INSP-Final | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | DONE |
Troy Cobbley
|
|
|
Permit finaled
FInal inspection to coincide with Fire Alarm Final. Jerermiah Robison is point of contact Phone #: ###-#### Inspection requested via web by Randy Knutson
|
DOC - Permit Finaled | | | 9/25/2018 | | DONE |
|
|
|
Per Troy C
|
INSP-Final | 9/20/2018 | 9/21/2018 | 9/21/2018 | P | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet. Forward flush assembley needs to be permanant, air compressor needs connected, need exterior alarm bell installed, need monitoring of the wall post indicator valve. All interconnections with the fire alarm system need to be pre-tested. Forward flush passed.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2018 | 9/20/2018 | 9/21/2018 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test for the dry system passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2018 | 9/20/2018 | 9/20/2018 | P | CANC |
Troy Cobbley
|
|
|
Called Randy- inspection for yesterday failed. need to re schedule before final can be completed. Final on Wet and Dry Systems. Jeremiah Robison is contact Phone #: ###-#### >> Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2018 | 9/19/2018 | 9/20/2018 | A | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Forrest inspection comments-Not ready. System gauges at riser indicate no pressure at 0830hrs.24 HR on Dry System. Jeremiah Robison is contact Phone #: ###-#### >> Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2018 | 9/18/2018 | 9/19/2018 | P | PART |
Adele J Schaffeld-Griffin
|
|
|
Forrest Inspection comments-Overhead hydrostatic test for both the wet and dry systems completed satisfactory.Hydro on full Building. Jeremiah Robison is contact Phone #: ###-#### >> Inspection requested via web by Randy Knutson
|
INSP-Sprinkler Rough-in | 8/8/2018 | 8/9/2018 | 8/9/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping inn the commons area soffits complete, approved for cover.
rough in for common areas Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Troy Cobbley
|
|
|
Porte-Coche rough-in passed. Piping can be covered.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 8/2/2018 | 8/3/2018 | 8/3/2018 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans/mod for the front entry canopy are on site. No inspection performed. To be rescheduled for monday.
CANOPY AREA Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Troy Cobbley
|
|
|
tenting in main corridor/verticals passed.Piping can be covered.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 7/9/2018 | 7/10/2018 | 7/10/2018 | A | PASS |
Troy Cobbley
|
|
|
The remaining tenting passed except for the vertical piping in the main corridor/north side. The previous corrections have been addressed.
|
INSP-Sprinkler Rough-in | 7/5/2018 | 7/6/2018 | 7/6/2018 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the center section of the building. The dry system piping for the front canopy is not installed yet. Tenting is not done yet. I noted a missing earthquake brace on the main just before it will exit to the front canopy. I noted revised piping and fittings for the supply to the front canopy tht will need to be included in calculations. The low point drain the the janitors closet has not been installed yet.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/27/2018 | 6/29/2018 | 6/29/2018 | A | PART |
Jim Page
|
|
|
ROugh to cover inspection for overhead fire sprinkler piping/tenting on east wing complete, east wing is approved for cover. Center section of building to be inspected at a later date.
eastside Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/26/2018 | 6/27/2018 | 6/27/2018 | A | PASS |
Troy Cobbley
|
|
|
tenting inspection for the west wing only has passed and piping can be covered.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/22/2018 | 6/25/2018 | 6/25/2018 | A | FAIL |
Jim Page
|
|
|
Tenting not installed at time of inspetion, tenitng will need to be completed and inspected before overhead fire sprinkler piping can be covered, no cover is approved.
tenting inspection Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | PASS |
Troy Cobbley
|
|
|
The rough-in for the wet and dry systems in the west wing is passed. A tenting inspection is needed before a cover approval is given. Per the contractor plans have been resubmitted.
Call prior to going Phone #: 2084774515 >> Inspection requested via mobile web by Jeremiah
|
INSP-Sprinkler Rough-in | 6/21/2018 | 6/21/2018 | 6/21/2018 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow morning
Call prior to going Phone #: 2084774515 >> Inspection requested via mobile web by Jeremiah Robinson
|
INSP-Sprinkler Rough-in | 6/19/2018 | 6/19/2018 | 6/19/2018 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the west end, cpvc piping as marked on the plans. I noted that the pipe sizing does not match in the Resident room as marked on the plans, residential pendants have been installed in the Corridor, pendant heads are overspaced in the Corridor, there are many "shadowed" areas in the Resident Room Restrooms, 2 1/2" cpvc piping has been installed where steel piping is shown, piping is missing earthquake bracing. No tenting has been installed yet.
Call prior to going Phone #: 2088613011 >> Inspection requested via mobile web by Matt-overhead inspection
|