Information based on query as of Saturday, April 27, 2024.
Permit Information
Permit NumberBLD18-01064
StatusIssued
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameC30616 B37 Office Building
Customer Number 
ePlanReviewYes
Description
(MICRON BUILDING 37) (Project Management-Ron Hill) (Plan Mod #3 to recinfigure the fitness area) (Plan Mod #2 to revise shaft details and head of wall details) (PLAN MOD 1: TO REPLACE WATER CLOSETS WITH URINALS) Permit for the build out of a new three story office building to include exterior wall infill and finishes, general site work and the completion of the interior of the building. This builsing is fully fire sprinklered for area increase. The structural frame and foundation were permitted under BLD18-00157.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection7/5/20197/5/20197/5/2019 PASS
DetailsJim Storey
esi has occ requist unfiled.
BLD-Final2/21/20192/21/20192/21/2019APASS
DetailsJim Storey
final ok perm.
BLD-Final2/20/20192/21/20192/21/2019APASS
DetailsJim Storey
Dave Phone #: ###-#### final ok perm.
BLD-Final1/29/20191/30/20191/30/2019APART
DetailsJim Storey
Chris ###-#### ok for tco// foam protected at exterior wall//fire stop spk boiller rm// adj doors 15 lbs//occ load sign// mat at 2nd floor.
FIRE-Final Inspection1/29/20191/29/20191/29/2019PPASS
DetailsTroy Cobbley
Life safety passed.

Dave Phone #: ###-####
BLD-Final1/8/20191/9/20191/9/2019APASS
DetailsJim Storey
Dave Phone #: ###-#### temp occ ok for 2nd floor/ maintane protected exit access.
FIRE-Final Inspection1/8/20191/8/20191/8/2019PPART
DetailsTroy Cobbley
Life safety passed for the second floor. The fire alarm notification modification in the Lobby for the Link in Building 36 will need to be done prior to a phase 3 sign off.


second floor // Dave Phone #: ###-####
BLD-Framing/Rough-in1/3/20191/3/20191/3/2019PPASS
DetailsJim Storey
Please call Robert; Locker room walls and gyp. ceiling. Phone #: ###-#### Inspection requested via web by Chris Fuhrman walls and ceilling
BLD-Ceiling Grid Inspection1/3/20191/3/20191/3/2019PPASS
DetailsJim Storey
Please call Robert; Area C, 1st Floor Phone #: ###-#### Inspection requested via web by Chris Fuhrman
FIRE-Final Inspection12/27/201812/28/201812/28/2018PFAIL
DetailsJim Page
Fire alarms are not complete, need fire alarms for phase 2 finaled. Phase 2 is not ready for life fire safety inspection.

Dave-2nd floor of phase 2 Phone #: ###-####
BLD-Ceiling Grid Inspection12/27/201812/27/201812/27/2018PPASS
DetailsJim Storey
Please call Chris
1st Floor A ; B Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Ceiling Grid Inspection12/20/201812/21/201812/21/2018PPART
DetailsJim Storey
Please call Robert Snow - 1st floor areas A ; B Phone #: ###-#### Inspection requested via web by Chris Fuhrman ok west half/ pending tape and fire chalking at shaft nw
BLD-Ceiling Grid Inspection12/18/201812/19/201812/19/2018APASS
DetailsJim Storey
Please call Chris; Area 2C Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Final12/17/201812/17/201812/17/2018PPART
DetailsMike Jordan
Dave Phone #: ###-####. Ok to occupy the 3rd. floor, lobby and stairwell to link only.
BLD-Final12/14/201812/17/201812/17/2018PCANC
DetailsMike Jordan
lobby 2nd and 1st and 3rd floor-Dave Phone #: ###-####
FIRE-Final Inspection12/14/201812/17/201812/17/2018PPART
DetailsTroy Cobbley
Phase 1 life safety passed.

lobby 2nd and 1st and 3rd floor-Dave Phone #: ###-####
BLD-Framing/Rough-in12/17/201812/17/201812/17/2018PPASS
DetailsMike Jordan
1st. floor area C restrooms hardlids ok.
BLD-Framing/Rough-in12/17/201812/17/201812/17/2018ACANC
DetailsMike Jordan
Please call Chris; 2nd floor restroom ceilings area C Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Final12/14/201812/14/201812/14/2018PCANC
DetailsMike Jordan
dave Phone #: ###-####
FIRE-Final Inspection12/14/201812/14/201812/14/2018PFAIL
DetailsJim Page
Need signage leading from exterior to fire sprinkler riser room. Install fire lane signage as discussed. Provide notification over fire department connection, currently no bell or A/V device is installed. Stairwells need to be 100% complete before TCO can be authorized for life fire safety. Elevator smoke detectors report as a supervisor, detectors need to report as general alarm.

dave Phone #: ###-####
FIRE-Final Inspection12/13/201812/14/201812/14/2018AFAIL
DetailsTroy Cobbley
Todays inspection was for the third floor. Need additional emergency lighting in the first floor Main Lobby and the Entry, Need room signage, Need fire dept. access signage, Need the fire alarm system complete in all areas as per previous notes and for all areas in the common path of egress such as the Link, Provide sprinkler canopies in the path of egress, Provide key for knox box, Provide exit signs at the exterior exit doors at the bottom of the stair toweres

Dave Phone #: ###-####
BLD-Final12/12/201812/13/201812/13/2018PCANC
DetailsMike Jordan
Dave Phone #: ###-####
FIRE-Final Inspection12/13/201812/13/201812/13/2018PFAIL
DetailsJim Page
Need fire alarm and fire sprinklers finaled for Phase 1 TCO requested areas before life fire safety inspection will be performed.

