Permit Information
Permit NumberESC16-01582
StatusFinaled
Name DEAN HINMAN
Site Address 2919 N 26TH ST
Project NameOdom Estates Subdivision
Customer Number 
ePlanReviewNo
Description
Project involves the extension of Neff Street to 26th Street, two common driveways, sewer, water, irrigation, drainage facilies, roadway utilities, and landscaping. No GRD permit required by PW. Drainage flows to the west, ESC plan calls for silt fence sediment control on the west limit of disturbance. Other BMPs include stabilized rock construction entrance, concrete washout containment, trash containment, and permit signage. Inlet protection should be installed on new subdivsion storm drains after installation. Site preparation and installation of BMPs required prior to construction, call 608-7070 to schedule. EPA eNOI filed for CGP, tracking # IDR12B040.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final6/28/20196/28/20196/28/2019PPASS
DetailsAndy J. Long
All parcels complete. Temporary BMPs removed. ESC permit finaled.
Aging Inspection5/6/20195/6/20195/6/2019 PASS
DetailsMichael Zawacki
Last few homes under construction. DI protection still installed on Neff. No ESC issuea at site.
Aging Inspection3/4/20193/4/20193/4/2019 PASS
DetailsMichael Zawacki
Most homes complete, no ESC issues at site.
Aging Inspection12/31/201812/31/201812/31/2018 PASS
DetailsMichael Zawacki
Work on multiple SFH. No dirt or trash. No ESC issues.
Aging Inspection10/29/201810/29/201810/29/2018 PART
DetailsMichael Zawacki
Still some homes being built. Some dirt on sidewalks and trash from building waste. No major ESC issues.
Aging Inspection8/27/20188/27/20188/27/2018 PASS
DetailsMichael Zawacki
most homes complete. Area is clean.
Aging Inspection6/25/20186/25/20186/25/2018 PASS
DetailsMichael Zawacki
DIs still protected on 26th. Framing on two homes. Few lots still vacant and starting to grow weeds. No ESC issues at site.
Aging Inspection4/23/20184/23/20184/23/2018 PASS
DetailsMichael Zawacki
WIP on one home. Still a few vacant lots in development. All Dis are protected. Some dirt in gutters.
General Inspection2/19/20182/19/20182/20/2018 CANC
DetailsAndy J. Long
General Inspection12/18/201712/18/201712/18/2017 PASS
DetailsAndy J. Long
General Inspection10/18/201710/18/201710/18/2017PFAIL
DetailsMichael Zawacki
Paint/stucco just being dumped on ground, no washout or containment.
General Inspection10/4/201710/4/201710/4/2017 PASS
DetailsAndy J. Long
General Inspection8/4/20178/4/20178/4/2017PPASS
DetailsAndy J. Long
WIP on SFHs at Odom Estates. BMPs installed. No trackout or discharges to 26th or west on Neff.
General Inspection6/14/20176/16/20176/16/2017ACANC
DetailsMelissa Jannusch
General Inspection5/1/20175/1/20175/1/2017PPASS
DetailsAndy J. Long
BMPs installed. Still need to regrade lots and remove stockpile. No trackout, fugitive dust, or other issues observed. Permit and SWPPP posted.
Complaint Inspection4/18/20174/18/20174/18/2017PPASS
DetailsAndy J. Long
New storm drain inlets on 26th and on Neff side of Odom Estates have now had sediment filter bags installed this morning. Some minor trackout on Neff between two lots at entrance is to be swept later this week.

Excess stockpiles and tree debris from the irrigation ditch culvert will be removed end of this week or next depending on when the soil dries enough to get equipment on lots.

Talked to RP Dean via phone, met onsite superintendant Terrel.

Will check in next week.
General Inspection3/15/20173/28/20173/28/2017PPASS
DetailsMelissa Jannusch
WIP on curbs and gutters. No significant trackout. Project ok.
General Inspection3/15/20173/15/20173/15/2017APASS
DetailsAndy J. Long
WIP on utilities. Limited BMPs installed, permit sign posted. WIP installing communications utilities. No significant trackout or complaints received. No corrections requested
General Inspection12/1/201612/5/201612/5/2016PPEND
DetailsAndy J. Long
No activity, no corrections requested at this time. Site preparation not yet completed
Site Preparation12/1/201612/1/201612/1/2016PPASS
DetailsAndy J. Long
Excavation equipment staged and some minor rough grading has been completed. No activity or personnel on site at time of inspection. No trackout or other issues observed at site, will re-inspect next week for SWPPP sign posting and sediment control between Odom Estates and Chesler Park subdivision projects.