INSP-Final Inspection | 12/26/2018 | 12/28/2018 | 12/28/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for level 2 complete.
Mike Martin is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2018 | 12/17/2018 | 12/17/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for level 2 witnessed, no pressure loss observed.
Tony Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | PASS |
Troy Cobbley
|
|
|
This inspection was for the Area "C" Fitness Center. Piping can be covered. Per contractor the limited use of wood is fire rated.
Tony Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | FAIL |
Troy Cobbley
|
|
|
This inspection was for the Area "C" Fitness Center. Piping could not be viewed due to insulation blocking it. Could not perform inspection. No piping to be covered prior to a rough-in inspection.
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | CANC |
Jim Page
|
|
|
Rescheduled for 12DEC18 per conversation with POC, this request is cancelled.
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in sky-bridge link complete, approved for cover.
Tony Cetani is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/29/2018 | 11/30/2018 | 11/30/2018 | P | PART |
Jim Page
|
|
|
Tamper switches in riser room and level 2 are now being monitored, flow switches in riser room and level 2 are monitored, both report to micron central station, system on level 2 can be made active.
Flow switch test per Tony Cetani ###-#### Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | DONE |
Jim Page
|
|
|
Conference complete
Tony Cetani is the contact and he would like a 2nd floor consultation. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/26/2018 | 11/26/2018 | 11/26/2018 | P | PART |
Jim Page
|
|
|
Previously noted issue for fire sprinkler in exterior canopy corrected, area inspected approved for ocver.
Tony Cetani is the contact for this rough to cover inspection. He needs one head on the first floor looked at. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/21/2018 | 11/26/2018 | 11/26/2018 | A | PART |
Troy Cobbley
|
|
|
The pendant head piping on the second floor marked "ok" in red is ok for cover. The first floor head in the exterior canopy is not ok for cover due to wet piping being installed in a cold area.
|
INSP-Sprinkler Rough-in | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in lobby and hardlid on level 2 complete, areas inspected approved for cover.
Tony Cetani is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in various areas complete, areas inspected approved for cover.
Tony Cetani is the Shilo Foreman. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans for the areas requested for inspection
Tony Cetani is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for hydro since all heads have not been cut in.
Tony Cetani is the contact. Thanks. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 8/24/2018 | 8/27/2018 | 8/27/2018 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Phone #: ###-#### Inspection requested via web by Stan Beus
|