Permit Information
Permit NumberELE19-02808
StatusFinaled
Name MOUNTAIN POWER ELECT
Site Address 999 W MAIN ST Unit: 110
Project Name 
Customer Number19-026
ePlanReviewNo
Description
Alteration: Provide the electrical work associated with the Kin Bar and Restaurant remodel.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final4/29/20204/29/20204/29/2020APASS
DetailsRock A. Hudson
Phone #: ###-#### Inspection requested via web by Jeremy Cloud
Card signed. Final ok
Final3/19/20203/20/20203/20/2020AFAIL
DetailsRock A. Hudson
Phone #: ###-#### Inspection requested via web by Jeremy Cloud
As per 2015 IECC C408.3.1 a lighting system commissioning report shall be completed by the registered disign professional prior to final.
BCC 4-05-32, No code violation shall be retained. AC disconnecting means for tasting lounge is missing interior cover and has exposed wiring to public and is located next to a gathering shelter on east side of tasting lounge.
Final3/16/20203/17/20203/17/2020APART
DetailsRock A. Hudson
Partial Final. Request inspection after 10AM. Phone #: ###-#### Inspection requested via web by Jeremy Cloud
Access to in duct heater not needed due to unit abandoned and access patched. Emergency egress ballast for rear patio in route to site. No card posted. TCO for kitchen and bar ok
Final3/13/20203/16/20203/16/2020PFAIL
DetailsRock A. Hudson
Partial Final Phone #: ###-#### Inspection requested via web by Jeremy Cloud
110.22- Main switches powering this space shall be labelled.
300.22- Electrical penetrations shall be sealed. Cooler.
422.31- Hardwired appliances shall have disconnecting means.
* Patio egress not operational.
Electrical Rough-In3/11/20203/12/20203/12/2020APASS
DetailsRock A. Hudson
Phone #: ###-#### Inspection requested via web by Jeremy Cloud
Adequate access shall be provided for an in duct heater in walkway ceiling above hardlid.
Grid for tasting bar and panel corridor rough in ok cover
Electrical Rough-In2/17/20202/18/20202/18/2020PPASS
DetailsRock A. Hudson
Kitchen ceiling Phone #: ###-#### Inspection requested via web by Jeremy Cloud
Main kitchen area grid only rough in ok cover.
Electrical Rough-In1/20/20201/21/20201/21/2020APASS
DetailsRock A. Hudson
walls/ceiling for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Back foyer walls complete walls and hardlid rough in ok cover
Electrical Rough-In1/9/20201/10/20201/10/2020APASS
DetailsRock A. Hudson
walls/ceilings in storefront for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel
110.26- Access shall be provided for all electrical equipment. HVAC unit buried above hardlid.
110.26(A) and (A)(4)(c)- Work space shall be provided for HVAC electrical enclosure and door of enclosure shall open to at least 90 degrees. Copper plumbing lines run in front of door blocking work space and door operation.
Must be corrected for grid inspections.
Tasting reception area outer walls and ceiling not ready.
Back wall of tasting reception area and vestibule walls and ceiling rough in ok cover.
Electrical Rough-In12/11/201912/12/201912/12/2019APASS
DetailsRock A. Hudson
Bar-Kitchen wall Phone #: ###-#### Inspection requested via web by Mike McCarrel Kitchen wall added rough in ok cover
Electrical Rough-In12/10/201912/11/201912/11/2019APASS
DetailsRock A. Hudson
walls/ceilings for cover in tasting lounge Phone #: ###-#### Inspection requested via web by Mike McCarrel
Areas noted rough in ok cover
Electrical Rough-In11/21/201911/22/201911/22/2019APASS
DetailsRock A. Hudson
Phone #: ###-#### Inspection requested via web by Mike McCarrel
Discussed receptacle locations in face up positions. As per 406.5(E),(F), and (H)- restrictions for counter top, work areas, and seating areas.
Tasting bar soffits and duct pocket walls rough in ok cover
Electrical Rough-In10/17/201910/18/201910/18/2019PPASS
DetailsRock A. Hudson
Walls for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Walls and hardlids marked on contractor print rough in ok cover
Electrical Rough-In10/2/201910/3/201910/3/2019PPASS
DetailsDaryl DeGrange
Walls for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel Small amount of one side completed, spoke with Magnum from Kincade construction, discussed no cover without ok to cover inspection. rough-in ok cover walls marked in orange/ DKD initials on sheet AZ-1
Electrical Rough-In8/13/20198/14/20198/14/2019APASS
DetailsRock A. Hudson
Underslab raceways for cover Phone #: ###-#### Inspection requested via web by Mike McCarrel
Conduits noted rough in ok cover
Conference8/9/20198/12/20198/12/2019PPASS
DetailsRock A. Hudson
Phone #: ###-#### Inspection requested via web by Mike McCarrel
Discussed equipment grounding requirements on load side of transformer to 120/208 sub panel boards. As per 250.30(A)(1 thru 8) no connection is allowed to the grounded conductor and non-current carrying metal parts on load side of transformer in this case a system bonding jumper shall be installed at transformer. Equipment grounds shall be added to sub-feeds for panel boards due to non-metallic raceways present underground.
Also discussed 210.8(B) GFCI requirements for other than dwelling kitchens. If a receptacles are installed for equipment in kitchen area they shall have GFCI protection, if chenged to hard wired appliances additional disconnecting means is required as per 422.31(A) and (B).