Permit Information
Permit NumberESC17-00406
StatusFinaled
Name Pat Klein
Site Address 519 N 9TH ST
Project NameBHS Gym and Perf. Arts Reno.
Customer Number 
ePlanReviewNo
Description
BMPs: RP is TBD. Gutter protection (wattles with sand bags) along north gutter, DI protection, material storage, concrete washout, dust control prevention. Campus improvements for Boise High. The improvements include interior renovation of the existing gym and demo of the adjacent music building. A new 2 story building including basement will be constructed in its place. Minor site improvements will include an ADA compliant ramp at the main vestibule entry.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Aging Inspection11/11/201911/11/201911/12/2019 CANC
DetailsMichael Zawacki
DOC - Permit Finaled11/12/201911/12/201911/12/2019PPASS
DetailsMichael Zawacki
Aging Inspection9/9/20199/9/20199/9/2019 PASS
DetailsMichael Zawacki
Exterior work completed, no esc issues at site.
Site Final7/9/20197/23/20197/24/2019PNR
DetailsAndy J. Long
Site Final7/1/20197/9/20197/9/2019APEND
DetailsAndy J. Long
notify contractor to remove DI bag
Site Final6/24/20196/26/20197/1/2019ACANC
DetailsAndy J. Long
Site Final7/1/20197/1/20197/1/2019PNR
DetailsAndy J. Long
Some minor landscaping, alley paving, and exterior clean up remaining. Temporary DI sediment bag installed at 10th and Washington needs to be removed.

Will follow up with contractor next week.
Aging Inspection6/24/20196/24/20196/24/2019 CANC
DetailsAndy J. Long
Aging Inspection4/22/20194/22/20194/22/2019 PASS
DetailsMichael Zawacki
Walkway between school and gym open. Work still in interior. No ESC issues.
Aging Inspection12/17/201812/17/201812/17/2018 PASS
DetailsMichael Zawacki
Site contained no ESC issues.
Aging Inspection10/17/201810/17/201810/17/2018 PASS
DetailsMichael Zawacki
All disturbances contained in fenced area. Most excavations are below surrounding grade. Dumpster on site, materials stored on concrete pad. Mason work looks completed on outside, no dust from cutting at time of inspection.
General Inspection8/17/20188/20/20188/20/2018APASS
DetailsAndy J. Long
No trackout from site to 9th or 10th. Stockpiles stored within center of site. No corrections requested
General Inspection7/30/20188/14/20188/17/2018ACANC
DetailsAndy J. Long
General Inspection7/30/20187/30/20187/30/2018 PASS
DetailsAndy J. Long
No trackout or discharges to 9th or 10 street, stockpile stored in alley north of gym will need protection if remaining onsite. Currently in use, dry conditions.
Random Inspection5/29/20185/29/20185/29/2018PPASS
DetailsAndy J. Long
General Inspection5/7/20185/7/20185/7/2018PPASS
DetailsAndy J. Long
WIP on gym retrofit. No discharges or trackout
General Inspection4/4/20184/6/20184/6/2018APASS
DetailsAndy J. Long
General Inspection3/28/20183/28/20184/4/2018 CANC
DetailsAndy J. Long
rescheduled
General Inspection1/26/20181/26/20181/26/2018 PEND
DetailsMichael Zawacki
Two corrections issued vebally.
McAlvain has an overflowing Eco-pan, asked them to have it replaced.
DI in 10th street unprotected and receiving runoff from site, Asked CM company to get it taken care of.
Site Preparation10/18/201710/25/201710/27/2017ADONE
DetailsMichael Zawacki
Need ESCP and spill kit on site.
General Inspection10/18/201710/18/201710/18/2017PPASS
DetailsMichael Zawacki
No site prep conducted. Check for BMPs and any violations.
Site clean and BMPs installed. No spill kit or ESCP on site. Scheduled follow up for next week.
Aging Inspection2/18/20192/18/2019   
DetailsAndy J. Long