Information based on query as of Thursday, May 9, 2024.
Permit Information
Permit NumberBLD17-00339
StatusFinaled
Name CM COMPANY
Site Address 7009 W FRANKLIN RD
Project NameBishop Kelly High School
Customer Number 
ePlanReviewYes
Description
(BISHOP KELLY HIGH SCHOOL) (NORTH WING ADDITION) ""PLAN MODIFICATION FOR CHNGES TO THE ENGINEERING ROOM AND PLAN CLARIFICATIONS"" Construct a new 24,845 square foot science and technology classroom building on the existing Bishop Kelly High School campus. The addition will new classroom areas and a gathering area. Each of the classrooms and the gathering area are provided with additional exit doors directly to the exterior. This building is fully fire sprinklered for area increase and is fully alarmed. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/3/20188/6/20188/6/2018PPASS
DetailsMike Jordan
Please final fire life safety permit once the fire alarm permit is signed off (FIR17-00683). Contact Dominick Fery - ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps. Ok for perm occ.
FIRE-Final Inspection8/3/20188/6/20188/6/2018PPASS
DetailsTroy Cobbley
Life safety passed

Please final fire life safety permit once the fire alarm permit is signed off (FIR17-00683). Contact Dominick Fery - ###-####. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
BLD-Final7/13/20187/16/20187/16/2018APART
DetailsMike Jordan
Ross is the super. Last item to be reviewed is ceiling tile. Thank you! Phone #: ###-#### Inspection requested via web by Jackie Phelps. Ok for temp occ. while the remainder of the flooring and engineering room are completed.
FIRE-Final Inspection7/13/20187/16/20187/16/2018APART
DetailsTroy Cobbley
A temporary for life safety is being given until the Engineering Room is complete. The project related fire alarm permit will need to be finaled as well.

Ross is the super. Last item to be reviewed is ceiling tile. Thank you! Phone #: ###-#### Inspection requested via web by Jackie Phelps
FIRE-Hydro test above ground7/13/20187/13/20187/13/2018PCANC
DetailsTroy Cobbley
Duplicate inspection
FIRE-Final Inspection7/12/20187/13/20187/13/2018PFAIL
DetailsTroy Cobbley
Need all ceiling tile installed, Engineering Room complete (plan mod) and the project related fire alarm permit finaled. Per Ron Johnson a temporary will be ok when all of the ceiling tile has been installed


Ross is the super. Scheduling a final in the event our hardware and tile get done in time. We got approval to cover today. Also scheduled a conference to review as much as we can and then finish Monday if we have to. Thank you. Phone #: ###-#### Inspection requested via web by Jackie Phelps
FIRE-Conference7/12/20187/13/20187/13/2018PPART
DetailsTroy Cobbley
Fire life safety walk through - em lights, exit lights, egress lights, hardware and ceiling tile will be in progress for a final on Monday. Would like to get as much as we can looked at Friday and finish up Monday with the fire sprinkler contractor. (There is a chance we might achieve everything by Friday afternoon so will request a final as well) Phone #: ###-#### Inspection requested via web by Jackie Phelps
BLD-Final7/12/20187/13/20187/13/2018PPEND
DetailsMike Jordan
Ross is the super, this inspection will be dependent on if fire Life Safety passes which is also scheduled for tomorrow. Phone #: ###-#### Inspection requested via web by Jackie Phelps
BLD-Ceiling Grid Inspection7/11/20187/12/20187/12/2018PPASS
DetailsMike Jordan
Plumbing final (PLM17-03541) scheduled for AM on 7-12, if this passes, we would like approval to install all ceiling tile. Phone #: ###-#### Inspection requested via web by Jackie Phelps
FIRE-Final Inspection7/11/20187/12/20187/12/2018PFAIL
DetailsTroy Cobbley
Not ready for final yet. Need the sub permits taken care of

