INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PASS |
Thomas Walsh
|
|
|
Completed fire alarm testing today, including a full test of the 5th floor corridors, and units. Records of Completion paperwork filled out, signed off and submitted to the office. NOTE: Some work in the building continues, that may cause dust (cleaning, sweeping, etc.). Contractor was advised to take necessary steps to prevent false alarms.
|
INSP-Alarm Testing | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | PART |
Thomas Walsh
|
|
|
Completion of fire alarm testing for floors P/G up to the 4th floor. Tested two atic DP valves to ensure tied into exterior bell - OK Tested Elevator # 1 recall, shunt trip, and activation of 5th floor smoke guard door - all tested OK. Retested two (2) strobe devices in P/G that did not work last test - tested OK This test completes fire alarm system, up through the fourth floor.
|
INSP-Alarm Testing | 8/16/2015 | 8/16/2015 | 8/16/2015 | P | PART |
Thomas Walsh
|
|
|
Continued testing of fire alarm system, following troubles encountered last inspection. Tested all floors general alarm and individual units for all floors - all tested satifactorily. Tested notification in parking garage - found two strobe units that were not operating. Tested 5th floor common areas - units not ready for testing. Elevator #1 5th floor SDs, and HD not tested - problem with smoke guard unit. Dry pipe valves on the 5th floor need to be tested to confirm ext. bell is connected. Confirmed off site monitoring and receipt of alarms - also proper address confirmed. Fire alarm system is complete up to the 4th floor, except as noted above.
|
INSP-Final Inspection | 8/15/2015 | 8/15/2015 | 8/15/2015 | P | PART |
Thomas Walsh
|
|
|
Fire alarm test for River's Edge Apts. All fire sprinkler systems (dry and wet), tested, including water flow, tampers, trip test of dry pipe valves, low air alarms, etc. All fire sprinkler systems tested satisfactorily. ested other initiating devices for elevator functions - recall, alt. recall shunt trip for both elevators. Elev. # 1 could not verify shunt trip - no access to heat detector. Tested MP, and other SDs for door holders, SFDs, etc. Noted a circuit problem with unit sounders not sounding. Contractor agreed to troubleshoot before resuming testing. NOTE: Parking garage notification not tested this visit.
|
INSP-Final Inspection | 8/13/2015 | 8/14/2015 | 8/14/2015 | A | CANC |
Thomas Walsh
|
|
|
Fire alarm testing not performed today. The contractor needed time to hunt down a few ground faults and other trouble signals that were on the FACP. Fire sprinklers were being put into service throughout the day. By the end of the day, all GFs and troubles were cleared, and the final dry pipe system was being put on line. Contrator agreed to pretest what he could before our inspection tomorrow (8/15).
|
INSP-Final Inspection | 8/13/2015 | 8/13/2015 | 8/13/2015 | P | CANC |
Thomas Walsh
|
|
|
Talked to alarm contractor and told him that we cannot start fire alarm testing, until fire sprinkler systems (dry and wet) are ready for testing, which should be another day or so as hydrotesting and air testing of systems is currently being performed. If all the hydrotests and air test pass without problems, then the sprinklers can be made ready for flow testing, tampers, trip test of DP valves, etc.
|
INSP-Final Inspection | 8/12/2015 | 8/13/2015 | 8/13/2015 | A | CANC |
Thomas Walsh
|
|
|
As early as possible Phone #: 2089414511 >> Inspection requested via mobile web by Nathan Price Inspection cancelled via mobile web on Thursday, August 13, 2015.
|
INSP-Conference | 1/20/2015 | 1/20/2015 | 1/22/2015 | P | DONE |
Forrest France
|
|
|
On site conference with contractor regarding SA locations at living units, NFPA 72 guidelines, plan review comments, and two way communication per IBC requirements.
|
Permit Ready to Issue | | | 12/11/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/11/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/11/2014 | | 12/11/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 12/10/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 12/10/2014 | | 12/10/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/10/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Application received | | | 12/9/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 9 2014 9:50AM
|
Plan assigned to (Lee) | 12/9/2014 | | 12/9/2014 | | DONE |
Lee G Meredith
|
|
|
|