Permit Information
Permit NumberFIR18-00428
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 8000 S FEDERAL WAY
Project NameMICRON BUILDING 37
Customer Number 
ePlanReviewYes
Description
[Micron Building 37 Office Building - C30616]
The fire sprinkler scope of work consists of connecting to previously installed 6" underground stub in and extend a wet class I manual standpipe for the three required stairs per NFPA 14 and FM global. In addition, Level 3 shall be fully sprinklered per NFPA13 and FM global with a wet system extended from the floor control assembly from the combination standpipe in stair 1, utilizing 8.0k ssu's and ssp's fed by 4" mains, 1½" branch lines with 1" arm-overs, drops and sprigs. The system has been designed based on OH1, 120 ft² maximum spacing per the owner’s request. Levels 1 and 2 shall be fully sprinklers under future permits.

• The underground piping is under permit FIR18-00308.
• There are three standpipes.
• As per the assistant fire marshal a manual standpipe is adequate

[BLD18-01064]
Permit for the build out of a new three story office building to include exterior wall infill and finishes, general site work and the completion of the interior of the building. This building is fully fire sprinklered for area increase. The structural frame and foundation were permitted under BLD18-00157.

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/22/20191/24/20191/24/2019PPASS
DetailsTroy Cobbley
Permit finaled


Tony Phone #: ###-####
INSP-Final Inspection12/12/201812/13/201812/13/2018AFAIL
DetailsTroy Cobbley
All tile on the 3rd floor is installed but the path of egress on the second floor and first floor have sprinkler issues which include shipping caps still on pendants and lay-in tile missing. Per Jim the only tampers and flow switches tested have been for the second floor.
Tony Phone #: ###-####
INSP-Final Inspection12/11/201812/12/201812/12/2018AFAIL
DetailsTroy Cobbley
Need all ceiling tile installed prior to a final for the 3rd floor.

Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection12/11/201812/11/201812/11/2018PCANC
DetailsJim Page
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Conference12/10/201812/10/201812/10/2018PDONE
DetailsJim Page
Fire conference for coverage3 around TV monitors complete, sprinkler will be adjusted for proper coverage around TV monitors.

Tony Phone #: ###-####
INSP-Final Inspection12/6/201812/7/201812/7/2018PFAIL
DetailsJim Page
TV monitors that are ceiling mounted are obstructing, correct obstruction issue.

Tony Phone #: ###-####
INSP-Sprinkler Rough-in11/15/201811/15/201811/15/2018APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 3 complete, level 3 approved for cover.
INSP-Sprinkler Rough-in/Hydro11/14/201811/15/201811/15/2018ADONE
DetailsJim Page
Hydrostatic test for level 3 and both standpipes witnessed, no pressure loss observed. All but 7 heads complete at time of hydro, hydro for level 3 is complete.



Hydro on 3rd floor and Hydro for stand pipes in all stair wells. Tony Cetani is the Shilo Foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in10/2/201810/3/201810/3/2018APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 3 complete, city approved plans will be notated for areas approved for cover.

Tony Cetani is the contact for this rough inspection. He is needing the inspection on the 2nd floor. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in9/28/201810/1/201810/1/2018APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 3 complete, city approved plans will be notated for areas approved for cover.

12 sprinkler heads on 3rd floor. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in9/4/20189/4/20189/4/2018APART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping on level 3 complete, a cover inspection for finish drops/sprinklers will be required before finish ceiling can be installed.
INSP-Sprinkler Rough-in/Hydro8/31/20189/4/20189/4/2018PPART
DetailsJim Page
Hydrostatic test for level 3 overehad fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.

Tony Cetani is the contact for this RTC/Hydro inspection. We appreciate your help with this. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus