INSP-Final Inspection | 1/15/2020 | 1/15/2020 | 1/15/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
James will reach out on panel patching. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 1/14/2020 | 1/14/2020 | 1/14/2020 | P | CANC |
Troy Cobbley
|
|
|
Not ready.
Call James about repair work around access panel Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 1/10/2020 | 1/13/2020 | 1/13/2020 | P | FAIL |
Troy Cobbley
|
|
|
Waiting for the builder to repair the wall at the riser/access panel. Per contractor the irrigation system is not a shared system with the fire sprinklers.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 1/9/2020 | 1/10/2020 | 1/10/2020 | P | FAIL |
Troy Cobbley
|
|
|
**Failed* Ceilings need patching around escutcheons, irrigation needs to tied into flow switch, required signage needs to mounted on riser.**MAS**
Call James before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 1/9/2020 | 1/9/2020 | 1/9/2020 | P | CANC |
Troy Cobbley
|
|
|
Call James when heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Final Inspection | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | CANC |
Troy Cobbley
|
|
|
Call James before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro witnessed with no loss on guage.
Hydro only - ready any time. Call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2019 | 10/17/2019 | 10/17/2019 | P | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to sheetrock workers opening valve
Call James before heading out, hydro only while it is warm enough. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 10/8/2019 | 10/9/2019 | 10/9/2019 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed. Piping can be covered. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | FAIL |
Troy Cobbley
|
|
|
Tenting inspection failed due to modifications needed to block out cold air from entering the area under the second floor. I met with the builder and discussed it. As Built plan is already in progress and will be submitted to Mark within the next few days. Call James if there are any issues, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2019 | 10/2/2019 | 10/2/2019 | A | PART |
Troy Cobbley
|
|
|
Rough-in passed but as-builts need to be submitted showing changes. No piping to be covered until as-builts are provided and a tenting inspection has been passed. The supply piping to the riser has not been provided yet. Please call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|