INSP-Final Inspection | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Ken Phone #: ###-####
|
INSP-Final Inspection | 12/20/2018 | 12/26/2018 | 12/26/2018 | A | CANC |
Troy Cobbley
|
|
|
Contact Ken Orahood ###-#### 30 min prior to Fire Final start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 12/14/2018 | 12/17/2018 | 12/17/2018 | P | CANC |
Troy Cobbley
|
|
|
Contact Ken Orahood ###-#### 30 min prior to Fire Final Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Final Inspection | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | CANC |
Troy Cobbley
|
|
|
Contact Ken Orahood - ###-#### 30 min prior to Fire Final Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Contact Ken Orahood ###-#### 30 min prior to Hydro Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 12/5/2018 | 12/6/2018 | 12/6/2018 | P | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping is ok for cover.
Contact Ken Orahood ###-#### 30 Min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 11/19/2018 | 11/20/2018 | 11/20/2018 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping can be covered that are marked "ok"
Contact Ken Orahood ###-#### 30 Min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the hardlids in the Restrooms is ok for cover.
|
INSP-Sprinkler Rough-in | 11/6/2018 | 11/7/2018 | 11/7/2018 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations for four heads/piping that the hardlids are ok for cover.
Contact Ken Orahood ###-#### 30 Min prior to RTC Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PASS |
Troy Cobbley
|
|
|
The branchline restraints have been installed so they can be covered.
Contact Ken Orahood - ###-#### 30 Min prior to RTC Insp start please.
Thanks Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 9/25/2018 | 9/26/2018 | 9/26/2018 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was just for the hangers attachment points prior to being covered by sheetrock. What is installed appears ok but the siesmic bracing for the branchlines has not been addressed. So attachments can be covered where the rod is less than 6" from pipe to attachment point but the longer hangers can't be covered until the siesmic bracing is addressed.
Contact Ken Orahood ###-#### 20 min prior to RTC Insp start please and THANK YOU. Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|