Site Final | 10/7/2019 | 10/17/2019 | 10/18/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/6/2019 | 9/6/2019 | 9/6/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 8/1/2019 | 8/6/2019 | 8/7/2019 | P | PASS |
Andy J. Long
|
|
|
No new activity. Building appears to be vacant. Will check for site final next inspection
|
General Inspection | 8/1/2019 | 8/1/2019 | 8/1/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/1/2019 | 7/1/2019 | 7/1/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/30/2019 | 5/30/2019 | 5/30/2019 | | PASS |
Michael Zawacki
|
|
|
All work completed. Wattle is still around seepage beds off of Federal Way.
|
General Inspection | 4/29/2019 | 4/29/2019 | 4/29/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/29/2019 | 3/29/2019 | 4/1/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/26/2019 | 2/26/2019 | 2/27/2019 | | PASS |
Michael Zawacki
|
|
|
Work completed. Landscaping not complete, still no grass. Wattles are installed around seepage beds.
|
General Inspection | 1/22/2019 | 1/22/2019 | 1/22/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Michael Zawacki
|
|
|
Landscapers on site prepping disturbed areas. Exterior building waork and parking lot complete.
|
General Inspection | 11/20/2018 | 11/20/2018 | 11/20/2018 | | PASS |
Michael Zawacki
|
|
|
Entire lot around building paved. Job trailer and storage is on bare lot to east. No trackout or issues leading onto Federal Way.
|
Site Preparation | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | CANC |
Michael Zawacki
|
|
|
Meant to schedule an inspection with public works.
|
General Inspection | 10/19/2018 | 10/19/2018 | 10/19/2018 | P | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 10/10/2018 | 10/10/2018 | 10/11/2018 | P | PASS |
Andy J. Long
|
|
|
Rock construction installed. Track out from yesterday has been cleaned. Sweeper unit still on site.
Good response in cleaning, requested that other entrance on staging yard east of site have rock and that sweeper should been ran on shoulder of road this afternoon.
|
General Inspection | 10/8/2018 | 10/10/2018 | 10/10/2018 | A | FAIL |
Andy J. Long
|
|
|
check on site after rain.
Trackout from road shoulder and site.
Correction request to install rock construction entrance/track pad and sweep/clean up street.
Project manager has rented sweeper unit and is cleaning road. States that a construction entrance has been installed. Follow up scheduled.
|
Tracking Control | 10/4/2018 | 10/4/2018 | 10/8/2018 | P | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 10/8/2018 | 10/8/2018 | 10/8/2018 | P | PEND |
Andy J. Long
|
|
|
No trackout at site. Did entrance inspection with project supervisor Bryce. Reviewed installation specifications and noted they will need to consider location for employees to park without causing trackout. Temporary 3/4 mix placed at the southeast/east entrance onto Federal Way.
Site is to supposed to be paved before the end of the month. Will follow up this week after rainfall.
|
BMP Violation | 10/4/2018 | 10/4/2018 | 10/4/2018 | A | FAIL |
Andy J. Long
|
|
|
No construction entrance or designated access for deliveries or employee parking. Need to designate a parking area and location for heavy duty construction entrance. Currenly parking in dirt/mud along shoulder of road.
|
General Inspection | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Michael Zawacki
|
|
|
Building pad and walls complete. Water wagon on site and being used. Site is clean. Alta is on edge of federal way doing trench work.
|
General Inspection | 8/20/2018 | 8/21/2018 | 8/21/2018 | A | PASS |
Michael Zawacki
|
|
|
Working on building pads. Multiple washouts on site, secondary containmnet for diesel/form oils. Water wagon on site. Workers parking mostly off site, no dust issues.
|
Site Preparation | 8/6/2018 | 8/21/2018 | 8/20/2018 | P | CANC |
Andy J. Long
|
|
|
data entry error
|
General Inspection | 8/6/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Andy J. Long
|
|
|
Site grading completed, now working on foundation and should be vertical soon. No trackout, fugitive dust, or other violations observed.
|
General Inspection | 5/10/2018 | 5/10/2018 | 5/10/2018 | P | PASS |
Michael Zawacki
|
|
|
Site grading underway. Entrances are built, water truck on site. Some dust is being kicked up by front end loader near haul road and stockpile area. Weekly site inspections are being done by Specialty Supply.
|