BLD-Final | 5/7/2020 | 5/7/2020 | 5/8/2020 | P | PASS |
Tony Young
|
|
|
Nick **Screened* Phone #: ###-####
|
FIRE-Final Inspection | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, solar panel inspection is complete under BLD19-04240, final life fire safety inspection is complete.
Nick Phone #: ###-####
|
BLD-Final | 4/21/2020 | 4/21/2020 | 4/22/2020 | P | NR |
Tony Young
|
|
|
screened - as far you know - solar permit final scheduled for am // Nick Phone #: ###-####// needs f/l/s full pass and electrical final 1st
|
BLD-Final | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | NR |
Tony Young
|
|
|
screened - as far you know - solar permit final scheduled for am // Nick Phone #: ###-####// needs electrical final 1st and fire and life safety final pass
|
BLD-Final | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | PART |
Mike Jordan
|
|
|
Ken Phone #: ###-####. Tempered glazing has been installed. ADA toilets on order. Commisioning has been completed and report is being written. Ok for temp occ.
|
FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given with boise fire approval. Need a permit for the solar panel/system and one additional exit discharge light is needed at the south east exit door.
Ken Phone #: ###-####
|
BLD-Final | 10/18/2019 | 10/21/2019 | 10/21/2019 | P | NR |
Tony Young
|
|
|
Ken Phone #: ###-####,, walk through only,, needs Accessibility to meet plans,, egress in dorms to function, signage, tempered glass, trades, etc.
|
FIRE-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | CANC |
Troy Cobbley
|
|
|
To be canceled per Ken since they are still having generator issues. Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | FAIL |
Troy Cobbley
|
|
|
Provide information for the change to a diesel gererator, provide testing of the automatic switch over of the generator since it did not function, provide signage for the gererator as discussed, provide testing of the exit signs and emergency lights, provide fire lane signage. See the review comments for items marked in blue.
Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/16/2019 | 10/17/2019 | 10/17/2019 | A | FAIL |
Troy Cobbley
|
|
|
No inspection performed. No city approved plans or small documents on site. Ken Phone #: ###-####
|
FIRE-Final Inspection | 10/15/2019 | 10/16/2019 | 10/16/2019 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled due to time constraints due to work load. Ken Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Tony Young
|
|
|
Ken Phone #: ###-####
|
BLD-Wall cover | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PART |
Tony Young
|
|
|
Phone #: 2088300687 >> Inspection requested via mobile web by Hard lids for cover,, ok pending special inspection and also trades
|
BLD-Wall cover | 6/5/2019 | 6/5/2019 | 6/5/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Fire stop behind outlets,, 4 areas ok
|
BLD-Energy code compliance | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2084777563 >> Inspection requested via mobile web by Lalo - insulation in wall,, work in progress,, ok to cover as needed to stay in progress
|
BLD-Framing/Rough-in | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2084777563 >> Inspection requested via mobile web by Lalo Delgado - Framer
|
BLD-Other | 4/18/2019 | 4/19/2019 | 4/19/2019 | P | CANC |
Jim Sly
|
|
|
Call prior to going Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening
|
BLD-Other | 4/18/2019 | 4/19/2019 | 4/19/2019 | A | PASS |
Jim Sly
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening Remainder of shear wall fastening........OK.
|
BLD-Framing/Rough-in | 4/9/2019 | 4/11/2019 | 4/11/2019 | A | PART |
Tony Young
|
|
|
Call prior to going Phone #: 2088300687 >> Inspection requested via mobile web by Shear wall fastening,, work in progress on various walls,, ok so far
|
BLD-Conference | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by Justin// frame ?s on bracing,, doing straps and panels at the same time,, ok
|
BLD-Other | 2/5/2019 | 2/6/2019 | 2/6/2019 | P | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088300687 >> Inspection requested via mobile web by CMU Wall Grout,, pending special inspection
|
BLD-Concrete | 1/22/2019 | 1/23/2019 | 1/23/2019 | A | PART |
Jim Sly
|
|
|
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Slab pour-MTI inspected OK pendind MTI special inspection, tests and approvals.
|
BLD-Concrete | 1/21/2019 | 1/22/2019 | 1/22/2019 | P | DEFR |
Dave Hannah
|
|
|
As late as possible Phone #: 2088502262 >> Inspection requested via mobile web by Slab pour-MTI inspected (ouit of time)
|
BLD-Footing | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PEND |
Tony Young
|
|
|
Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection
|
BLD-Foundation | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | PEND |
Tony Young
|
|
|
Phone #: 2088502262 >> Inspection requested via mobile web by Tim-10:30am-MTI scheduled,, ok pending report
|
BLD-Foundation | 11/27/2018 | 11/29/2018 | 11/29/2018 | A | PART |
Jim Storey
|
|
|
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim 10am pour time bar clearance si on site to follow up.
|
BLD-Conference | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PART |
Brandon Shaw
|
|
|
Special inspection required, North East, South East and Wesr footings, work in progress...
|
BLD-Footing | 11/15/2018 | 11/19/2018 | 11/19/2018 | A | PART |
Tony Young
|
|
|
As early as possible Phone #: 2088502262 >> Inspection requested via mobile web by Tim,, special inspection required,, looked at the plans,, south and east footings,, work in progress
|