Permit Information
Permit NumberFIR19-00309
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 11783 W KING ST
Project NameFairview Apts 24-Plex #11783
Customer Number 
ePlanReviewYes
Description
Shilo will install a new fire sprinkler system into the new 24-plex per NFPA 13R, 2016 and the City of Boise.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/17/20199/18/20199/18/2019APASS
DetailsTroy Cobbley
The FDC piping has been changed to galvanized. Permit finaled. Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/17/20199/17/20199/17/2019PCANC
DetailsTroy Cobbley
Could not make it to this inspection due to work load and time constriants. Will need to be rescheduled.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/13/20199/16/20199/16/2019AFAIL
DetailsTroy Cobbley
**Failed FDC piping that is exposed needs to be galvanzied. Location approved.*MAS**
Gabe Garduno is the contact for this final inspection. Thank you for your help. Have a nice day. Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Final Inspection9/4/20199/5/20199/5/2019APART
DetailsTroy Cobbley
The fire sprinkler work in the six north end apartments is complete. 1st - 3rd floors. The fire alarm interconnect is complete. FDC nees relocated from the air conditioner condenser.

Gabe Garduno is the contact for this final inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/3/20199/4/20199/4/2019AFAIL
DetailsTroy Cobbley
Today's inspection had it passed would be only for the six north most apartments. However two of the three flow switches did not function. Still need to test the crawl space tamper switches.


Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/12/20196/13/20196/13/2019APASS
DetailsTroy Cobbley
The overhead hydro tests witnessed.

Gabe Garduno is the contact for this overhead Hydro test. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/11/20196/12/20196/12/2019ACANC
DetailsJim Page
Cancelled per conversation with point of contact, leak was found, hydrostatic test to be rescheduled for a later date.

Gabe Garduno is the contact. This inspection is to be done in connection with an underground flush/hydro for 11792 W. Fairview at 10:00 AM, as well as an underground flush/hydro for this building. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/28/20195/29/20195/29/2019APASS
DetailsTroy Cobbley
Tenting inspection passed. Piping can be covered.

Gabe Phone #: ###-####
INSP-Sprinkler Rough-in5/21/20195/22/20195/22/2019AFAIL
DetailsTroy Cobbley
Tenting inspection failed. To be repaired as discussed in the breeze ways
INSP-Sprinkler Rough-in5/17/20195/20/20195/20/2019PPART
DetailsTroy Cobbley
Tenting is not complete for the third floor. Rough-in for the first and third floors is complete except for acouple of tie-ins at the Breezeway. Riser room tenting is not complete.


Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/10/20195/13/20195/13/2019PPASS
DetailsTroy Cobbley
Todays inspection was for the second floor only. Piping can be covered but a second cover inspection will be needed when the soffits are installed.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/6/20195/7/20195/7/2019AFAIL
DetailsTroy Cobbley
Numerous corrections needed. Wil need to be rescheduled when tenting, pipe sizes addressed and install is complete. Gabe Garduno is the contact for this partial RTC. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus