Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD18-02497
StatusIssued
Name ESI
Site Address 3101 N SYCAMORE DR
Project NameBoise Fire Station #9
Customer Number 
ePlanReviewYes
Description
(BOISE FIRE STATION #9) GREEN TAG FOR GREEN BUILDING “”SPECIAL INSPECTIONS ARE REQUIRED PER THE ATTACHED FORM 310”” Demolition of the existing Fire Station #9, and construct a new 7,903 sq. ft. Fire Station with work to include general demolition, and site work and the construction of the fire station per the approved plans. Building to meet the 2012 International Green Construction Code (IGCC). This building is fully fire sprinklered for R-2 occupancy. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/7/20205/7/20205/8/2020PPASS
DetailsTony Young
Nick **Screened* Phone #: ###-####
FIRE-Final Inspection4/27/20204/27/20204/27/2020PPASS
DetailsJim Page
Previously noted item has been corrected, solar panel inspection is complete under BLD19-04240, final life fire safety inspection is complete.

Nick Phone #: ###-####
BLD-Final4/21/20204/21/20204/22/2020PNR
DetailsTony Young
screened - as far you know - solar permit final scheduled for am // Nick Phone #: ###-####// needs f/l/s full pass and electrical final 1st
BLD-Final4/20/20204/21/20204/21/2020ANR
DetailsTony Young
screened - as far you know - solar permit final scheduled for am // Nick Phone #: ###-####// needs electrical final 1st and fire and life safety final pass
Plan Reviewer's activity  4/20/2020 DONE
DetailsJason Blais
Received final commissioning reports.
PubWorks Occupancy Approval11/1/201911/1/201911/1/2019 DONE
DetailsTiffany Lowery
BLD-Final10/25/201910/28/201910/28/2019APART
DetailsMike Jordan
Ken Phone #: ###-####. Tempered glazing has been installed. ADA toilets on order. Commisioning has been completed and report is being written. Ok for temp occ.
PubWorks Temp Occupancy Appr10/24/201910/24/201910/24/2019 DONE
DetailsTiffany Lowery
FIRE-Final Inspection10/22/201910/22/201910/22/2019PPART
DetailsTroy Cobbley
A temp for life safety is being given with boise fire approval. Need a permit for the solar panel/system and one additional exit discharge light is needed at the south east exit door.

Ken Phone #: ###-####
BLD-Final10/18/201910/21/201910/21/2019PNR
DetailsTony Young
Ken Phone #: ###-####,, walk through only,, needs Accessibility to meet plans,, egress in dorms to function, signage, tempered glass, trades, etc.
FIRE-Final Inspection10/18/201910/21/201910/21/2019ACANC
DetailsTroy Cobbley
To be canceled per Ken since they are still having generator issues. Ken Phone #: ###-####
FIRE-Final Inspection10/17/201910/18/201910/18/2019AFAIL
DetailsTroy Cobbley
Provide information for the change to a diesel gererator, provide testing of the automatic switch over of the generator since it did not function, provide signage for the gererator as discussed, provide testing of the exit signs and emergency lights, provide fire lane signage. See the review comments for items marked in blue.

