[St. Luke's Children Pavilion]
The fire sprinkler scope of work consists of a medical office building with three levels of parking underground and five levels above ground. There is also a roof plaza and a sky bridge to the existing hospital. The three levels of parking are dry pipe systems and the five levels above ground are wet systems. The water supply is from a 6" city connections and a fire pump rated at 500 gpm @ 70 psi. There is a manual wet standpipe system consisting of two standpipes supplied from the FDC. The three dry systems utilize a nitrogen generator. Each floor has a loop design.

• The Steel and Concrete is under permit BLD17-00090.
• The TI portion is under permit BLD17-02757.
• The underground is under permit FIR18-00117.
• The project is under two different parcels.

[BLD17-02757, BLD17-00090]
This permit if for the construction of the Sky Bridge and tenant building out for the 3 story below grade parking garage and 4 story medical office with an occupied roof. Scope of work includes tenant improvement build out, envelope, sky bridge, mechanical, electrical, plumbing and fire systems. This project consists of multiple permits including BLD17-00090 Structural Steel and Concrete, GRD16-00070 Shoring, Grading, Drainage and Site Utilities.

Alternative Materials and Methods:

• There are no AMM at this time. However, the building review is not finished.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/16/20195/17/20195/17/2019PPASS
DetailsJim Page
Final fire sprinkler inspection complete.

Justin Phone #: ###-####
INSP-Conference5/2/20195/3/20195/3/2019ADONE
DetailsTroy Cobbley
We spoke about cordination of Vesda inspection and final sprinkler inspecton in regards to ceiling tile installation. Project walk, expectations for close out // Justin Phone #: ###-####
INSP-Final Inspection4/5/20194/9/20194/9/2019APART
DetailsJim Page
All fire alarm components associated with the fire sprinkler system has been tested, all devices tested satisfactorily.

THIS IS AN ALARM FINAL SO IT WILL TAKE A COUPLE HOURS.
WE WILL CALL IN ANOTHER FINAL LATER WHEN ALL THE CEILING TILES ARE IN. Phone #: ###-#### Inspection requested via web by Brad Bettencourt
INSP-Sprinkler Rough-in/Hydro4/8/20194/8/20194/8/2019PCANC
DetailsJim Page
INSP-Sprinkler Rough-in3/27/20193/27/20193/27/2019PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on levels 4 and 5 complete, approved for cover. All rough to cover inspections complete.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro3/27/20193/27/20193/27/2019PDONE
DetailsJim Page
Hydrostatic test for east side standpipe, level 4 and level 5 to include penthouse witnessed, no pressure loss observed.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in3/21/20193/22/20193/22/2019PCANC
DetailsJim Page
Time trip tests for LL3, LL2 dry systems. Please call Jeff with time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in3/13/20193/14/20193/14/2019PPART
DetailsJim Page
Rough to cover inspection for the remaining overhead fire sprinkler piping on level 3 complete, all of level 3 approved for cover. Overhead fire sprinkler piping above hardlids next to sky bridge inspected, piping above hardlids in inspected areas approved for cover.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro3/13/20193/14/20193/14/2019PDONE
DetailsJim Page
Hydrostatic test for three dry systems witnessed, no pressure loss observed.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in3/6/20193/7/20193/7/2019PPART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 3 complete, notated city approved drawings with areas approved for cover. Remaining sprinkler piping on level 2 inspected, all of level 2 approved for cover.

JUSTIN Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro3/6/20193/7/20193/7/2019PPART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 3 witnessed, no pressure loss observed.

JUSTIN Phone #: ###-####
INSP-Sprinkler Rough-in3/4/20193/5/20193/5/2019PPART
DetailsJim Page
Fire pump commissioning complete.

fire pump test // justin Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro2/22/20192/22/20192/22/2019PPART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 2 witnessed, no pressure loss observed.

INSP-Sprinkler Rough-in2/21/20192/22/20192/22/2019APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete, notated city approved drawings with red in areas approved for cover.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro2/20/20192/21/20192/21/2019APART
DetailsJim Page
Hydrostatic yesy for pump room, west standpipe and level 1 witnessed, no pressure loss observed.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in12/11/201812/12/201812/12/2018APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings on level 1 with yellow highlighter/red ink areas approved for cover.

Justin Phone #: ###-####
INSP-Sprinkler Rough-in11/6/201811/7/201811/7/2018APASS
DetailsTroy Cobbley
See the city approved plans for the area in the lower level of the parking garage where piping is ok for cover.

cover // Justin Phone #: ###-####
INSP-Sprinkler Rough-in10/31/201810/31/201810/31/2018PPART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping above hardlid on 1st lower parking level complete, overhead fire sprinkler piping at base of ramp on 1st lower level approved for cover.

of Justin Phone #: ###-####
INSP-Sprinkler Rough-in9/12/20189/13/20189/13/2018APASS
DetailsAdele J Schaffeld-Griffin
Inspection Comments from Forrest-Overhead rough in approved for cover at first floor sheetrock ceilings per plan annotations. Refer to stamped plan set, sheet FP8 for locations and dated remarksTHIS IS A ROUGH IN FOR HARD LIDS ON 1st FLOOR.
TOM SMALL IS OUR SITE CONTACT Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt
INSP-Sprinkler Rough-in8/29/20188/30/20188/30/2018APASS
DetailsTroy Cobbley
See the city approved plans for 2nd floor locations (clouds) where sprinkler piping can be covered. Marked "OK" in red.


Justin Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro8/14/20188/16/20188/16/2018APASS
DetailsJim Page
24 hour air test complete for dry systems in fire pump room.

JUSTIN IS OUR CONTACT
THIS IS TO FINISH THE (3) 24 HOUR AIR TEST FOR THE DRY SYSTEMS IN THE PARKING LEVELS Phone #: ###-#### Inspection requested via web by Brad Bettencourt
INSP-Sprinkler Rough-in8/15/20188/15/20188/15/2018PPART
DetailsJim Page
Rough in inspection for overhead fire sprinkler piping in parking garage levels B3, B2, and B1 to include level 1 wet system.
INSP-Sprinkler Rough-in/Hydro8/14/20188/15/20188/15/2018APART
DetailsJim Page
24 hour air test started at 11AM with 41 PSI on each system.

JUSTIN IS OUR CONTACT