Call Chris - Phase 1 Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Ceiling Grid Inspection12/12/201812/13/201812/13/2018APASS
DetailsMike Jordan
Please call Chris; 1st floor lobby Phone #: ###-#### Inspection requested via web by Chris Fuhrman. 1st. floor lobby only ok.
BLD-Framing/Rough-in12/12/201812/12/201812/12/2018PPASS
DetailsMike Jordan
Chris Phone #: ###-####. Hardlids, 1st floor restrooms in area 1A. 2nd.floor hardlids Room 201 excersise room ok.
BLD-Framing/Rough-in12/10/201812/11/201812/11/2018APASS
DetailsMike Jordan
Chris Phone #: ###-####. Hard lids at 2nd floor, area EC201 only ok.
FIRE-Conference11/28/201811/28/201811/28/2018ADONE
DetailsJim Page
Noted that office furniture is still being placed on level 3 after GC notification that office furniture was to not be set until active fire protection is in place, no fire sprinklers are active and no fire alarms are active. Floor is being loaded with extra fuel without any active automatic fire protection in place.
BLD-Framing/Rough-in11/27/201811/27/201811/27/2018PPASS
DetailsJim Storey
Please call Chris
Area 2C RR hard ceiling, corridor 101 hard ceiling Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Ceiling Grid Inspection11/26/201811/26/201811/26/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### 2nd floor areas a and b
BLD-Ceiling Grid Inspection11/19/201811/20/201811/20/2018ADEFR
DetailsJim Sly
Chris Phone #: ###-####
Notified Chris..............
BLD-Framing/Rough-in11/15/201811/15/201811/15/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### hard ceillings 2nd floor/ restarm west, stair east
FIRE-Conference11/15/201811/15/201811/15/2018ADONE
DetailsJim Page
Had a previous conversation with GC about installing office furniture before fire sprinklers and fire alarms are active. Discussed with Ron Johnson, placing of office furniture is not allowed, office furniture has been installed on level 3 after conversation stating that funiture is not to be installed. No other office furniture is authorized. The GC has been notified verbally that no office furniture is to be installed due to the increased fuel load that the furniture presents. If more office furniture is installed after this entry then the project will have a stop work notice placed and the project will be red tagged, this action is supported per conversation with Ron Johnson, Assistant Fire Marshall.
BLD-Framing/Rough-in11/13/201811/13/201811/14/2018PPART
DetailsJim Storey
Chris Phone #: ###-#### 1st floor restarms ceillings ok 2nd floor shafts sealled// expantinon joint in stair encloser need listing.
BLD-Framing/Rough-in11/5/201811/5/201811/5/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### stair 1# and 2nd floor restaroom 2
BLD-Framing/Rough-in11/2/201811/2/201811/2/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### 3rd floor 80 % ok to drop ceilling/ shafts ok
BLD-Framing/Rough-in10/31/201810/31/201810/31/2018PPART
DetailsJim Storey
Chris Phone #: ###-#### shafts west end ok
BLD-Foundation10/29/201810/30/201810/30/2018APASS
DetailsJim Storey
Dave-reinforcing rebar Phone #: 208-631-lab on grade
BLD-Framing/Rough-in10/26/201810/29/201810/29/2018APART
DetailsJim Storey
Chris Phone #: ###-#### hard ceilling first secnond floors ok up to stairs ok/ restarooms ok
BLD-Energy code compliance10/24/201810/24/201810/24/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### backing ok in restarooms/ insulation on walk bridge ok// framing exterior sides ok
BLD-Framing/Rough-in10/18/201810/18/201810/18/2018PPASS
DetailsJim Storey
Chris-per Chris-inspection has nothing to do with the plan mod Phone #: ###-#### all exterior walls ok to cover/ elavator ok to cover/ ceilling 3 rd floor west half ok.
BLD-Framing/Rough-in10/15/201810/15/201810/15/2018PPART
DetailsJim Storey
Chris-as per Chris-thisinspection does not have anything to do with the plan mod that was turned in Phone #: ###-#### lobby 1st and 2nd floors insulation ok// south wall pending insulation and vappor barrior at canopy.
BLD-Energy code compliance10/8/201810/8/201810/8/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### 3rd floor shaft tops ok// ok to proceed with outsde membrane and fire stopping// hard ceilling break rm 3rd fl se corner.
BLD-Framing/Rough-in10/3/201810/3/201810/3/2018PPASS
DetailsJim Storey
Chris Phone #: ###-#### top of shafts13 and 15 3rd/top 12 on 2nd/ restarooms 3 rd ceillings ok to cover
