BLD-Final | 5/7/2020 | 5/7/2020 | 5/8/2020 | P | PASS |
Tony Young
|
|
|
Nick **Screened* Phone #: ###-####
|
FIRE-Final Inspection | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, solar panel inspection is complete under BLD19-04240, final life fire safety inspection is complete.
Nick Phone #: ###-####
|
BLD-Final | 4/21/2020 | 4/21/2020 | 4/22/2020 | P | NR |
Tony Young
|
|
|
screened - as far you know - solar permit final scheduled for am // Nick Phone #: ###-####// needs f/l/s full pass and electrical final 1st
|
BLD-Final | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | NR |
Tony Young
|
|
|
screened - as far you know - solar permit final scheduled for am // Nick Phone #: ###-####// needs electrical final 1st and fire and life safety final pass
|
Plan Reviewer's activity | | | 4/20/2020 | | DONE |
Jason Blais
|
|
|
Received final commissioning reports.
|
PubWorks Occupancy Approval | 11/1/2019 | 11/1/2019 | 11/1/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | PART |
Mike Jordan
|
|
|
Ken Phone #: ###-####. Tempered glazing has been installed. ADA toilets on order. Commisioning has been completed and report is being written. Ok for temp occ.
|
PubWorks Temp Occupancy Appr | 10/24/2019 | 10/24/2019 | 10/24/2019 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given with boise fire approval. Need a permit for the solar panel/system and one additional exit discharge light is needed at the south east exit door.
Ken Phone #: ###-####
|
BLD-Final | 10/18/2019 | 10/21/2019 | 10/21/2019 | P | NR |
Tony Young
|
|
|
Ken Phone #: ###-####,, walk through only,, needs Accessibility to meet plans,, egress in dorms to function, signage, tempered glass, trades, etc.
|
FIRE-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | CANC |
Troy Cobbley
|
|
|
To be canceled per Ken since they are still having generator issues. Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide information for the change to a diesel gererator, provide testing of the automatic switch over of the generator since it did not function, provide signage for the gererator as discussed, provide testing of the exit signs and emergency lights, provide fire lane signage. See the review comments for items marked in blue.
Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | FAIL |
Troy Cobbley
|
|
|
No inspection performed. No city approved plans or small documents on site. Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/15/2019 | 10/16/2019 | 10/16/2019 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled due to time constraints due to work load. Ken Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Tony Young
|
|
|
Ken Phone #: ###-####
|
BLD-Wall cover | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PART |
Tony Young
|
|
|
Phone #: 2088300687 >> Inspection requested via mobile web by Hard lids for cover,, ok pending special inspection and also trades
|
BLD-Wall cover | 6/5/2019 | 6/5/2019 | 6/5/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Fire stop behind outlets,, 4 areas ok
|
BLD-Energy code compliance | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2084777563 >> Inspection requested via mobile web by Lalo - insulation in wall,, work in progress,, ok to cover as needed to stay in progress
|
BLD-Framing/Rough-in | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2084777563 >> Inspection requested via mobile web by Lalo Delgado - Framer
|
BLD-Other | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | CANC |
Jim Sly
|
|
|
Call prior to going Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening
|
BLD-Other | 4/18/2019 | 4/19/2019 | 4/19/2019 | A | PASS |
Jim Sly
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening Remainder of shear wall fastening........OK.
|
BLD-Framing/Rough-in | 4/9/2019 | 4/11/2019 | 4/11/2019 | A | PART |
Tony Young
|
|
|
Call prior to going Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening,, work in progress on various walls,, ok so far
|
BLD-Conference | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Justin// frame ?s on bracing,, doing straps and panels at the same time,, ok
|
BLD-Other | 2/5/2019 | 2/6/2019 | 2/6/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by CMU Wall Grout,, pending special inspection
|
BLD-Concrete | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PART |
Jim Sly
|
|
|
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Slab pour-MTI inspected OK pendind MTI special inspection, tests and approvals.
