Permit Information
Permit NumberESC18-00692
StatusIssued
Name CECIL WILCOMB
Site Address 807 N 8TH ST
Project NameSt John's Catherdral
Customer Number 
ePlanReviewNo
Description
-(ST. JOHNS CATHEDERAL) Replacement of 8th Street Stairs of the existing church
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final7/6/20207/6/20207/7/2020PNR
DetailsMichael Zawacki
Still some fence and pot o pottie at site.
Aging Inspection7/6/20207/6/20207/6/2020 CANC
DetailsAndy J. Long
Aging Inspection5/4/20205/4/20205/4/2020 PASS
DetailsMichael Zawacki
Crew on site doing stone caps around steps and welding on hand railings.
No cutting or grinding, no issues.
Aging Inspection3/2/20203/2/20203/3/2020 PASS
DetailsMichael Zawacki
Aging Inspection12/30/201912/30/201912/30/2019 PASS
DetailsMichael Zawacki
All work looks completed. Plywood still installed on top by railings, small storage area still fenced off.
Aging Inspection10/28/201910/28/201910/28/2019 PASS
DetailsAndy J. Long
Stairs complete, area on 8th street used for staging has been cleaned. WIP on railing and finishing touches. No correcitons requested.
Aging Inspection8/26/20198/26/20198/27/2019 PASS
DetailsMichael Zawacki
No workers at time of inspection. Stairs and wall completed. Wood forms installed at level where hand rails will go.
General Inspection6/25/20196/25/20196/26/2019 PASS
DetailsAndy J. Long
WIP. Daily cleaning of work area. Okay for cutting water to be contained in gutter in front of work and allowed to dry. No wet weather cutting or allowing water to leave the contained area directly in front of steps.
General Inspection4/22/20194/23/20194/26/2019PPASS
DetailsAndy J. Long
Work area is clean. No slrurry in gutter. Gutter beyond work area has been swept. No corrections.
General Inspection4/16/20194/17/20194/22/2019PCANC
DetailsAndy J. Long
General Inspection4/11/20194/11/20194/16/2019PPEND
DetailsAndy J. Long
Crews still saw cutting. Covered staging area not yet set up. Observed end of day clean of slurry in gutter with wet vac. Follow up scheduled.
Conference4/10/20194/10/20194/11/2019PDONE
DetailsAndy J. Long
Conducted with RP Cecil. Stone cutting operation getting slurry into gutter. Drains to storm drain around the corner at Fort and 9th.

-Request to clean up staging and material storage.
- Make designated cutting area surrounded by berm.
- Collect slurry water for settling in a container
- Clean gutter after each day
- Remove materials no longer need.
- Cover area with tarp or pop up tent.
BMP Violation4/10/20194/10/20194/10/2019PFAIL
DetailsAndy J. Long
Dirty stagy and work area. Gutter drains to storm drain inlet on 9th Street, no inlet protection.

pH of murky stone cutting water is 10.4, should not be higher than 9th.

Need to remove or cover all materials. Clean up staging area. Install inlet protection. Clean up mud and sand in gutter. Suck up water pooling in gutter and place in containment for evaporation or disposal.
Complaint Inspection3/18/20193/18/20193/25/2019PPEND
DetailsAndy J. Long
issued verbal correction request to contain slurry from brick cutting dust control. Needs to be contained and filtered as much as practicable before flowing to gutter.
General Inspection11/16/201811/16/201811/19/2018PPART
DetailsMichael Zawacki
All work on 8th street side of church, material being stored in parking lot across Hayes. Hosing down sandstone dust and washing into gutter, gator guard in place. Will need to watch off site flow and clean gutters.
General Inspection8/13/20188/14/20188/15/2018APASS
DetailsAndy J. Long