BLD-Framing/Rough-in10/1/201810/1/201810/1/2018PPART
DetailsJim Storey
Chris Phone #: ###-####
2nd floor #7 1 in membrane missing//2nd floor #5 and #9 core and 5/8 exstend to beam web/ 3 fl #13 an #15 complet top of shaft assembly./3 fl #13 and 15 exterior membrane.
BLD-Foundation9/27/20189/27/20189/28/2018PPASS
DetailsJim Storey
Dave-slab on grade-reinforcement for loading dock Phone #: ###-####
BLD-Wall Bracing9/20/20189/20/20189/20/2018PPASS
DetailsJim Storey
Chris-per Chris does not have anything to do with the plan mod Phone #: ###-#### ok to cover.
BLD-Framing/Rough-in9/20/20189/20/20189/20/2018PPASS
DetailsJim Storey
Chris-per Chris does not have anything to do with the plan mod Phone #: ###-#### rain ledder/ ele under floor// pic flor to floor/ pending as noted on site
BLD-Framing/Rough-in9/13/20189/14/20189/14/2018APASS
DetailsJim Storey
Exterior walls section C; North, East and South. Exterior wall North Insulation 1st floor; 3rd Floor Shafts 5 ,6, 7 ; 9; Second Floor Shafts 1 ; 8; Restroom 307 ; 308 walls Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Framing/Rough-in9/13/20189/13/20189/13/2018PCANC
DetailsMike Jordan
Exterior walls section C; North, East and South. Exterior wall North Insulation 1st floor; 3rd Floor Shafts 5 & 9; Second Floor Shafts 1 & 8; Restroom 307 & 308 walls Phone #: ###-#### >> Inspection requested via web by Chris Fuhrman Inspection cancelled from web by: Chris Fuhrman
BLD-Framing/Rough-in9/13/20189/13/20189/13/2018PCANC
DetailsMike Jordan
Exterior walls section C; North, East and South. Exterior wall North Insulation 1st floor; 3rd Floor Shafts 5 & 9; Second Floor Shafts 1 & 8; Restroom 307 & 308 walls Phone #: ###-#### >> Inspection requested via web by Chris Fuhrman Inspection cancelled from web by: Chris Fuhrman
BLD-Framing/Rough-in9/11/20189/12/20189/12/2018ACANC
DetailsJim Storey
Area C Exterior Walls (N, E & S); Insulation / Vapor Barrier North Wall of Electrical 1st Floor Phone #: ###-#### >> Inspection requested via web by Chris Fuhrman Inspection cancelled from web by: Chris Fuhrman
BLD-Wall cover9/5/20189/5/20189/5/2018PPASS
DetailsJim Storey
Please call Chris when in route Phone #: ###-#### Inspection requested via web by Chris Fuhrman core board framing/ pipe wrap./ ok on 3dr and 2nd floors at rtu 5 and 9.
BLD-Wall cover8/28/20188/29/20188/29/2018AFAIL
DetailsJim Storey
Please call chris when in route - firewalls and shafts Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Conference8/24/20188/24/20188/24/2018PPASS
DetailsJim Storey
Review Stairway Door and Shaft Wall Details
Please call Chris Fuhrman when in route
Thank you, Phone #: ###-#### Inspection requested via web by Chris Fuhrman noted w/chris submitals in his office.
BLD-Wall cover8/20/20188/20/20188/20/2018PPART
DetailsJim Storey
Fire wall 3rd floor section a and framing 3rd floor section c Phone #: ###-#### Inspection requested via web by Chris Fuhrman west shaft tops ok/ east part.
BLD-Framing/Rough-in8/16/20188/17/20188/17/2018ANR
DetailsJim Storey
3rd floor framing area C // Dave Perkins Phone #: ###-#### c/n isued// provide listingforhead of wall assembly and material used.//s/fd instaled 1/2 in 1/2 out of wall assemblies provide listing./provide core board wall/shaft listing for aplacation at door jambs/ bar joist membrane penatrations.// provide fire stopping listings and products from all trades for all penatrations.
BLD-Foundation8/15/20188/16/20188/16/2018APASS
DetailsJim Storey
rebar // Dave Phone #: ###-####
BLD-Conference8/13/20188/14/20188/14/2018PPASS
DetailsJim Storey
Meet to review shaft conflicts with CTA 1:30PM OK per Jim Storey Phone #: ###-#### Inspection requested via web by Chris Fuhrman
BLD-Energy code compliance8/9/20188/10/20188/10/2018APASS
DetailsJim Storey
Dave Phone #: ###-#### 1st floor ok to cover exterior walls and interior/ not ok for cover shafts and stair enclosers.
BLD-Framing/Rough-in7/18/20187/19/20187/19/2018APASS
DetailsJim Storey
Levels 2 & 3 interior - Dave Phone #: ###-#### ok to cover noter on plan all but shaft areas
BLD-Framing/Rough-in7/12/20187/12/20187/12/2018PFAIL
DetailsJim Storey
Dave Phone #: ###-#### 2nd floor clip to studs screws grid a and L
BLD-Framing/Rough-in7/10/20187/10/20187/10/2018PPASS
DetailsJim Storey
3rd fl ext framing - Dave Phone #: ###-#### exterior walls as noted ok to insulate// shaft elavator and stair encloser rated walls need evauated for clearance.