Ken Phone #: ###-####
FIRE-Final Inspection10/16/201910/17/201910/17/2019AFAIL
DetailsTroy Cobbley
No inspection performed. No city approved plans or small documents on site. Ken Phone #: ###-####
FIRE-Final Inspection10/15/201910/16/201910/16/2019PCANC
DetailsTroy Cobbley
To be rescheduled due to time constraints due to work load. Ken Phone #: ###-####
BLD-Ceiling Grid Inspection9/11/20199/11/20199/11/2019PPASS
DetailsTony Young
Ken Phone #: ###-####
BLD-Wall cover6/20/20196/21/20196/21/2019APART
DetailsTony Young
Phone #: 2088300687 >> Inspection requested via mobile web by Hard lids for cover,, ok pending special inspection and also trades
BLD-Wall cover6/5/20196/5/20196/5/2019PPART
DetailsTony Young
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Fire stop behind outlets,, 4 areas ok
BLD-Energy code compliance5/29/20195/30/20195/30/2019APART
DetailsTony Young
As early as possible Phone #: 2084777563 >> Inspection requested via mobile web by Lalo - insulation in wall,, work in progress,, ok to cover as needed to stay in progress
BLD-Framing/Rough-in5/23/20195/24/20195/24/2019APASS
DetailsBrandon Shaw
Phone #: 2084777563 >> Inspection requested via mobile web by Lalo Delgado - Framer
BLD-Other4/18/20194/19/20194/19/2019PCANC
DetailsJim Sly
Call prior to going Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening
BLD-Other4/18/20194/19/20194/19/2019APASS
DetailsJim Sly
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening
Remainder of shear wall fastening........OK.
BLD-Framing/Rough-in4/9/20194/11/20194/11/2019APART
DetailsTony Young
Call prior to going Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening,, work in progress on various walls,, ok so far
BLD-Conference3/18/20193/18/20193/18/2019PPART
DetailsTony Young
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Justin// frame ?s on bracing,, doing straps and panels at the same time,, ok
BLD-Other2/5/20192/6/20192/6/2019PPART
DetailsTony Young
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by CMU Wall Grout,, pending special inspection
BLD-Concrete1/22/20191/23/20191/23/2019APART
DetailsJim Sly
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Slab pour-MTI inspected
OK pendind MTI special inspection, tests and approvals.
BLD-Concrete1/21/20191/22/20191/22/2019PDEFR
DetailsDave Hannah
As late as possible Phone #: 2088502262 >> Inspection requested via mobile web by Slab pour-MTI inspected (ouit of time)
BLD-Footing12/20/201812/21/201812/21/2018APEND
DetailsTony Young
Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection
BLD-Foundation12/5/201812/6/201812/6/2018APEND
DetailsTony Young
Phone #: 2088502262 >> Inspection requested via mobile web by Tim-10:30am-MTI scheduled,, ok pending report
BLD-Foundation11/27/201811/29/201811/29/2018APART
DetailsJim Storey
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim 10am pour time bar clearance si on site to follow up.
BLD-Conference11/20/201811/21/201811/21/2018APART
DetailsBrandon Shaw
Special inspection required, North East, South East and Wesr footings, work in progress...
BLD-Footing11/15/201811/19/201811/19/2018APART
DetailsTony Young
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection required,, looked at the plans,, south and east footings,, work in progress
Fees Due Hold10/6/2018 10/8/2018 DONE
DetailsChristina Prado
Fees Due Hold10/5/2018 10/5/2018 DONE
DetailsChristina Prado
Issue & PRINT to be Invoiced  10/4/2018 DONE
Paid via JV
Print Occupancy Form  10/4/2018 DONE
OVERRIDE  9/13/2018  
Plan assigned to (CDM)7/20/20187/20/20189/13/2018 PASS
DetailsCarl D Madsen
08/03 Fire Station #9 New - Green Bldg
PLANS/APPL TAKEN TO FRONT DESK  9/13/2018 DONE
Permit Ready to Issue  9/13/2018 DONE
NEED
RP - met
ACHD - met
GC FORM - met
REVISED VALUE - met
Routing - PLAN CHECK8/16/2018 9/13/2018 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK9/7/2018 9/11/2018 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL9/7/2018 9/11/2018 PASS
DetailsCarl D Madsen
Routing PW Sewer Design9/10/2018 9/10/2018 PASS
DetailsDeAnn Brown
Routing Off Site - STRUCTURAL8/16/2018 9/7/2018 FAIL
DetailsCarl D Madsen
Routing PW Sewer Design8/17/2018 8/28/2018 FAIL
DetailsDeAnn Brown
Changes to utility plan and demo plan required and discussed with the engineer. Please upload new plan sheets.
Routing - PUBLIC WORKS8/16/2018 8/17/2018 PASS
DetailsMorgan Webb
Routing Off Site - STRUCTURAL7/20/2018 8/16/2018 FAIL
DetailsCarl D Madsen
Route to Impact Fee Review8/9/20188/12/20188/10/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE7/20/20187/20/20188/8/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - PLAN CHECK7/20/2018 8/8/2018 FAIL
DetailsCarl D Madsen
1st review completed  8/8/2018 FAIL
Routing - MECHANICAL7/20/2018 7/27/2018 PASS
DetailsTroy James
Routing - PUBLIC WORKS7/20/2018 7/27/2018 PASS
DetailsMorgan Webb
Routing - PLUMBING7/20/2018 7/26/2018 PASS
DetailsBill VanDegrift
verify NPW connection location and trap primer location
Routing - Design Review7/20/2018 7/26/2018 PASS
DetailsAndrea Tuning
No review required. Property is zoned R-2.
Routing PW Environmental7/24/2018 7/26/2018 PASS
DetailsRick Christenson
Routing PW Solid Waste7/24/2018 7/25/2018 PASS
DetailsEvan Carpenter
Routing PW Street Lights7/24/2018 7/25/2018 PASS
DetailsTom Marshall
Routing - Erosion and Sediment7/20/2018 7/25/2018 PASS
DetailsMichael Zawacki
RP needed before demo begins.
Routing - PLANNING7/20/2018 7/24/2018 PASS
DetailsNicolette Womack
CUP18-00021. Add tree approved in the SW corner and two trees approved in NE corner.
Routing - Addressing7/20/2018 7/24/2018 PASS
DetailsDoug Chausow
Routing PW Sewer Design7/24/2018 7/24/2018 FAIL
DetailsDeAnn Brown
Add to keynote 6 on sheet C5.00 Site Utilities Plan: "Contact City of Boise Public Works 48 hours in advance to obtain a sewer tap permit and schedule inspection."
Add to keynote 9 on sheet C5.00 Site Utilities Plan: "Contact City of Boise Public Works 48 hours in advance to obtain a sewer plug permit and schedule inspection."
Routing PW Drainage7/24/2018 7/24/2018 PASS
DetailsBrian Murphy
Plans ACCEPTED BY PLAN TECH  7/20/2018 DONE
Recd Pcfee & Taken To Pln CK  7/20/2018 DONE
Intake Approval  7/20/2018 PASS
Application received  7/13/2018 DONE
Application submitted via PDS Online on Jul 13 2018 8:27AM