Ross Phone #: ###-####
BLD-Wall cover5/14/20185/15/20185/15/2018ADONE
DetailsMike Jordan
Isaac Phone #: ###-####
BLD-Wall cover5/9/20185/10/20185/10/2018PPART
DetailsMike Jordan
Ross Phone #: ###-####. Hardlids for restrooms ok, pending mech. and fire sprinkler.
BLD-Wall cover4/17/20184/18/20184/18/2018APASS
DetailsMike Jordan
Ross Phone #: ###-####. Interior steel stud framed walls in engineering room ok.
BLD-Framing/Rough-in4/2/20184/3/20184/3/2018PPASS
DetailsMike Jordan
Early afternoon please - Ross Phone #: ###-####. North wing classrooms ok for cover, except fot gathering room and engineering room. Also computer storage and computer work room at south wing ok.
BLD-Framing/Rough-in3/26/20183/26/20183/26/2018PPASS
DetailsMike Jordan
Ross Phone #: ###-####. North corridor wall only ok.
BLD-Wall cover2/26/20182/27/20182/27/2018APART
DetailsJim Sly
Ross Phone #: ###-####
Select walls as marked and initialed on thier condensed plan. Mainly South 1/2 of bldg.
BLD-Wall Bracing2/15/20182/15/20182/15/2018PFAIL
DetailsMike Jordan
shear-Ross Phone #: ###-####. INterior shear walls., missing screws or screws did not attach to studs or strapping.
BLD-Wall Bracing12/28/201712/28/201712/28/2017PPASS
DetailsMike Jordan
Ross Phone #: ###-####. Exterior shear walls (north,south and east walls) ok.
BLD-Framing/Rough-in12/21/201712/21/201712/21/2017PPASS
DetailsJim Storey
Ross-roof sheathing Phone #: ###-####balance of deck ok to cove noted on plan
BLD-Wall Bracing12/18/201712/19/201712/19/2017APASS
DetailsMike Jordan
Ross Phone #: ###-####. Roof nailing and straps at north east wing and north wing from grids 6.5 to 10.
BLD-Framing/Rough-in12/15/201712/18/201712/18/2017APART
DetailsMike Jordan
Roof sheathing & exterior walls - Ross Phone #: ###-####. Work in progress on nailing and installin straps at north east portion of building. Will recall when completed.
BLD-Other12/11/201712/11/201712/11/2017PPART
DetailsJim Sly
Roof nailing- Ross Phone #: ###-####
Roof deck nailing 6/12.....OK at South wing......West 1/2f.
BLD-Framing/Rough-in12/11/201712/11/201712/11/2017PPART
DetailsJim Sly
Ross Phone #: ###-####
Roof blocking...strapping OK West 1/2 of South wing
BLD-Other12/6/201712/6/201712/7/2017PPART
DetailsDave Hannah
roof sheathing // North wing classrooms // Ross Phone #: ###-#### see plans for area signed off
BLD-Framing/Rough-in11/6/201711/7/201711/7/2017APASS
DetailsMike Jordan
Ross Phone #: ###-####. Remainder of exterior steel stud framed walls. Ok to install OSB sheeting.
BLD-Framing/Rough-in11/3/201711/3/201711/3/2017PPASS
DetailsMike Jordan
After 3pm please- Ross Phone #: ###-####. Exterior steel stud framed walls from grids 7 to 10 on grid A. grids a to D on grid 10.
BLD-Other10/18/201710/23/201710/23/2017APART
DetailsMike Jordan
floor placement // Ross Phone #: ###-####. Welded wire mesh for slab on grade, west half of building. Will install concrete dobi's prior to placement. Will have specil inspection.
BLD-Footing10/4/201710/5/201710/5/2017APASS
DetailsMike Jordan
Ross-interior footings-pour time 9:00 Phone #: ###-####. Remainder of interior footings ok. Will have special inspection.
BLD-Foundation10/3/201710/3/201710/3/2017PPART
DetailsMike Jordan
Ross-interior footings Phone #: ###-####-pour time 2:00. Interior footings for corridors. Noted no city approved plans on site.
BLD-Conference9/19/20179/20/20179/20/2017ACANC
DetailsMike Jordan
Moved to pm for framing inspection of arch to tennis courts.