INSP-Final Inspection | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Mike Martin is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/30/2019 | 5/31/2019 | 5/31/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test after install of dry uprights witnessed, no pressure loss observed.
Mike Martin is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 5/2/2019 | 5/2/2019 | 5/2/2019 | P | DONE |
Troy Cobbley
|
|
|
I spoke to the building contractor about requirements for heat for the wet pipe system above the office.The contact is Cade. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 4/26/2019 | 4/29/2019 | 4/30/2019 | P | DONE |
Troy Cobbley
|
|
|
Jon and I discussed the requirements for heat tor the wet pipe system above the ceilings in the aoffice area. After a discussion with the fire dept I let Jon know the if direct heat is not provided or insulation provided that heat transfer calculations will be required from a registered engineer.
Jon Beazer is requesting a consult for this project. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection substantially complete, fire alarm components have been tested and verified with central station , remaining items for fire sprinkler completion is providing fire sprinkler in area where old paint booth is going to be removed. Permit will remain in issued status until all sprinkler work is completed.
Austin Farnworth is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/12/2019 | 4/16/2019 | 4/16/2019 | A | CANC |
Troy Cobbley
|
|
|
The fire alarm permit did not get called in for inspection.
Jim Baker is the contact for this final inspection. We are trying to coordinate with Crane Alarm. We are hoping for a 12:30 time slot. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | PART |
Jim Page
|
|
|
Previously noted items have been corrected, rough in inspection for scope of work sudstantially complete, a follow up inspection will be required when existing paint booth is removed and fire sprinklers are provided.
|
INSP-Sprinkler Rough-in/Hydro | 4/11/2019 | 4/12/2019 | 4/12/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Jim Baker is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/11/2019 | 4/12/2019 | 4/11/2019 | A | CANC |
Jim Page
|
|
|
Jim Baker is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | FAIL |
Jim Page
|
|
|
Provide fire sprinkler in entry that was enclosed between buildings. Provide freeze protection for main and heads between buildings, doorway was enclosed, no heating in area between buildings. Include extra 6 inch 90 on riser main to duct heads that is not shown on the city approved drawings. Install missing retaining straps. Remove cover material in office area that was installed. Provide city approved drawings for remaining building, not just the paint booth. Install high temperature heads that are above heaters. Heads next to old paint booth wall are over 9 foot from wall as well as heads outside of old paint booth entry, heads a over 8 foot off of wall, heads are overspaced. Install flexible vic couplings on risers/riser nipples where required throughout sprinkler system.
Jim Baker is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in paint-booth itself is complete, overhead filters can be placed, no use of the paint booth is authorized until final inspections are complete.
Jeff Chaney is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/28/2019 | 3/4/2019 | 3/4/2019 | P | FAIL |
Jim Page
|
|
|
Office fire sprinkler piping does not match city approved drawings. 2 inch teardrop hangers on 4 inch main trapeze needs to be changed to the correct heavy duty type hangers. Hanger attachment in pit under paint booth does not match any of the submitted attachment methods. Provide fire sprinklers under overhead doors by paint booth. Verify added 90's on 6 inch will work with calcs. Add fire sprinklers btween paint booth and main building, no sprinklers in mentioned area at time of inspection and buildings are connected. Provide and submit heat calculations to verify upright heads will not freeze in attic space and area between main building and paint booth.
Austin Farnsworth is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/28/2019 | 3/4/2019 | 2/28/2019 | A | CANC |
Jim Page
|
|
|
Austin Farnsworth is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2019 | 2/28/2019 | 2/28/2019 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test witnessed with no visible loss of pressurel. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2019 | 2/28/2019 | 2/27/2019 | A | CANC |
Jim Page
|
|
|
Austin Farnsworth is the contact for this hydro only. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|