Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberESC17-01488
StatusFinaled
Name DON MORGAN
Site Address 8485 S FEDERAL WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
(LM CONSTRUCTION) Grading permit to excavate, grade and compact site earth materials in preparation for a new shell building to be constructed under a future building permit, filed under BLD18-00596. All work to be performed as approved by the Public Works Department and Planning & Zoning Department under DRH17-00143. Scope of work includes underground utilities only. No buildings or footings are allowed to be constructed under this permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final10/7/201910/17/201910/18/2019PPASS
DetailsMichael Zawacki
General Inspection10/7/201910/7/201910/7/2019 PASS
DetailsAndy J. Long
General Inspection9/6/20199/6/20199/6/2019 CANC
DetailsMichael Zawacki
General Inspection8/1/20198/6/20198/7/2019PPASS
DetailsAndy J. Long
No new activity. Building appears to be vacant. Will check for site final next inspection
General Inspection8/1/20198/1/20198/1/2019 CANC
DetailsAndy J. Long
General Inspection7/1/20197/1/20197/1/2019 CANC
DetailsAndy J. Long
General Inspection5/30/20195/30/20195/30/2019 PASS
DetailsMichael Zawacki
All work completed. Wattle is still around seepage beds off of Federal Way.
General Inspection4/29/20194/29/20194/29/2019 PASS
DetailsAndy J. Long
General Inspection3/29/20193/29/20194/1/2019 CANC
DetailsAndy J. Long
General Inspection2/26/20192/26/20192/27/2019 PASS
DetailsMichael Zawacki
Work completed. Landscaping not complete, still no grass. Wattles are installed around seepage beds.
General Inspection1/22/20191/22/20191/22/2019 CANC
DetailsAndy J. Long
General Inspection12/17/201812/17/201812/17/2018PPASS
DetailsMichael Zawacki
Landscapers on site prepping disturbed areas. Exterior building waork and parking lot complete.
General Inspection11/20/201811/20/201811/20/2018 PASS
DetailsMichael Zawacki
Entire lot around building paved. Job trailer and storage is on bare lot to east. No trackout or issues leading onto Federal Way.
Site Preparation10/18/201810/19/201810/19/2018ACANC
DetailsMichael Zawacki
Meant to schedule an inspection with public works.
General Inspection10/19/201810/19/201810/19/2018PCANC
DetailsAndy J. Long
Tracking Control10/10/201810/10/201810/11/2018PPASS
DetailsAndy J. Long
Rock construction installed. Track out from yesterday has been cleaned. Sweeper unit still on site.

Good response in cleaning, requested that other entrance on staging yard east of site have rock and that sweeper should been ran on shoulder of road this afternoon.
General Inspection10/8/201810/10/201810/10/2018AFAIL
DetailsAndy J. Long
check on site after rain.

Trackout from road shoulder and site.

Correction request to install rock construction entrance/track pad and sweep/clean up street.

Project manager has rented sweeper unit and is cleaning road. States that a construction entrance has been installed. Follow up scheduled.
Tracking Control10/4/201810/4/201810/8/2018PCANC
DetailsAndy J. Long
Tracking Control10/8/201810/8/201810/8/2018PPEND
DetailsAndy J. Long
No trackout at site. Did entrance inspection with project supervisor Bryce. Reviewed installation specifications and noted they will need to consider location for employees to park without causing trackout. Temporary 3/4 mix placed at the southeast/east entrance onto Federal Way.

Site is to supposed to be paved before the end of the month. Will follow up this week after rainfall.
BMP Violation10/4/201810/4/201810/4/2018AFAIL
DetailsAndy J. Long
No construction entrance or designated access for deliveries or employee parking. Need to designate a parking area and location for heavy duty construction entrance. Currenly parking in dirt/mud along shoulder of road.
General Inspection9/20/20189/20/20189/20/2018PPASS
DetailsMichael Zawacki
Building pad and walls complete. Water wagon on site and being used. Site is clean. Alta is on edge of federal way doing trench work.
General Inspection8/20/20188/21/20188/21/2018APASS
DetailsMichael Zawacki
Working on building pads. Multiple washouts on site, secondary containmnet for diesel/form oils. Water wagon on site. Workers parking mostly off site, no dust issues.
Site Preparation8/6/20188/21/20188/20/2018PCANC
DetailsAndy J. Long
data entry error
General Inspection8/6/20188/6/20188/6/2018PPASS
DetailsAndy J. Long
Site grading completed, now working on foundation and should be vertical soon. No trackout, fugitive dust, or other violations observed.
General Inspection5/10/20185/10/20185/10/2018PPASS
DetailsMichael Zawacki
Site grading underway. Entrances are built, water truck on site. Some dust is being kicked up by front end loader near haul road and stockpile area. Weekly site inspections are being done by Specialty Supply.