inspection10/17/201810/18/201810/18/2018AFAIL
DetailsTroy Cobbley
Need to pretest interconnection with the fire sprinkler devices, one 15cd strobe is mounted too high, another 15cd strobe is overspaced, missing two weather proof back boxes, drawings show networking with the airport fire alarm system but networking has not been set up so there is no off site or on site communiction. No actual testing performed.


Please call to schedule exact time. Phone #: ###-#### Inspection requested via web by Gary Gambino