|
BLD-Concrete | 1/21/2019 | 1/22/2019 | 1/22/2019 | P | DEFR |
Dave Hannah
|
|
|
As late as possible Phone #: 2088502262 >> Inspection requested via mobile web by Slab pour-MTI inspected (ouit of time)
|
BLD-Footing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PEND |
Tony Young
|
|
|
Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection
|
BLD-Foundation | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | PEND |
Tony Young
|
|
|
Phone #: 2088502262 >> Inspection requested via mobile web by Tim-10:30am-MTI scheduled,, ok pending report
|
BLD-Foundation | 11/27/2018 | 11/29/2018 | 11/29/2018 | A | PART |
Jim Storey
|
|
|
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim 10am pour time bar clearance si on site to follow up.
|
BLD-Conference | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PART |
Brandon Shaw
|
|
|
Special inspection required, North East, South East and Wesr footings, work in progress...
|
BLD-Footing | 11/15/2018 | 11/19/2018 | 11/19/2018 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection required,, looked at the plans,, south and east footings,, work in progress
|
Fees Due Hold | 10/6/2018 | | 10/8/2018 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 10/5/2018 | | 10/5/2018 | | DONE |
Christina Prado
|
|
|
|
Issue & PRINT to be Invoiced | | | 10/4/2018 | | DONE |
|
|
|
Paid via JV
|
Print Occupancy Form | | | 10/4/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/13/2018 | | |
|
|
|
|
Plan assigned to (CDM) | 7/20/2018 | 7/20/2018 | 9/13/2018 | | PASS |
Carl D Madsen
|
|
|
08/03 Fire Station #9 New - Green Bldg
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/13/2018 | | DONE |
|
|
|
NEED
RP - met
ACHD - met
GC FORM - met
REVISED VALUE - met
|
Routing - PLAN CHECK | 8/16/2018 | | 9/13/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/7/2018 | | 9/11/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 9/7/2018 | | 9/11/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 9/10/2018 | | 9/10/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing Off Site - STRUCTURAL | 8/16/2018 | | 9/7/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Sewer Design | 8/17/2018 | | 8/28/2018 | | FAIL |
DeAnn Brown
|
|
|
Changes to utility plan and demo plan required and discussed with the engineer. Please upload new plan sheets.
|
Routing - PUBLIC WORKS | 8/16/2018 | | 8/17/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing Off Site - STRUCTURAL | 7/20/2018 | | 8/16/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 8/9/2018 | 8/12/2018 | 8/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/20/2018 | 7/20/2018 | 8/8/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 7/20/2018 | | 8/8/2018 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/8/2018 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 7/20/2018 | | 7/27/2018 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 7/20/2018 | | 7/27/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLUMBING | 7/20/2018 | | 7/26/2018 | | PASS |
Bill VanDegrift
|
|
|
verify NPW connection location and trap primer location
|
Routing - Design Review | 7/20/2018 | | 7/26/2018 | | PASS |
Andrea Tuning
|
|
|
No review required. Property is zoned R-2.
|
Routing PW Environmental | 7/24/2018 | | 7/26/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 7/24/2018 | | 7/25/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 7/24/2018 | | 7/25/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - Erosion and Sediment | 7/20/2018 | | 7/25/2018 | | PASS |
Michael Zawacki
|
|
|
RP needed before demo begins.
|
Routing - PLANNING | 7/20/2018 | | 7/24/2018 | | PASS |
Nicolette Womack
|
|
|
CUP18-00021. Add tree approved in the SW corner and two trees approved in NE corner.
|
Routing - Addressing | 7/20/2018 | | 7/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Sewer Design | 7/24/2018 | | 7/24/2018 | | FAIL |
DeAnn Brown
|
|
|
Add to keynote 6 on sheet C5.00 Site Utilities Plan: "Contact City of Boise Public Works 48 hours in advance to obtain a sewer tap permit and schedule inspection."
Add to keynote 9 on sheet C5.00 Site Utilities Plan: "Contact City of Boise Public Works 48 hours in advance to obtain a sewer plug permit and schedule inspection."
|
Routing PW Drainage | 7/24/2018 | | 7/24/2018 | | PASS |
Brian Murphy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/20/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 7/20/2018 | | PASS |
|
|
|
|
Application received | | | 7/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 13 2018 8:27AM
|